United States of America, and Cross v. Earth Sciences, Inc., and Cross

599 F.2d 368, 9 Envtl. L. Rep. (Envtl. Law Inst.) 20542, 13 ERC (BNA) 1417, 1979 U.S. App. LEXIS 14485, 13 ERC 1417
CourtCourt of Appeals for the Tenth Circuit
DecidedMay 23, 1979
Docket77-1302, 77-1303
StatusPublished
Cited by148 cases

This text of 599 F.2d 368 (United States of America, and Cross v. Earth Sciences, Inc., and Cross) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, and Cross v. Earth Sciences, Inc., and Cross, 599 F.2d 368, 9 Envtl. L. Rep. (Envtl. Law Inst.) 20542, 13 ERC (BNA) 1417, 1979 U.S. App. LEXIS 14485, 13 ERC 1417 (10th Cir. 1979).

Opinion

LOGAN, Circuit Judge.

This is an appeal from a district court order dismissing a suit brought by the United States against Earth Sciences, Inc., (Earth Sciences) under the Federal Water Pollution Control Act (FWPCA), 33 U.S.C. § 1251 et seq., specifically § 1311.

The government appeals the district court’s conclusion that the FWPCA ex *370 empts all mining activities from point sources regulation. Earth Sciences cross-appeals, and defends the trial court’s decision on the alternative grounds that Earth Sciences’ overflows were not from a “point source,” the stream involved in this case was not a “navigable water” under the Act, no person made a “discharge” of the pollutant at issue here, and the government suit was precluded by a prior choice to pursue administrative remedies.

The events which gave rise to this action occurred at Earth Sciences’ gold leaching operation on the Rito Seco Creek in Costilla County, Colorado, and were stipulated by the parties. Gold leaching is a process whereby a toxic substance, here a sodium cyanide-sodium hydroxide water solution, is sprayed over a “heap” of gold ore, separating the gold from the ore. The leachate solution is then collected and the gold extracted for commercial sale. The center of Earth Sciences’ operation is a 3V2- to 4-acre pile of gold ore on top of an impermeable plastic membrane and 12 inches of sand constructed with a gradual slope, causing the leachate solution to funnel to one end into a small fiberglass-lined pool, called the primary sump. The solution is pumped from the primary sump into a processing trailer where the gold is removed, and then back onto the heap or into the primary sump. A 168,000-gallon reserve sump is available to catch excess leachate or runoff in emergency situations. The entire operation consists of several open excavations lined with plastic membrane, the processing trailer and pumps, all designed to be a closed system without any pollutant discharge.

Warm April temperatures caused faster melting than expected of a blanket of snow covering the heap, filling the primary and reserve sumps to capacity. This caused a one- to five-gallon-per-minute discharge of the sodium cyanide-sodium hydroxide leach-ate solution into the Rito Seco Creek for about a six-hour period. The solution is stipulated to be a pollutant under the FWPCA. Earth Sciences did not report the discharge to either state or federal environmental authorities.

A few days later the Colorado Division of Wildlife received a report of dead fish on the Rito Seco, causing a state inspector and two other wildlife employees to visit the Earth Sciences site. The inspector interviewed Earth Sciences employees and verified that a discharge had occurred. While the state employees were photographing and taking water samples of the operation, the reserve sump overflowed a second time, discharging approximately ten gallons per minute into the Rito Seco for two hours, until a bulldozer was used to construct a dirt berm around the edge of the- reserve sump to stop the flow. Within a week Earth Sciences constructed another reserve sump with an additional capacity of 398,000 gallons.

Because the FWPCA encourages use of approved state enforcement procedures, 33 U.S.C. §§ 1316(c) and 1319(a)(1), the Environmental Protection Agency (EPA) requested the Colorado Department of Health to act to prevent further discharges. The state notified Earth Sciences it had violated Colo.Rev.Stat. § 25-8-501 (1973), which requires a permit to discharge pollutants, and Colo.Rev.Stat. § 25-8-601(2) (1973), allowing for criminal penalties if a discharge is not reported. Colorado ordered Earth Sciences to cease and desist from further illegal discharges and to “perform any work necessary to prevent future unauthorized discharges” or stop its operation. Earth Sciences notified the Department of Health the newly-constructed reserve sump in combination with existing facilities would “accommodate 1.6 times as much water” as would fall on the heap in any 24-hour period, based on maximum rainfall statistics in the area since 1951. The state did not initiate any criminal prosecution.

Apparently the EPA decided the Colorado enforcement was insufficient and issued its own notice of violation and cease and desist order under 33 U.S.C. § 1319(a)(3), which reads as follows;

Whenever on the basis of any information available to him the Administrator finds that any person is in violation of *371 section 1311, ... he shall issue an order requiring such person to comply with such section or requirement, or he shall bring a civil action in accordance with subsection (b) of this section.

The EPA notice informed Earth Sciences the cyanide solution discharges violated 33 U.S.C. § 1311(a), because Earth Sciences had not applied for and been granted a permit to discharge pollutants under 33 U.S.C. § 1342. The notice identified an open ditch between the reserve sump and the Rito Seco Creek as a point source, defined in 33 U.S.C. § 1362(14) as

any discernible, confined and discrete conveyance, including but not limited to any pipe, ditch, channel, tunnel, conduit, well, discrete fissure, container, rolling stock, concentrated animal feeding operation, or vessel or other floating craft, from which pollutants are or may be discharged. This term does not include return flows from irrigated agriculture.

Contrasted with the state order, the EPA order was substantially more detailed and required Earth Sciences submit a plan to assure future discharges would not occur.

Five days after the EPA order was issued a sampling team of two EPA employees visited the Earth Sciences site. Groundwater seeps of approximately one gallon per minute were observed below the sumps running toward the Rito Seco and partially gathering into pools near the creek. Samples taken from two of these pools were found to contain cyanide.

Earth Sciences’ compliance with the EPA order reaffirmed the capacity of the reserve sump system against maximum recorded precipitation, and identified several steps Earth Sciences would take to divert the natural runoff away from the leaching facilities. Earth Sciences also assured the EPA it would monitor groundwater seeps around the sumps and the quality and quantity of the runoff.

Soon thereafter the United States filed suit, alleging Earth Sciences committed three separate violations of FWPCA, one each time the reserve sump overflowed and one as a result of the tests on the water collected from the groundwater seeps. All three violations were asserted under 33 U.S.C. § 1311(a).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northwest Environmental Defense Center v. Brown
640 F.3d 1063 (Ninth Circuit, 2011)
Greater Yellowstone Coalition v. Lewis
628 F.3d 1143 (Ninth Circuit, 2011)
Greater Yellowstone v. Lewis
Ninth Circuit, 2010
New Mexico Mining Ass'n v. Water Quality Control Commission
2007 NMCA 084 (New Mexico Court of Appeals, 2007)
NM Mining Assn. v. WATER QUALITY CONTROL
164 P.3d 81 (New Mexico Court of Appeals, 2007)
North Carolina Shellfish Growers Ass'n v. Holly Ridge Associates, LLC
278 F. Supp. 2d 654 (E.D. North Carolina, 2003)
Reynolds v. RUCK'S MUSHROOM SERVICE, INC.
246 F. Supp. 2d 449 (E.D. Pennsylvania, 2003)
Sierra Club v. El Paso Gold Mines, Inc.
198 F. Supp. 2d 1265 (D. Colorado, 2002)
American Wildlands v. Browner
94 F. Supp. 2d 1150 (D. Colorado, 2000)
Rice v. Harken Exploration Co.
89 F. Supp. 2d 820 (N.D. Texas, 1999)
Gill v. LDI
19 F. Supp. 2d 1188 (W.D. Washington, 1998)
Holbrook v. Devcon Enterprises, Inc., No. Cv-97-0567376-S (Dec. 31, 1997)
1997 Conn. Super. Ct. 12882 (Connecticut Superior Court, 1997)
Williams Pipe Line Co. v. Bayer Corp.
964 F. Supp. 1300 (S.D. Iowa, 1997)
Sierra Club v. Martin
71 F. Supp. 2d 1268 (N.D. Georgia, 1996)
United States v. Lambert
915 F. Supp. 797 (S.D. West Virginia, 1996)
Beartooth Alliance v. Crown Butte Mines
904 F. Supp. 1168 (D. Montana, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
599 F.2d 368, 9 Envtl. L. Rep. (Envtl. Law Inst.) 20542, 13 ERC (BNA) 1417, 1979 U.S. App. LEXIS 14485, 13 ERC 1417, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-and-cross-v-earth-sciences-inc-and-cross-ca10-1979.