United States Fidelity & Guaranty Co. v. United States

11 F.2d 750, 1926 U.S. App. LEXIS 2597
CourtCourt of Appeals for the Fourth Circuit
DecidedFebruary 27, 1926
DocketNo. 2385
StatusPublished

This text of 11 F.2d 750 (United States Fidelity & Guaranty Co. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. United States, 11 F.2d 750, 1926 U.S. App. LEXIS 2597 (4th Cir. 1926).

Opinion

WADDILL, Circuit Judge.

This is a writ of error to the United States District Court for the District of Maryland. Defendant in error, plaintiff in the court below, instituted its action at law to recover of plaintiff in error the amount of a certain penal bond for $30,000, dated the 21st of May, 1918, given to pay to the defendant in error the amount of said bond, and to indemnify and save harmless said defendant in error on account of advances made by it under said bond and upon the terms and conditions therein specified.

Prior to the execution of this bond, to wit, on the 14th day of May, 1918, defendant in error entered into a contract with the Gas Oil Chemical Company, whereby the latter company agreed to sell and deliver to the defendant in error 100,000 gallons of toluol at the price of $1.50 per gallon. . Briefly, the terms and conditions set forth in the conT tract were that the contractor would sell and deliver to the United States, and the United States would purchase, the said 100,000 gallons of toluol, manufactured in compliance with certain specifications of the Ordnance Department, dated the 30th of March, 1918. Deliveries were to begin as soon as practicable, not later than July 1,1918, and thereafter at the rate of not less than 10,000 gallons per month, until the total quantity contracted for had been furnished. With a view of facilitating the furnishing of the said toluol, the parties entered into the contract of the 21st of May, 1918, as supplemental to that of the 14th of May, 1918, whereby the government agreed to, and did, advance, on account of such undertaking, the sum of $30,-000, and the said Gas Oil Chemical Company obligated itself to repay the $30,000 within the time specified in said supplemental contract. The bond sued on'herein was duly executed by plaintiff in error, the surety company, to save the government harmless on account of such advance. Defendant in error, insisting that plaintiff in error had wholly, breached its contract, instituted this suit to recover the $30,000 paid by it as aforesaid, and for the repayment of which the bond was given. The plaintiff in error duly appeared and interposed its defense to the action, insisting that it was not, and the government was, responsible for the alleged breach of the contract, and that it had sustained damages, as a result thereof, for an amount largely in excess of the bond sued on, and that hence no recovery should be had thereon.

Upon appropriate pleadings and the testimony adduced in open court, the District Court instructed the jury to return a verdict in favor of the defendant in error for the total amount of $30,000, the penalty of said bond, less $879.75 paid on account thereof, to wit, the sum of $29,102.25. The court submitted to the jury the question of whether interest should be allowed upon the amount found to be due the government. Upon the jury awarding interest, the court entered its judgment against the defendant, plaintiff in error herein, for $32,361.70, and rejected defendant’s defense in its entirety.

Many exceptions were taken to the action of the trial judge, set forth in 42 different bills of exceptions, and the plaintiff in error makes 43 assignments of error to the court’s action. The rulings of the court, as set forth in the 42 bills of exceptions, cover a great variety of questions, some of which may be said to be of doubtful propriety;' but all, with the view this court takes of the merits of the controversy, become immar terial, and the same may be said of the greater number of assignments of error. The bills of exceptions and assignments of error, in nearly every instance, relate to matters held by the lower court, and in which we concur, either to depend upon hearsay testimony, or to relate to matters immaterial and irrelevant to the real merits of the ease.

The ease, as decided by the District Court, is apparently a simple one, in that, with a record of considerable size, and with the large number of exceptions and assignments of error as aforesaid, the judge’s conclusion is that the government should recover the largest possible amount to which it would be entitled in any view of the case, and the defendant the least amount. This makes the case one of easy solution, if the conclusions are correctly arrived at. A careful read[752]*752ing of the record, especially from pages 109 to 124, and pages 130, 131, gives apparently an accurate account of. the claims asserted by the defendant, plaintiff in error, the consideration given the same by the War Department, and the outcome thereof. Briefly stated, the plaintiff in error placed its damages, resulting from the breach of the contract by defendant in error, at $53,548.01, the same being set forth in eight different items. Of these items, only Nos. 7 and 8, for $14,409 and $5,246.44, respectively, aggregating $19,655.44, were allowed, which defendant, plaintiff in error, declined to accept, with the result that, so far as the War Department was concerned, the entire claim was rejected.

The court, in reaching its conclusion, seems to have acted upon the theory that the contract was breached under the second paragraph of article 12 of the original contract of the 14th of May, 1918, because of the abandonment and the willful and continuous violation of it by the contractor, and not under the first section of said article, which authorizes the termination and cancellation of the same upon giving notice to the contractor by the Chief of Ordnance, if in his opinion the need for further toluol under the contract had ceased to exist. Article 12 of the original contract is as follows:

“Termination of Contract. — This contract, including any extension thereof, may be terminated and canceled by notice in writing to the contractor by the Chief of Ordnance, as follows:

“(1) Because in the opinion of the Chief of Ordnance the need for further toluol under this contract has ceased to exist.

“(2) Because of the abandonment of willful or continued violation of this contract by the contractor.

“Upon termination of this contract for the first-named cause the United States shall pay the contractor (a) for all toluol theretofore accepted by the United States, (b) for all such as may (subject to inspection) be ready for delivery, and (e) for all in process of manufacture. In addition, if at the time such notice is given less than 100,000 gallons has been accepted by the United States there may be added such sum, if any, as the Chief of Ordnance may deem necessary justly to compensate the contractor for its work hereunder. In addition, if at the time such notice was given less than 12,000 gallons of toluol has been accepted by the United States, the United States shall pay to the contractor the difference in value between 12,000 gallons and the amount theretofore accepted and paid for by the United States. Any termination of this contract for the second-named cause or causes shall be without prejudice to any other rights or remedies that the United States may have at law against the contractor.”

That the breach of the contract was by the government, and not by the contractor, seems to us, from the testimony in this ease, to admit of no doubt. The government took pains to give notice of cancellation in strict accordance with section 1 of article 12, and the contract was promptly canceled as soon as it became evident that the government’s needs would no longer require the further use of toluol. This was one of the very possibilities that caused the provision, with respect to cancellation by the government, to be inserted in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
11 F.2d 750, 1926 U.S. App. LEXIS 2597, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-united-states-ca4-1926.