United States Fire Insurance Company v. America Walks at Port St. Lucie, LLC

CourtDistrict Court of Appeal of Florida
DecidedMay 15, 2024
Docket2023-1784
StatusPublished

This text of United States Fire Insurance Company v. America Walks at Port St. Lucie, LLC (United States Fire Insurance Company v. America Walks at Port St. Lucie, LLC) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fire Insurance Company v. America Walks at Port St. Lucie, LLC, (Fla. Ct. App. 2024).

Opinion

DISTRICT COURT OF APPEAL OF THE STATE OF FLORIDA FOURTH DISTRICT

UNITED STATES FIRE INSURANCE COMPANY, Appellant,

v.

AMERICA WALKS AT PORT ST. LUCIE, LLC, Appellee.

No. 4D2023-1784

[May 15, 2024]

Appeal from the Circuit Court for the Nineteenth Judicial Circuit, St. Lucie County; Brett M. Waronicki, Judge; L.T. Case No. 562023CA000035A.

Guy W. Harrison and Edward Etcheverry of Etcheverry Harrison, LLP, Fort Lauderdale, for appellant.

Theodore L. Tripp, Jr., and Meredith McBride of Hahn Loeser & Parks LLP, Fort Myers, for appellee.

GERBER, J.

The appellant surety, which had filed a declaratory judgment action in the circuit court against the appellee developer, appeals from the circuit court’s order granting the developer’s motion to compel the surety’s declaratory judgment action to arbitration. The surety argues the circuit court erred in determining a valid arbitration agreement exists between the surety and the developer. The surety argues such a determination cannot be made until, in the developer’s earlier-filed arbitration action, the arbitrator determines whether the developer had validly terminated an underlying “prime contract” with its general contractor, and thus had validly accepted assignment of a “master subcontract” containing the arbitration agreement which the developer seeks to enforce.

We agree with the surety’s argument. We therefore reverse the circuit court’s order granting the developer’s motion to compel the surety’s declaratory judgment action to arbitration. We remand with directions to the circuit court to stay the surety’s declaratory judgment action until, in the developer’s earlier-filed arbitration action, the arbitrator determines whether the developer validly accepted assignment of the “master subcontract,” and thus whether a valid arbitration agreement exists between the developer and the surety.

Background

1. The Tangled Web of Contracts Involved in this Case

The complicated nature of this appeal arises from the three interrelated contractual relationships underlying this case.

First, the developer and the general contractor (“the GC”) entered into the “prime contract” for constructing a residential community project.

Second, the GC entered into a master subcontract and two job-specific subcontracts with a land development subcontractor (“the sub”).

Third, the sub obtained performance bonds from the surety covering the two job-specific subcontracts. The performance bonds incorporate the two job-specific subcontracts by reference. The performance bonds also provide that if the sub defaults on its performance under either of the two job-specific subcontracts, the GC is owed the payment under the bonds.

Both the prime contract and the master subcontract provide that if the developer terminates the prime contract for cause, the developer may take assignment of the master subcontract from the GC upon the developer giving notice to the GC and the sub. Both the prime contract and the master subcontract also provide that upon the developer giving such notice, the developer would be owed payment under the surety’s performance bonds.

Further complicating this case is that the prime contract, the master subcontract, and the performance bonds each provide for a different dispute resolution process.

The prime contract provides that any claim or dispute between the developer and the GC “arising out of or relating to” the prime contract shall be submitted to binding arbitration under the American Arbitration Association’s (“AAA”) Construction Industry Rules. A third party may be joined into such binding arbitration only with that third party’s consent.

The master subcontract provides that, at the GC’s sole discretion, any claim or dispute “arising out of, relating or and/or in any way connected with” the two job-specific subcontracts shall be resolved by binding

2 arbitration under the AAA’s Construction Industry Rules. The master subcontract also provides the arbitrator shall decide “[a]ny disputes concerning the interpretation or the enforceability of th[e] [master subcontract’s] arbitration agreement,” including “the scope of arbitrable issues.”

The surety’s performance bonds do not contain an arbitration agreement. Instead, the performance bonds provide that “[a]ny proceeding, legal or equitable, under [the performance bonds] may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located.” As stated above, the performance bonds also expressly incorporate the two job-specific subcontracts.

2. The Dispute Leading to the Developer’s Earlier-Filed Arbitration Action

One day, the GC sent the developer a notice terminating the prime contract for cause, citing the developer’s alleged nonpayment under the prime contract. Later that day, the developer sent the GC a notice terminating the prime contract for cause, citing the GC’s alleged various breaches under the prime contract.

The next day, the developer notified the GC and the sub that the developer had terminated the prime contract and was accepting assignment of the master subcontract.

A few days later, the developer notified the surety that the sub was in default under the two job-specific subcontracts and, therefore, demanded the surety pay the developer under the surety’s performance bonds.

The surety responded it needed to investigate whether the developer was a proper claimant under the performance bonds, and whether conditions precedent to asserting a claim under the performance bonds had been satisfied.

During the surety’s investigation, the sub took the position that the developer did not have any payment rights under the performance bonds. The sub claimed the GC’s termination of the prime contract—which had preceded the developer’s purported termination of the prime contract later that day—had effectively terminated the two-job specific subcontracts, invalidated the bonds, and precluded the developer from accepting assignment of the master subcontract or replacing the GC as being owed payment under the bonds.

3 The developer then submitted to the AAA a demand for arbitration against the GC, the sub, and the surety. The developer’s demand sought to enforce the arbitration agreements in both the prime contract and the master subcontract. The developer’s demand also sought to recover damages for the GC’s alleged breaches of the prime contract, the sub’s alleged breaches of the two job-specific subcontracts, and the surety’s non-payment under the performance bonds. The developer’s demand further sought a declaratory judgment on three issues: (1) whether the GC’s termination of the prime contract was improper; (2) whether the developer’s termination of the prime contract for cause and acceptance of the master subcontract’s assignment were valid; and (3) whether the surety owed payment to the developer under the performance bonds for the sub’s alleged breaches of the two job-specific subcontracts.

3. Last But Not Least, the Surety’s Circuit Court Declaratory Judgment Action, and the Developer’s Motion to Compel that Action to Arbitration

The surety then filed, in the circuit court, a declaratory judgment action naming the developer as the sole defendant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

St. Paul Fire & Marine Ins. Co. v. Woolley/Sweeney Hotel 5
545 So. 2d 958 (District Court of Appeal of Florida, 1989)
Henderson Inv. Corp. v. International Fidelity Ins. Co.
575 So. 2d 770 (District Court of Appeal of Florida, 1991)
Seifert v. US Home Corp.
750 So. 2d 633 (Supreme Court of Florida, 1999)
Shotts v. OP Winter Haven, Inc.
86 So. 3d 456 (Supreme Court of Florida, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
United States Fire Insurance Company v. America Walks at Port St. Lucie, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fire-insurance-company-v-america-walks-at-port-st-lucie-fladistctapp-2024.