United States of America, for and on Behalf of Taylor & Polk Construction, Incorporated v. Mill Valley Construction, Incorporated, as Principal Hartford Fire Insurance Company, as Surety, United States of America, for and on Behalf of Taylor & Polk Construction, Incorporated v. Mill Valley Construction, Incorporated, as Principal Hartford Fire Insurance Company, as Surety

29 F.3d 154, 39 Cont. Cas. Fed. 76,684, 1994 U.S. App. LEXIS 17013
CourtCourt of Appeals for the Fourth Circuit
DecidedJuly 12, 1994
Docket92-2096
StatusPublished

This text of 29 F.3d 154 (United States of America, for and on Behalf of Taylor & Polk Construction, Incorporated v. Mill Valley Construction, Incorporated, as Principal Hartford Fire Insurance Company, as Surety, United States of America, for and on Behalf of Taylor & Polk Construction, Incorporated v. Mill Valley Construction, Incorporated, as Principal Hartford Fire Insurance Company, as Surety) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for and on Behalf of Taylor & Polk Construction, Incorporated v. Mill Valley Construction, Incorporated, as Principal Hartford Fire Insurance Company, as Surety, United States of America, for and on Behalf of Taylor & Polk Construction, Incorporated v. Mill Valley Construction, Incorporated, as Principal Hartford Fire Insurance Company, as Surety, 29 F.3d 154, 39 Cont. Cas. Fed. 76,684, 1994 U.S. App. LEXIS 17013 (4th Cir. 1994).

Opinion

29 F.3d 154

39 Cont.Cas.Fed. (CCH) P 76,684

UNITED STATES of America, for and on behalf of TAYLOR & POLK
CONSTRUCTION, INCORPORATED, Plaintiff-Appellant,
v.
MILL VALLEY CONSTRUCTION, INCORPORATED, as Principal;
Hartford Fire Insurance Company, as Surety,
Defendants-Appellees.
UNITED STATES of America, for and on behalf of TAYLOR & POLK
CONSTRUCTION, INCORPORATED, Plaintiff-Appellee,
v.
MILL VALLEY CONSTRUCTION, INCORPORATED, as Principal;
Hartford Fire Insurance Company, as Surety,
Defendants-Appellants.

Nos. 92-2096, 92-2127.

United States Court of Appeals,
Fourth Circuit.

Argued May 3, 1993.
Decided July 12, 1994.

ARGUED: Claron A. Robertson, III, Robertson & Sinkler, Charleston, SC, for appellant. Leonard Rose, Rose, Brouillette & Shapiro, P.C., Kansas City, MO, for appellees. ON BRIEF: Therese Trouche Smythe, Robertson & Sinkler, Charleston, SC, for appellant. Michael J. Plambeck, Rose, Brouillette & Shapiro, P.C., Kansas City, MO, for appellees.

Before WIDENER and HAMILTON, Circuit Judges, and MICHAEL, United States District Judge for the Western District of Virginia, sitting by designation.

Affirmed in part, reversed in part, and remanded with instructions by published opinion. Judge WIDENER wrote the opinion, in which Judge HAMILTON and Judge MICHAEL joined.

OPINION

WIDENER, Circuit Judge.

Taylor and Polk Construction, Inc. (T & P) brought a breach of contract action pursuant to the Miller Act, 40 U.S.C. Secs. 270a & 270b, against Mill Valley Construction, Inc. (Mill Valley) for payments due on labor and materials it supplied during a construction project at Charleston Air Force Base in South Carolina. The district court set aside a $443,088.00 jury verdict for T & P because it found that damages had not been proven with the requisite certainty under state law. Because we are of the opinion that the method of proving damages was adequate and the damage instruction given was, under the facts of this case, at least as favorable as a proper instruction, we reverse for entry of judgment on the verdict. We affirm the denial of the defendants' motion for a new trial.I. Facts

On or about July 12, 1988 Mill Valley contracted with the United States Department of the Air Force (Government) to be the general contractor for the renovation of family housing units on Charleston Air Force Base in South Carolina. As required by the Miller Act, 40 U.S.C. Sec. 270a(a)(2), Mill Valley secured a payment bond for the benefit of those supplying materials and labor.1 On September 27, 1988 Mill Valley subcontracted with T & P to do a large portion of the work. The parties agreed to a contract under which T & P would be paid $1,739,276 for performance of the work, subject to additions and modifications by Change Order, on approximately 186 housing units of various types as shown on the "SCHEDULE OF UNIT TYPES, COSTS, AND ESTIMATED UNITS" (Schedule of Costs).2 The Schedule of Costs listed the total cost of each type of housing unit. This total cost had been calculated according to a handwritten sheet entitled "Schedule of Values" which broke down each type of housing unit by the estimated costs for the particular type of work to be performed (patios, roofing, painting, etc.).3

Under the contract monthly progress payments were to be made based on valuation of work done.4 Although the contract indicates that valuation would be determined by percentage of each total unit completed, both parties testified that T & P actually submitted payment applications (bills) listing the estimated percentage of work completed on each unit by type of work performed. The Government's inspector approved each submission before payment. Although the contract generally provided that Mill Valley would pay T & P within 10 working days from payment by the Government, an explicit provision also stated that T & P would receive payment "on demand" regardless of payment by the Government.5

From its inception in October 1988, the project was plagued by work change orders, construction delays, and general disagreement over the type and quality of work to be performed. Mill Valley ultimately requested the removal of the Government project inspector in August 19896 and terminated T & P November 16, 1989. However, delay and inspection problems continued and the project was not completed until December 1990, a year after the scheduled completion with an increase in contract price for Mill Valley of $367,000.00.

On May 17, 1990, T & P filed this action in district court against Mill Valley and its surety, Hartford Fire Insurance Company, seeking payment under the Miller Act, 40 U.S.C. Secs. 270a and 270b, for materials and labor it had provided in performance of the contract and for breach of contract. T & P alleged that Mill Valley breached the contract when it wrongfully terminated T & P for nonperformance which Mill Valley had proximately caused by failing to pay all amounts due to T & P in a timely manner, refusing to accept work tendered by T & P in accordance with its subcontract, directing T & P to perform work in excess of its subcontract obligations and then refusing to compensate it, and unilaterally modifying the scope of work required of T & P pursuant to the subcontract, thus impairing T & P's ability to perform. T & P alleged that it suffered approximately $700,000, as a direct consequence of the wrongful termination and breach. Trial testimony established the following.

T & P began work on or about October 6, 1988 and submitted its first payment application for renovations on the first few houses at the end of the month. There was a change order even for the first few houses. Mill Valley did not make payment until December 7, 1988, but that lateness was not accounted for much of the time. Upon inspection of the units, the Government decided that additional electrical pole work would need to be done on these and all subsequent units.7 Although both parties agreed that such work was not contemplated in the original contract, Mill Valley directed T & P to proceed, said it would file a change order with the Government contracting officer, and assured T & P that it would be paid for the additional work. The parties agree that at several later stages of construction Mill Valley asked T & P to perform additional work which was not specified in the original contract. A large additional expense, for example, was the wiring and hookup of approximately 160 overhead electrical service poles mentioned above. T & P was also asked to redo painting and switch from latex to oil-based paint, relocate the air conditioning units, skim-coat sheetrock, replace kitchen light fixtures with more expensive fluorescent light fixtures, perform extra brick and demolition work, install flooring and pipe insulation, and change plastic wall boxes to metal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
29 F.3d 154, 39 Cont. Cas. Fed. 76,684, 1994 U.S. App. LEXIS 17013, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-and-on-behalf-of-taylor-polk-construction-ca4-1994.