United States Fidelity & Guaranty Co. v. City of Canton

128 So. 744, 157 Miss. 680, 1930 Miss. LEXIS 336
CourtMississippi Supreme Court
DecidedJune 9, 1930
DocketNo. 28643.
StatusPublished
Cited by1 cases

This text of 128 So. 744 (United States Fidelity & Guaranty Co. v. City of Canton) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. City of Canton, 128 So. 744, 157 Miss. 680, 1930 Miss. LEXIS 336 (Mich. 1930).

Opinion

Cook, J.,

delivered the opinion of the court.

The appellant, United States Fidelity & Guaranty Company, filed a bill of complaint in the chancery court of Madison county, Mississippi, against the city of Canton, and the W. J. Horie Construction Company. There *687 was a decree pro confesso and final against the "W. J. Horie Construction Company, but a demurrer of the city of Canton was sustained and the bill was finally dismissed as to it, and from the decree so dismissing the bill this appeal was prosecuted.

The averments of the bill of complaint were in substance as follows: That during the year 1927 the city of Canton advertised for bids for the construction of certain curbs and gutters and the paving of certain of its streets according to plans and specifications prepared by its engineer and then on file in the office of the city clerk; that among- other things it was required by the said city that the successful bidder for said work: should enter into a good and sufficient bond with the said city to guarantee the faithful performance of the work and the contract; that the bid of the W. J. Horie Construction Company was accepted, and the contract to do the work was awarded to it upon its entering into a bond with a surety company as surety, which should be acceptable to the city attorney. That thereupon the W. J. Horie Construction Company applied to the appellant to furnish such a bond as the city required; that the said application being acceptable to the appellant it then executed a bond in the sum of thirty thousand dollars as required by the city, and the same was accepted by the city; that thereafter the city, by its proper authorities, entered into a contract with the said W. J. Horie Construction Company to pave certain streets mentioned in said contract and to lay concrete curbs and gutters as set out and mentioned therein; that thereafter the said construction company proceeded under said contract and the provisions of said bond to construct said curbs, gutters, and paving, and did complete the construction of the same according to the plans and specifications on or about the 6th day of November, 1928, as shown by the final estimate prepared by the city engineer, a copy of which estimate was filed as an exhibit to the bill.

*688 The bill further charged that, although by the provisions of the contract and the bond, the W. J. Horie Construction Company was obligated to pay for all labor and material furnished and used in the construction of said paving, curbs, and gutters, the bond being expressly made a part of the contract, yet it failed 'to pay certain bills and accounts for labor performed and material used in the construction of said paving, curbs, and gutters. That on or about December 4, 1928, the said city of Canton gave notice to the public that the said construction company had completed the work, and the city had, on the 19th day of November, 1928, settled with the said construction company, and advised all persons having claims or demands against said contractor to take notice accordingly. That .prior to the settlement with the said contractor on November 19, 1928, the appellant ascertained that the contractor had not paid all parties furnishing labor and material which were necessary and which were used in the construction of this paving, and the curbs and gutters, the various claims and amounts alleged to be due them being listed. That at the time it made the final settlement with the contractor on November 19, 1928, the said city had notice of one claim for five hundred fifty-one dollars and sixty-seven cents, which the said contractor by false affidavit asserted it had paid; and that notice of the other unpaid claims was given to said city after said final settlement'.

The bill of complaint further averred that the claims listed and paid by the appellant represented materials and labor necessary to and used in the construction of said curbs, gutters, and paving, and that one of the pro- ’ visions of the bond which was executed by the contractor and the appellant surety company,' and accepted by the city, was as follows:

“The obligee shall, before making to the principal, the final payment provided for under the contract herein referred to, deliver written notice to the surety at its of *689 fice aforesaid, and the written consent of the surety thereto obtained.”

It was further averred that one of the provisions of the contract which was also made a part of the bond, and was a part of the consideration for the execution of the bond by the appellant, was that the city obligated and bound itself to the said surety as follows:

“Payments for said work will be made as the work progresses on estimates made by the city engineer, and on his approval, not to exceed eighty-five per cent of the amount of said estimate; fifteen per cent being reserved by the city until the said pavement and concrete curbs and gutters are finally completed and accepted by the city engineer, which said fifteen per cent so reserved shall be held as additional or cumulative security for the faithful performance of said contract, and will be paid to the contractor whenever said pavement and concrete curbs and gutters are completed according to the contract and approved and accepted by the city engineer and the mayor and board of aldermen of the city of Canton.”

It was also alleged that; notwithstanding the fact that all these and other provisions were embodied in the contract, not only for the protection of the city, but for the protection .of the surety as well, and were a part of the contract for which the appellant agreed and undertook to execute the bond, the said city passed an order authorizing and directing a settlement with the contractor upon the approval of its final estimate by the city engineer and city commissioner, and that in pursuance of said order the said city settled in full with said contractor for all balance due under his contract, including the fifteen per cent retainage, notwithstanding the fact that under the contract and bond it was provided that the said fifteen per cent retainage would be retained until the contractor had completed the work as provided for by the plans and specifications, and had paid for all labor and material furnished in the construction of said *690 pavement, curbs, and gutters, and that the said fifteen per cent retainage was paid out to the said contractor without the knowledge and consent of the appellant.

It was also charged that the contractor had never completed the contract and was not entitled to the fifteen per cent retainage, because the appellant had never consented to the payment of this retainage to the contractor, and because the contractor had failed and refused to pay the said claims of materialmen and laborers, and the appellant had been compelled to pay the same. That the said contractor could not have required the said city to pay the retained percentage until the contract had been discharged in every respect, and it had discharged its obligation to the city of Canton and to the appellant by complying with said contract, which it failed to do in the payment of materialmen and laborers.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
128 So. 744, 157 Miss. 680, 1930 Miss. LEXIS 336, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-city-of-canton-miss-1930.