United States Fidelity & Guaranty Co. v. Klamath County

23 P.2d 133, 143 Or. 471, 1933 Ore. LEXIS 177
CourtOregon Supreme Court
DecidedMarch 31, 1933
StatusPublished

This text of 23 P.2d 133 (United States Fidelity & Guaranty Co. v. Klamath County) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. Klamath County, 23 P.2d 133, 143 Or. 471, 1933 Ore. LEXIS 177 (Or. 1933).

Opinion

*472 R.OSSMAN, J.

The complaint alleges that November 2, 1927, Gr. W. Brown and the County of Klamath entered into a contract whereby Brown undertook to construct a section of highway for the county; that at the same time the plaintiff, as surety, signed a bond guaranteeing Brown’s faithful performance of his contract; that February 4, 1928, Brown abandoned performance of his contract; that later the plaintiff, with the consent of the Board of County Commissioners, completed performance of the contract; that during the progress of the work the County Commissioners approved estimates of the work done and money earned by the plaintiff which estimates of money earned, less retained percentages, were paid to the plaintiff; that September 15, 1928, the Board prepared the final estimate showing a balance of $4,746.76 due and payable to the plaintiff; and that December *473 22,1928, the Board paid to the plaintiff $3,946.76. Judgment is sought for $800. The answer admits the execution of the contract, the execution of the bond, Brown’s default, plaintiff’s completion of performance, and payment to the plaintiff of $3,946.76 upon the final estimate. All other averments of the complaint are denied. Further answering, the defendants allege that December 15, 1928, the county engineer prepared a final estimate of the amount owing the plaintiff for the completion of performance of the aforementioned contract showing there was due to it $3,946.76; that a warrant was issued to the plaintiff for $3,946.76 in full payment of its account against the county; that the plaintiff accepted the warrant as payment in full of all charges against the county; and that the plaintiff “is now estopped and debarred to say, allege or claim that any other and further sums or amounts whatsoever are due or owing to it under or by virtue of said contract”. This portion of the answer further alleges that one of the provisions of the contract stipulated that the acceptance of payment by Brown of the final estimate should constitute a release of Klamath county by him and his surety of all claims arising out of the contract, and that neither Brown nor the plaintiff, before accepting the warrant for $3,946.76, informed the defendants that the amount for which the warrant was drawn was erroneous or insufficient. The answer charges that, therefore, the acceptance of the warrant for the final estimate constituted “a final, agreed settlement and payment in full of all sums due to the plaintiff under or by virtue of said contract”. Next, this portion of the answer alleges:

“And these defendants do further allege that the said plaintiff, after it took over the said Q-. W. Brown contract, hereinbefore mentioned, did not pay out for *474 labor, material, supplies or the like or at all the said sum of $800.00 in payment of labor, material or supply claims due to laborers or materialmen furnishing labor or supplies for the completion of said contract, but the said plaintiff is attempting to collect the said $800.00 from Klamath County when it did not earn the same and when it did not pay out to laborers or materialmen or others or at all the said sum of $800.00 or any part thereof ¿ that all of the sum embraced in said $800.00 was paid out by the said original contractor, Gr. W. Brown, in payment of labor, material and supply claims, and all of the amount embraced in said $800.00 was applied and paid by said Gr. W. Brown on and for the performance of said contract, and there is nothing due to the plaintiff herein by reason of such payment of said sum by G. W. Brown, and the said plaintiff is estopped and debarred to claim the said sum or any part thereof of or from the defendants or either thereof”.

For a second further defense the defendants allege that January 12, 1928, Brown borrowed $800 from the Oregon Bank & Trust Company, giving his note therefor ; that the $800 was expended by Brown in the performance of his contract; that in order to secure payment of the note he delivered to the bank an instrument dated January 12, 1928, addressed to the county clerk, signed by himself, and reading as follows:

“Please deliver to the Oregon Bank & Trust Company my warrants for the months of January and February, 1928, for estimate No. 3, Market Road District No. 9, Klamath County, Oregon”.

that at that time Brown had not yet defaulted in the performance of his contract; that the plaintiff did not undertake the completion of the performance of the contract until after February 12, 1928; that the plaintiff had knowledge of the assignment before it proceeded with the contract; that the sums mentioned in *475 the assignment were no part of the retained percentages; that the plaintiff knew that the county court would honor the assignment by paying to the bank the sum of $800; that on December 15, 1928, the county court paid the Oregon Bank & Trust Company $800; and that these facts estop the plaintiff from claiming that it is entitled to the recovery of $800 from the county. The reply admits that the county engineer prepared the final estimate; denies that the amount of the estimate was $3,946.76; alleges that its amount was $4,746.76; admits that a warrant for $3,946.76 was drawn in its favor; “admits that the acceptance of full payment upon the final estimate should have the effect of a release to the defendants by the said Gr. W. Brown or his surety, the plaintiff herein, of all obligations or claims arising out of said agreement”; denies that the plaintiff, before accepting the amount of $3,946.76, failed to apprize the defendants that the amount was insufficient; and alleges that there was no consideration for accepting a lesser amount than the amount actually due.

The evidence developed the following undisputed facts: November 2, 1927, the Board of County Commissioners of Klamath county and Brown executed a contract whereby the latter bound himself to improve a section of roadway in Klamath county and the county agreed to pay him for his services according to a schedule of payments set forth in the contract. The contract bound Brown to furnish a surety bond guaranteeing the faithful performance of the contract, which he did, the plaintiff becoming his surety. The contract also provides:

“Monthly estimates of the amount earned by the contractor will be submitted to the owner by the county engineer. Such estimates, less 20 per cent, will be paid *476 by warrant as partial payments. * * * When one-half the work has been completed the amount retained will be reduced to 10 per cent”.

The contract further provides:

“When all work shall have been completed in accordance with the specifications attached hereto and made a part hereof to the satisfaction of the county engineer, he will make his final estimate which will include all sums retained from the partial payments and will have the effect of a certificate by him that the work under the contract has been completed and is accepted as such by the owner. The acceptance of payment upon the final estimate shall have the effect of a release to the owner by the. contractor of all obligations as a result of this agreement”.

January 12, 1928, Brown borrowed $800 from the Oregon Bank &

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
23 P.2d 133, 143 Or. 471, 1933 Ore. LEXIS 177, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-klamath-county-or-1933.