United States of America, City of Louisville, Intervening v. Louisville and Jefferson County Metropolitan Sewer District, Commonwealth of Kentucky

983 F.2d 1070, 1993 U.S. App. LEXIS 5186, 23 Envtl. L. Rep. (Envtl. Law Inst.) 20
CourtCourt of Appeals for the Sixth Circuit
DecidedJanuary 12, 1993
Docket91-6461
StatusUnpublished
Cited by1 cases

This text of 983 F.2d 1070 (United States of America, City of Louisville, Intervening v. Louisville and Jefferson County Metropolitan Sewer District, Commonwealth of Kentucky) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, City of Louisville, Intervening v. Louisville and Jefferson County Metropolitan Sewer District, Commonwealth of Kentucky, 983 F.2d 1070, 1993 U.S. App. LEXIS 5186, 23 Envtl. L. Rep. (Envtl. Law Inst.) 20 (6th Cir. 1993).

Opinion

983 F.2d 1070

36 ERC 1465, 23 Envtl. L. Rep. 20,815

NOTICE: Sixth Circuit Rule 24(c) states that citation of unpublished dispositions is disfavored except for establishing res judicata, estoppel, or the law of the case and requires service of copies of cited unpublished dispositions of the Sixth Circuit.
UNITED STATES of America, Plaintiff-Appellee,
City of Louisville, Intervening Plaintiff-Appellee,
v.
LOUISVILLE AND JEFFERSON COUNTY METROPOLITAN SEWER DISTRICT,
Defendant-Appellant,
Commonwealth of Kentucky, Defendant-Appellee.

No. 91-6461.

United States Court of Appeals, Sixth Circuit.

Jan. 12, 1993.

Before MERRITT, Chief Judge, and RALPH B. GUY, Jr. and RYAN, Circuit Judges.

RALPH B. GUY, Jr., Circuit Judge.

Defendant, Metropolitan Sewer District, appeals the district court's order terminating a 1981 consent decree. On appeal, defendant argues that the purpose of the consent decree has not been achieved and therefore the court should not have terminated the decree. We agree with the district court that the purpose of the consent decree has been accomplished and therefore affirm.

I.

Louisville and Jefferson County Metropolitan Sewer District (MSD) was created pursuant to enactments of the Kentucky Legislature, Ky.Rev.Stat. § 76.010, to develop and operate a sanitary and storm sewer system in Jefferson County, Kentucky. In the late 1970s, defendant contracted with Blount Brothers to build the Morris-Foreman Waste Water Treatment Plant (MFWTP), which was completed in 1974. The design plans, approved by the Environmental Protection Agency, anticipated sewage flow of 105 million gallons per day. MFWTP was issued a National Pollutant Discharge Elimination System (NPDES) permit by the EPA in 1977 pursuant to applicable provisions of the Clean Water Act. This permit required MSD to meet specific effluent limitations for biochemical oxygen demand (BOD) and total suspended solids (TSS). Unfortunately, substantial defects in design caused the plant's effluent to exceed its permit limits. Major litigation ensued between MSD and Blount Brothers, resulting in a multi-million dollar settlement. However, MSD was still faced with a plant that was not complying with its permit requirements.

In April 1978, the EPA brought an enforcement action against MSD for violating the plant's permit. MSD faced civil penalties of $10,000 per day for violating its permit. 33 U.S.C. § 1319(d) (1986). Over the next two years, the parties came to an agreement, memorialized in a "Memorandum of Understanding," and entered into a consent decree. According to appendix A of the consent decree, MSD was to undertake two steps to bring the plant into compliance with its permit. MSD was to conduct an "Interim Corrective Action Program" to ascertain if limited improvements to the plant could bring about compliance with applicable effluent limitations and an "Evaluation Program" to determine the relative feasibility and economic efficiency of alternative improvements. If these steps showed that the MFWTP could not achieve compliance with applicable effluent limitations without major physical modifications, then MSD was to submit a "Final Plan and Schedule" detailing the major physical modifications and equipment modification required. According to the consent decree, "[u]pon approval by EPA Region IV, MSD shall carry out that Final Plan and Schedule." (App. 62). The agreement also established those items EPA would fund and would not fund, those items the parties disagreed on funding, and those items the EPA felt were eligible for funding but would not approve unless shown to be necessary. The consent decree provided:

Although § 1319(d) of 33 U.S.C. provides that penalties may be sought for violation of applicable effluent limitations, EPA has elected not to seek such penalties in this instance in light of MSD's substantial efforts including both studies and physical work to correct the deficiencies which have prevented MFWTP from achieving applicable effluent limitations.

(App. 54).

MSD proceeded to undertake the actions required by the consent decree, completing the Interim Corrective Action Program and Evaluation Program. The Final Plan and Schedule was submitted to the EPA in 1984. One item MSD felt was needed was an additional UNOX reactor, also referred to as Battery D. The EPA disagreed with the necessity of this item. In 1985, the EPA approved the Final Plan and Schedule, except for the additional UNOX reactor.

While the various studies were being conducted, events were changing the volume and quality of the sewage coming into the plant. In 1981, a substantial portion of MSD's sewer system was destroyed by a series of explosions. Additionally, industrial sewage began to diminish in the area. Carl Neumayer, the director of operations and maintenance of MSD, stated in his affidavit:

As a result of the decrease in industrial sewage discharged into MSD's system, coupled with the Interim Corrective Actions undertaken by MSD in compliance with the Consent Decree, the quality of MSD's discharge effluent began to consistently meet the BOD and TSS effluent limitations set forth in MSD's EPA-issued discharge permit.

(App. 116). The parties agree that, from 1986 until 1989 and for several months in 1990, the plant was meeting the permit requirements. In July 1990, the EPA moved for a termination of the consent decree, "certif[ying] that the defendants have fully complied with the provisions of the Consent Decree." (App. 64).

In the meantime, in 1989, MSD had requested the EPA to re-evaluate the need for the additional UNOX reactor that the EPA omitted from its approval of the Final Plan and Schedule. Under the Clean Water Act, the EPA can give grants to assist the construction of wastewater treatment plants. 33 U.S.C. § 1281(g) (1986 & Supp.1992). But, under the complex procedures for grants, the EPA must wait until the state has certified a project and has determined that the project has priority over other works within the state. 33 U.S.C. § 1284(a)(3) (1986). On July 20, 1989, the EPA, following the established procedures for grants under the Clean Water Act, authorized the Commonwealth of Kentucky to review MSD's request for a re-evaluation of the need for the additional UNOX reactor. On August 17, 1990, after the EPA filed its motion for termination of the consent decree, MSD submitted a proposal for bioroughing towers, in lieu of the UNOX reactor, to the Commonwealth of Kentucky, arguing it was required because of additional sludge flows that were not included or anticipated in the development of the Final Plan. As Carl Neumayer explained in his affidavit:

MSD has been consistently expanding its sewer lines throughout Jefferson County in compliance with the mandate imposed by KRS 76.010 in order to accommodate area development, population expansion and public health needs. In addition, MSD has assumed responsibility for treating sewage previously treated by private package sewage treatment plants so as to eliminate discharge of inadequately treated sewage into Kentucky's waterways. In the last several years industrial discharges into MSD's sewer system have increased.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evoqua Water Techs. v. M.W. Watermark
940 F.3d 222 (Sixth Circuit, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
983 F.2d 1070, 1993 U.S. App. LEXIS 5186, 23 Envtl. L. Rep. (Envtl. Law Inst.) 20, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-city-of-louisville-intervening-v-louisville-and-ca6-1993.