United States of America for the Use and Benefit of Control Systems, Inc. v. Arundel Corporation

896 F.2d 143, 1990 WL 17178
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 11, 1990
Docket89-4289
StatusPublished
Cited by3 cases

This text of 896 F.2d 143 (United States of America for the Use and Benefit of Control Systems, Inc. v. Arundel Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America for the Use and Benefit of Control Systems, Inc. v. Arundel Corporation, 896 F.2d 143, 1990 WL 17178 (5th Cir. 1990).

Opinion

CLARK, Chief Judge:

I.

This suit involves various claims between the prime contractor, a subcontractor, and one of the subcontractor’s materialmen on Lock B of the Tennessee-Tombigbee Waterway Project in Smithville, Mississippi. The suit was originally instituted by the materialman for breach of contract and for payment on the prime contractor’s Miller Act bond. See 40 U.S.C. §§ 270a to 270d. This is the second appeal which has been taken in this action. The district court in its latest decision dismissed the prime contractor’s counterclaims against the materi-alman for delay damages. We affirm.

II.

A. Background.

In 1978, the Arundel Corporation, Guy F. Atkinson Company, and Gordon H. Bell, Inc., d/b/a/ Dillingham Heavy Construction, Inc. as joint venturers (Arundel) contracted with the Army Corps of Engineers (the Corps) to construct Lock B of the Tennessee-Tombigbee Waterway Project in Smithville, Mississippi. Arundel, as prime contractor, subcontracted with Lar Electric, Inc. (Lar) to perform certain electrical, instrumentation, control, and communications work on the project. Lar in turn contracted with Control Systems, Inc. (Control) to supply various control and electrical power systems. The Lar-Control contract incorporated the relevant specifications contained in the prime contract.

On April 25, 1979, the Corps issued Change Order Request No. C-21 to Arun-del. The Change Order required extensive modification of the Supervisory Control and Data Acquisition (SCADA) system which Control had contracted to supply to Lar. After conducting negotiations with all of the affected parties, the Corps on November 5, 1980 issued Arundel a Notice to Proceed on C-21, which Arundel subsequently delivered to Lar. Lar did not deliv *145 er the notice to Control until May 3, 1981. As a result, Control was delayed in completing its work on the SCADA system, and Arundel incurred increased overhead expenses on the project. The Corps also assessed liquidated damages against Arundel for reasons unrelated to the SCADA system.

In an effort to recoup its losses, Arundel withheld $89,263 due to Lar under the subcontract, claiming Lar was responsible for the delays and the liquidated damages. Lar in turn refused to pay Control $132,747 due under the Lar-Control contract, contending that Control was at fault.

B. Prior Proceedings.

Control filed an action against Lar for breach of contract and joined Arundel and its sureties on a claim under the Miller Act. The Miller Act allows labor and material-men to sue on the payment bond required of all prime contractors on federal construction projects. See 40 U.S.C. §§ 270a(a)(2), 270b. Lar and Arundel responded with counterclaims against Control and crossclaims against each other. The case was tried to the district court.

The court determined that Lar and Arun-del were liable to Control for $132,747, plus costs and interest. The court also awarded Lar the $89,263 due from Arundel under the subcontract and found that neither Control nor Lar was responsible for the liquidated damages assessed against Arun-del. The court dismissed the parties’ counterclaims against Control, finding that Control had performed within a reasonable time. The court also dismissed Arundel’s crossclaims against Lar, reasoning that Arundel was at fault for the delays because it failed to request a time extension from the Corps after receiving Change Order C-21. Lar and Arundel appealed.

On appeal, this court concluded in relevant part that Lar and not Arundel was responsible for requesting a time extension from the Corps and that Lar was liable for Arundel’s increased overhead expenses. We also determined that Lar was obligated to indemnify Arundel against Control’s Miller Act claim. United States ex rel. Control Systems, Inc. v. Arundel Corp., 814 F.2d 193, 196-97 (5th Cir.1987).

We further determined that Control’s time of performance under the Lar-Control contract was fourteen to twenty weeks and not a “reasonable time” as the district court had concluded. Id. at 198. We therefore remanded the parties’ counterclaims against Control for its alleged untimely performance of the Lar-Control contract. Id. at 200. On petition for rehearing, we concluded it was unnecessary to remand Lar’s counterclaims against Control because those claims were barred by Lar’s failure to timely notify Control of the alleged breach of contract. We expressed no opinion as to the legal or factual merits of Arundel’s counterclaims against Control. United States ex rel. Control Systems, Inc. v. Arundel Corp., 826 F.2d 298, 299 (5th Cir.1987) (per curiam).

C. The Present Proceedings.

On remand, the district court dismissed Arundel’s counterclaims against Control concluding that Arundel had no right of recovery in either tort or contract. The court reaffirmed Lar’s liability to Arundel for its increased overhead expenses and calculated Arundel’s damages to be $135,-479. The district court disallowed various suggested modifications to this amount, including Arundel’s claim to a ten percent profit markup. The parties concede that Lar is insolvent.

Arundel now appeals, asserting two theories to support its counterclaims against Control. Arundel claims to be a third-party beneficiary of the Lar-Control contract entitled to recover for Control’s alleged untimely performance. Arundel’s alternative contention is that Control is liable to Arun-del on a theory of negligence. Arundel also asserts that the district court erred in calculating its delay damages. We affirm the dismissal of Arundel’s counterclaims against Control and modify and affirm the district court’s determination of Arundel’s delay damages.

III.

A. Arundel’s Third-Party Beneficiary Claim.

The Mississippi Supreme Court has established the following analysis for de *146 termining whether a non-party to a contract is a third-party beneficiary of the contract entitled to sue for its breach:

(1) When the terms of the contract are expressly broad enough to include the third party either by name [or] as one of a specified class, and (2) the said third party was evidently within the intent of the terms so used, the said third party will be within its benefits, if (3) the prom-isee had, in fact, a substantial and articulate interest in the welfare of the said third party in respect to the subject of the contract.

Mississippi High School Activities Ass’n v. Farris, 501 So.2d 393, 396 (Miss.1987) (quoting Yazoo & M.V.R. Co. v. Sideboard, 161 Miss. 4, 133 So. 669, 671 (1931)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Woodring v. Robinson
892 F. Supp. 2d 769 (S.D. Mississippi, 2012)
Work v. Cmercl Underwriters
Fifth Circuit, 2003

Cite This Page — Counsel Stack

Bluebook (online)
896 F.2d 143, 1990 WL 17178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-control-systems-inc-ca5-1990.