United States Fidelity & Guaranty Co. v. Sellers

255 S.W. 26, 160 Ark. 599, 1923 Ark. LEXIS 312
CourtSupreme Court of Arkansas
DecidedNovember 5, 1923
StatusPublished
Cited by4 cases

This text of 255 S.W. 26 (United States Fidelity & Guaranty Co. v. Sellers) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. Sellers, 255 S.W. 26, 160 Ark. 599, 1923 Ark. LEXIS 312 (Ark. 1923).

Opinion

Wood, J.

The appellee instituted this action against Jos. McCoppin and the appellant, and alleged that he and one Joseph McCoppin, for himself and as agent for the appellant, entered into a contract with the appellee by which appellee was to haul gravel and sand to be used in the construction of pavements for Forrest City Improvement District No. 5. He alleged that McCoppin undertook and agreed to pay the plaintiff $1.50 for each yard of sand and gravel hauled from Little Crow Creek to Forrest City and $1.85 for each yard of sand and gravel hauled from Big Crow Creek to Forrest City; that at the time the contract was made it was represented to the appellee that there were 13,075 yards of gravel and sand to be hauled under the contract, and that, in fact, there was such an amount, and that appellee, relying upon such estimate, ordered, at great expense in price, the necessary equipment to perform the contract. He further alleged that, pursuant to such contract, appellee hauled 3,075 yards of sand and gravel, which entitled him to a payment of $5,579.11, of which amount the appellant had paid $4,927.91, leaving a balance of $851.20. He further alleged that on the 9th of July the appellant notified the appellee that the contract would be no longer recognized by the appellant, and thereby the appellant breached the contract. He further alleged that at the time of the breach of said contract there remained to 'be hauled 10,000 yards of sand and gravel; that the difference between the contract price as made by the parties for the hauling of the gravel and sand and the reasonable cost to the appellee of hauling the same amounted to forty cents per cubic yard, or a total of $4,000. He. further alleged that the appellant, the guaranty company, executed a bond for the benefit of all persons doing labor or furnishing material in said work for the benefit of the appellee, conditioned that Joseph McOoppin should pay all just claims for the same. Appellee prayed for judgment against McOoppin and the guaranty company in the sum of $4,851.20.

McOoppin answered and denied all the material allegations of the complaint. The guaranty company answered adopting the answer of McOoppin, so far as applicable, and denied that McOoppin, as its agent, contracted with the appellee as set up . in the complaint, and averred that, if McOoppin did undertake to contract in the name of the guaranty company, he had no authority to do so. The guaranty company denied that it had any contract with the appellee for any purpose, and especially for the hauling of sand and1 gravel for McOoppin. It is alleged that the bond executed by it was for the sole benefit of Forrest City Improvement District No. 5 of Forrest City, Arkansas, and that, under the terms of said bond the guaranty company did not make itself liable for material furnished or labor done or performed by any person for McOoppin or for Forrest City Improvement District No. 5.

The appellee testified in his own behalf, and, without setting out his testimony in detail, it suffices here to state that his testimony tended to support the allegations of his complaint. Appellee introduced the following paper, which was signed by him: “Exhibit 6: I will haul gravel on the street of Forrest Oity from Little Crow Creek for $1.50 per yard. I will haul from Big Crow Creek for $1.85 per yard; and also agree to furnish three teams on the streets and two at the creek.” Concerning this paper, appellee testified that it was a simple bid on the job, and he was to have a contract afterwards. McCoppin testified, among other things, concerning this paper that he understood that it constituted the entire 'contract between him and Sellers the moment Sellers gave it to him. He understood that it was left open for him to stop it or for Sellers to quit hauling. What witness meant was that the writing didn’t apply to the whole contract. Witness agreed to make advances to .Sellers for labor and to retain a certain amount as percentage, none of which was in the bid. .This was agreed to. ¡before Sellers went to work. This didn’t become a part of the contract, but Sellers came to him and said that he didn’t have the means to pay his labor, and asked if he would advance the money to pay it, and witness told him he would.

The guaranty company was not a contractor on the job, as witness understood, but was merely on witness’ bond. The estimates for the work had written across the head of each, “Jos. McCoppin, U. S. Fidelity & 'Guaranty Company, Contractors.” These estimates were furnished by the engineer.

The contract between Forrest City Improvement District No. 5, party of the first part, and Jos. McCoppin and U. S. Fidelity & Guaranty Company, surety, parties of the second part, executed in April, 1921, was introduced in evidence. This contract, by way of inducement, recites that a contract has been entered into between the party of the first part and McCoppin on the 30th of April, 1919, to do certain paving in the city of Forrest City; that the guaranty company was a surety on McCoppin’s bond for the faithful performance of the contract; that a suit had been filed by the district against McCoppin and the guaranty company, alleging that McCoppin had breached the contract, and the bond further recites that the parties of the second part were desirous of completing the work, and that the party of the first part, the district, was willing that same be done upon the following conditions: The first paragraph, stating the conditions, was that the second parties were to do all things necessary for the completion of the pavements as provided in the contract. The second was for the manner in which payments were to be made. The third provided for an additional stun to be paid the engineer. The fourth provided that the work should be prosecuted diligently and without unnecessary delay by the parties of the second part, and the work was to begin at once. The fifth specified that, in case the parties of the second part completed the work as provided in the original contract, then the penalty of $10 per day as prescribed in that contract was waived, otherwise to remain in full force and effect. It further recited that none of the parties waived any forfeitures or rights, except as therein provided, that any of the parties may have had under the original contract, and that, in case the parties of the second part completed the work as provided in the contract, the suit pending in the circuit court by the district against the parties of the second part should be dismissed at the cost of the parties of the second part.

At the request of the appellee the court, among other instructions, gave the following:

“No. 2. The writing by which Mr. Sellers proposed to haul the gravel for Mr. MoCoppin is not a completed contract. There is no written contract between the parties, plaintiff and defendant, and you will look to the verbal testimony herein to establish what their contract was. A verbal contract is good for such matters as are in controversy between the parties hereto; it is not required to be in writing.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Schnitt v. McKellar
427 S.W.2d 202 (Supreme Court of Arkansas, 1968)
Pictorial Paper Package Corp. v. Swamp & Dixie Laboratories, Inc.
122 S.W.2d 529 (Supreme Court of Arkansas, 1938)
Dewey Portland Cement Co. v. Benton County Lumber Co.
63 S.W.2d 649 (Supreme Court of Arkansas, 1933)
McCauley v. Arkansas Rice Growers' Cooperative Ass'n
287 S.W. 419 (Supreme Court of Arkansas, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
255 S.W. 26, 160 Ark. 599, 1923 Ark. LEXIS 312, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-sellers-ark-1923.