United States Fidelity & Guaranty Co. v. Koehler

137 S.E. 85, 36 Ga. App. 396, 1927 Ga. App. LEXIS 89
CourtCourt of Appeals of Georgia
DecidedFebruary 14, 1927
Docket17237, 17238
StatusPublished
Cited by6 cases

This text of 137 S.E. 85 (United States Fidelity & Guaranty Co. v. Koehler) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. Koehler, 137 S.E. 85, 36 Ga. App. 396, 1927 Ga. App. LEXIS 89 (Ga. Ct. App. 1927).

Opinion

Bell, J.

The Provident Trust & Security Company brought suit in Fulton superior court against Palmer Brick Company, as principal, and United States Fidelity & Guaranty Company, as surety, upon a bond. This bond was in the sum of $10,000 and was executed to indemnify and save harmless the Provident Company from any pecuniary loss resulting from the breach by the Palmer Company of any of the terms arid conditions of clause 4 [398]*398of a conditional lease between the Palmer Company, as lessor, and the Provident Company, as lessee. Clause 4 of this lease was as follows: “Said party of the first part [the Palmer Company] agrees to put the Shaw kiln located on the premises hereby leased in operation, under the direction and supervision of James W. English Jr. [president of the Palmer Company], or such competent person as he may select, at a cost not to exceed the sum of $8,266, as per estimate contained in letter of P. J. Smith to Thomas B. Felder, dated May 11, 1912, which cost is to be borne and paid for by said party of the second part [the Provident Company] • and when the repairs are so completed and the fires started, the kiln shall be operated for a period of sixty working days under the supervision of said James W. English Jr., or his duly authorized representative, the pay-rolls and costs of operating said kiln during this period to be paid by said party of the second part promptly when due; and if said Shaw kiln fails to burn 30,000 brick per day of twenty-four hours continuously for sixty working days, then this lease shall cease and terminate and no longer be of any force or effect. If, however, for any reason said James W. English Jr. can not be present in person to conduct.the test for sixty working days' hereinbefore referred to, and said test shall be unsuccessful, then and in that event he shall have the right, at the cost of said party of the first part, to take over said kiln and personally conduct another test for a period of sixty working days, and in the event this second test under the supervision of said James W. English. Jr. in person shall prove a success, under the terms of this instrument, then and in that event said party of the second part is to accept said kiln and premises under the terms hereof, and the terms of the lease covered by this agreement shall begin upon the day of acceptance of said kiln by said party of the second part; it being understood that said party of the second part shall be reimbursed by said party of the first part for the actual cost of operating said kiln the first test above referred to, from which amount shall be deducted the sums received from the sale of the brick manufactured during that period and the value of the merchantable brick on hand at the end of said period. In the event said second test shall also prove unsuccessful, said party of the first part shall thereupon reimburse said party of the second part for all costs incurred in repairing said- kiln, 'together, with the [399]*399expense of operating same during the first test of sixty working days above referred to, it being understood that there shall be deducted from the expense of operation for said period such sums as may be received from the brick manufactured during that period, together with the value of the merchantable brick on hand at that time. It is also understood and agreed that the tests referred to above are to be made from fresh clay brought in from the clay used by said party of the first part, and not from any clay which may now be on hand at its plant. Said party of the first part is to give said party of the second part satisfactory security guaranteeing the carrying out of the provisions of this contract.”

J. W. English Jr. was president of the Palmer Company. The bond in suit provided that the surety should not be liable for a greater sum than the penalty of the bond or subject to any action or proceeding thereon instituted later than February 3, 1913. The suit was not filed until March 31, 1913.

Among other things . the petition alleged: The plaintiff, in terms of clause 4 of the lease contract, with the Palmer Company, furnished for repairs and for the costs of operating the kiln during the first test a sum in excess of $10,000. This test proved that the kiln was a failure, demonstrating that it did not possess the required capacity as to production. J. W, English Jr', did not elect to make a second test. Both parties to the lease, however, desired that the kiln should be made a success, and if this could be done, that the lease should be continued in force; so that notwithstanding the Provident Company considered that the Palmer Company had now breached its contract and that the liability of the surety company had attached, the Provident Company, on November 4, 1912, after many negotiations between it and the defendants “relative to the breaches of the contract aforesaid and the liability of the” defendant surety company upon its bond, wrote the latter company a letter with regard to the matter, as follows: “In re: Bond dated August 3, 1912, made by the Palmer Brick Company, as principal, and your company as surety,- to our company, the 'Provident Trust Company, as obligee, we beg to say that on the 28th day of October, 1912, we wrote you a letter in which we stated that divers breaches of said contract had been committed as therein specified and set forth. Since writing you said letter we have taken up the situation as a whole, with the view of endeavoring to [400]*400have the construction of said kiln completed, as contemplated in the original contract between our company and. the Palmer Company. And, to this end, we are willing to proceed under the original contract and clause 4 thereof to furnish additional sums as may be required to complete the repairs called for, and purchase any and all such material as may be required by said Palmer Company, or its agents, to complete the said kiln and put the same in operation, provided such sum does not exceed. $3,000. On the other hand, if after said kiln is completely repaired and put in operation, and the 60-day test called for by said paragraph 4 of said contract is had, and the kiln successfully stands such test called for by said paragraph 4 of the said contract, then and in that event your liability on your bond will be at an end.” The surety company made the- following reply: “Replying to your favor of November 4th in regard to bond dated August 3d, 1912, made by Palmer Company as principal, and U. S. Fidelity Company as surety, and the Provident Trust- Company as obligee, we beg to say that the proposition made by you therein to us is hereby accepted.” The plaintiff, acting in good faith, furnished additional moneys on behalf of Palmer Company for the completion of the kiln, finishing the same in the early part of February, 1913. Thereupon the plaintiff proceeded to make a second test, James W. English Jr. having failed to make or conduct any such test, which second test, like the first, was unsuccessful, showing that .the kiln could not meet the terms and conditions of the lease contract as to production required. The second test was not completed until February 26, 1913, several weeks after the time limit for suit as expressed in the bond. The plaintiff demanded payment from the surety company of $10,000 on March 6, 1913. The provision in the bond to the effect that suit must be brought not later than February 3, 1913, was “distinctly waived by the parties to said contract or bond of indemnity by their conduct as hereinbefore set forth, and especially by the modifying of said contract or bond, as shown by the letters of November 4, 1912, attached as exhibits to this petition.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monroe Motor Express v. Jackson
38 S.E.2d 863 (Court of Appeals of Georgia, 1946)
Harrell v. Parker
198 S.E. 776 (Supreme Court of Georgia, 1938)
Johnson Lumber Co. v. Akers Lumber Co.
172 S.E. 667 (Court of Appeals of Georgia, 1934)
Loftis v. Metropolitan Casualty Insurance
167 S.E. 729 (Court of Appeals of Georgia, 1933)
Gary v. Central of Georgia Railway Co.
160 S.E. 716 (Court of Appeals of Georgia, 1931)
Central of Georgia Railway Co. v. Greene & Co.
154 S.E. 809 (Court of Appeals of Georgia, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
137 S.E. 85, 36 Ga. App. 396, 1927 Ga. App. LEXIS 89, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-koehler-gactapp-1927.