United States Gypsum Co. v. Muszynski

161 F. Supp. 2d 289, 2001 U.S. Dist. LEXIS 13449, 2001 WL 1018353
District Court, S.D. New York·Decided August 31, 2001·No. 00 CIV 9700(JSR)·Published·Cited by 1 cases

Opinion

MEMORANDUM ORDER

RAKOFF, District Judge.

Plaintiff United States Gypsum Company (“USG”) seeks by this action to challenge the failure of the United States Army Corps of Engineers (“COE”) to issue a permit that would permit USG to dump sediment from a channel adjoining one of its plants into an ocean floor site designated to receive dredged material from the Port of New York (the “Site”). Concomitantly, plaintiff challenges a change in the criteria for issuing such a permit that was set forth in a Memorandum of Agreement between the COE and the United States Environmental Protection Agency (“EPA”) and that led to their last-minute withdrawal of their prior effective approval of the permit. The COE may not issue such a permit without the EPA’s concurrence. 33 U.S.C. § 1413; 33 C.F.R. §§ 423.1-.4; 40 C.F.R. §§ 225.1-.4.

In response, defendants, comprised of the COE’s New York District, the EPA’s Region 2, and the relevant officials of each agency, have moved to dismiss the complaint for lack of subject matter jurisdiction on the ground that no final agency action was taken and that the change in criteria did not affect plaintiffs rights. Alternatively, defendants move to dismiss on the ground that none of the agencies’ actions was arbitrary and capricious. For the following reasons the motions are denied.

According to the administrative record, USG applied to the COE for the permit here in issue in April 1998. At that time, the practice of the COE, with the EPA’s concurrence, was to deny such a permit if the dredged material sought to be dumped at the Site contained polychlorinated biphenyls (“PCBs”) in a concentration of 400 parts per billion (“ppb”) or higher as measured by bioaccumulation in worm tissue; conversely, if the PCB level was lower than 400 ppb and all other applicable criteria were met, the permit would be granted. Since a sediment sample from USG’s proposed dredging site showed a worm-tissue PCB level of 128 ppb, and all other relevant criteria were met, the COE and EPA, in July 2000, issued a joint evaluation that the material proposed to be dredged was suitable for disposal at the Site. This conclusion was reiterated in a public notice published August 11, 2000 that indicated the defendants’ intention to approve USG’s application and invited public comment.

The public comment period ended September 25, 2000 with very few negative comments received. On September 26, 2000, however, the COE’s New York District and the EPA’s Region 2 executed a Memorandum of Agreement that lowered the acceptable worm-tissue PCB level for *291 disposal at the Site from 400 ppb to 113 ppb, applicable to all pending permit applications and effective immediately. By letter to the COE dated September 27, 2000, the EPA thereupon retracted its prior concurrence in the decision to grant USG’s dumping permit, on the express ground that the PCB level in the proposed dredged material was too high to meet the new standard. USG objected, contending that the new PCB standard of 113 ppb had been erroneously calculated, was not based on sound science, and had been improperly implemented. USG further alleged that in any event the PCB concentration in the dredging material it proposed to dump at the Site was actually 111 ppb, rather than 128 ppb as previously calculated, and therefore met the new standard. Nevertheless, by letter dated October 24, 2000 the EPA adhered to its determination that the permit should not be granted.

Theoretically, such non-concurrence by the EPA is not necessarily dispositive. Rather, the COE is then required to assess economically feasible alternatives to the proposed dumping, or if there are none and the dumping is, in the COE’s opinion, not contrary to the public interest, the COE must then so advise the EPA, which may withdraw its objections. 33 C.F.R. § 324.4(c). If the objections are not withdrawn within 15 days, the dispute is then referred to the COE’s Chief of Engineers, who may request a waiver from the EPA Administrator. 33 C.F.R. § 324.4(d).

Here, however, none of these steps was taken, at least so far as the record discloses; or, if they were, they had no effect, since neither the EPA nor the COE changed its position. Accordingly, after waiting two months beyond the EPA letter of October 24, 2000, USG, alleging that it was suffering severe economic consequences from the effective denial of the permit, brought this action.

An agency action is “final,” and thereby confers subject matter jurisdiction on this Court, 5 U.S.C. § 704, when it “mark[s] the consummation of the agency’s decisionmaking process,” i.e., the agency “has rendered its last word on the matter.” Whitman v. Am. Trucking Ass’ns, Inc., 531 U.S. 457, 121 S.Ct. 903, 915, 149 L.Ed.2d 1 (2001) (internal quotation marks omitted). “[T]he action must be one by which ‘rights or obligations have been determined,’ or from which ‘legal consequences will flow,’ ” Appalachian Power Co. v. EPA, 208 F.3d 1015, 1022 (D.C.Cir.2000), quoting Bennett v. Spear, 520 U.S. 154, 178, 117 S.Ct. 1154, 137 L.Ed.2d 281 (1997). However, an agency need not “dress[ ] its decision with the conventional accoutrements of finality,” and “its own behavior [may] bel[ie] the claim that its interpretation is not final.” Whitman, 121 S.Ct. at 915. Ultimately, where an agency’s decision is given practical effect, it will be sufficient to trigger judicial review. See Her Majesty the Queen in Right of Ontario v. EPA, 912 F.2d 1525, 1531 (D.C.Cir.1990).

In this case, the plaintiff challenges (i) the defendants’ adoption of the new PCB standard contained in the Memorandum of Agreement and (ii) the consequent denial of the previously-approved dumping permit. As to the first, whether the new PCB standard is a legislative rule subject to the notice and comment requirements of the Administrative Procedure Act or merely an interpretive rule or statement of past EPA-COE policy, it is still reviewable by this Court if its practical effects are final and binding:

If an agency acts as if a document issued at headquarters is controlling in the field, if it treats the document in the same manner as it treats a legislative rule, if it bases enforcement actions on the policies or interpretations formulat *292 ed in the document, if it leads private parties or State permitting authorities to believe that it will declare permits invalid unless they comply with the terms of the document, then the agency’s document is for all practical purposes “binding.”

Free access — add to your briefcase to read the full text and ask questions with AI

United States Gypsum Co. v. Muszynski, 161 F. Supp. 2d 289, 2001 U.S. Dist. LEXIS 13449, 2001 WL 1018353 (S.D.N.Y. 2001).

161 F. Supp. 2d 289 (United States Gypsum Co. v. Muszynski) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Amadei v. Nielsen
348 F. Supp. 3d 145 (E.D. New York, 2018)