United States Ex Rel. United Rentals, Inc. v. Hartford Fire Insurance

339 F. Supp. 2d 799, 2004 U.S. Dist. LEXIS 20644, 2004 WL 2327924
CourtDistrict Court, W.D. Texas
DecidedOctober 13, 2004
Docket1:03-cv-00131
StatusPublished
Cited by4 cases

This text of 339 F. Supp. 2d 799 (United States Ex Rel. United Rentals, Inc. v. Hartford Fire Insurance) is published on Counsel Stack Legal Research, covering District Court, W.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. United Rentals, Inc. v. Hartford Fire Insurance, 339 F. Supp. 2d 799, 2004 U.S. Dist. LEXIS 20644, 2004 WL 2327924 (W.D. Tex. 2004).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

YEAXEL, District Judge.

BE IT REMEMBERED that on July 19, 2004, the Court called the above-styled case for trial. Plaintiff United States for the Use of United Rentals, Inc. (“United Rentals”) appeared by counsel; Defendant Hartford Fire Insurance Company (“Hartford”) appeared by counsel. Having carefully considered the evidence in this action, the Court concludes that Hartford is not liable to United Rentals. In so deciding, the Court makes the following findings of fact and conclusions of law, holding, in summary, that the Miller Act’s one-year statute of limitations bars United Rentals from asserting the bond claim at issue in this cause. See 40 U.S.C. § 3133(b)(4) (2004).

Jurisdiction and Venue

This cause of action arises out of a construction contract with the United States Government and is brought under the Miller Act, 40 U.S.C. §§ 3131-3133 (2004)(for-merly 40 U.S.C. §§ 270a-270d), which provides for exclusive federal jurisdiction and requires that a civil action must be brought “in the United States District *801 Court for any district in which the contract was to be performed and executed, regardless of the amount in controversy.” 40 U.S.C. § 3133(b)(3)(B). See also United States ex rel. Harvey Gulf Int’l v. Maryland Cas. Co., 573 F.2d 245, 247 (5th Cir.1978).

Facts

Rayco Construction Company (“Rayco”) entered in a “Job Order Contract” (Solicitation Number DACA03-98-0002) with the United States Army Corps of Engineers (the “Corps”) in March 1998. Subsequently, the Corps issued Rayco Task Order Number 0112 for construction work at the United States Army Reserve Center at Camp Mabry in Austin, Texas. Pursuant to that task order, Rayco, the prime contractor, entered into several subcontracts for the performance of various work items at Camp Mabry, including paving work that was subcontracted to Zapata Paving (“Zapata”). Hartford, which is in the business of issuing payment bonds to the construction industry, is the surety that issued a public works payment bond in connection with the Camp Mabry project (bond number 46 BCS AG3656). Rayco was the principal of the bond.

United Rentals provided rental equipment to Zapata for the Camp Mabry project from June 2001 through August 2001. United Rentals issued invoices dated June 18, 2001, through August 29, 2001, to Zapata totaling $57,257.13. On August 15, 2001, United Rentals sent a notice to perfect a bond claim pursuant to Texas’s McGregor Act 1 in the amount of $17,017.72 to the Texas National Guard Army Board, Hartford, Rayco, and Zapata for rental equipment and supplies provided by United Rentals in June 2001. On September 14, 2001, United Rentals sent a second McGregor Act bond-claim in the amount of $40,313.23 to Camp Mabry, Hartford, Rayco, and Zapata for rental equipment an supplies provided in July and August 2001. Rayco made three subsequent payments to United Rentals in October 2001 in the amounts of $611.25, $1,143.99, and $1,646.64.

On November 1, 2001, United Rentals served notice by registered mail to Camp Mabry, Hartford, Rayco, and Zapata of its unpaid invoices under the Miller Act (the “Miller Act Bond Claim Notice”) totaling $57,257.13. The cover address sheet of the Miller Act Bond Notice stated in capital letters, “MILLER ACT BOND CLAIM.. ” The attached affidavit, titled “AFFIDAVIT FOR CLAIM UNDER THE MILLER ACT,” stated, “This letter is to perfect a claim under the Miller Act Bond on behalf of United Rentals in the amount of $57,257.13. Demand for payment is hereby made on the prime contractor and surety.”

Following United Rental’s mailing of the Miller Act Bond Notice, Hartford and United Rentals exchanged correspondence and information requested by Hartford from United Rentals. Rayco sent a demand letter to Zapata on March 11, 2002, to which Zapata responded on March 17, 2002, stating that it lacked the capital and assets to cover its debt. No further payments were made to United Rentals by Rayco, Zapata, or Hartford. The parties agree that there remains due an owing to United Rentals an unpaid claim for $57,257.13 for equipment and supplies United Rentals provided to Zapata for the Camp Mabry project.

United Rentals filed suit against Hartford in state court in Harris County, Texas on May 28, 2002, asserting claims for recovery on the payment bond under the Texas Public Bond Statute, commonly re *802 ferred to as the McGregor Act. See Tex. Gov’t Code Ann. § 2253.001-.079 (West 2002). Attached as an exhibit to the petition was the Miller Act Bond Claim Notice. The Harris County court transferred the action to state district court in Travis County by agreed order on September 6, 2002. On February 13, 2003, Hartford moved for summary judgment, asserting the state court’s .lack of subject-matter jurisdiction on the basis of the inapplicability of the McGregor Act, because the project was on federal property-Camp Mabry. On March 5, 2003, United Rentals filed the present cause of action in this Court seeking to adjudicate its bond claim under the Miller Act. The state court granted Hartford’s motion and dismissed the state action on April 7, 2003.

Issue

The parties agree that the sole issue before the Court is whether the filing of a federal bond claim under the Miller Act in state court tolls the act’s one-year statute of limitations.

Findings and Conclusions

The rights created by the Miller Act are federal in nature and scope, and federal law controls the computation of the limitations period. Those circuits that have considered the question have uniformly regarded the one-year filing requirement as a jurisdictional limitation on the substantive rights conferred by the Miller Act. In principle, this is consonant with the thesis that, because the right is federal in nature, the filing of suit in a non-federal jurisdiction does not toll the statute.

Maryland Cas. Co., 573 F.2d at 247 (internal citations omitted). The limitations period runs one year “after the day on which the last of the labor was performed or material was supplied by the person bringing the action.” 40 U.S.C. § 3133(b)(4). The parties agree that United Rentals last provided work on August 28, 2001, and that United Rentals commenced this federal suit on March 5, 2003, more than a year later.

Relying on United States v. Fidelity & Deposit Co. of Maryland, however, United Rentals argues that Hartford can be es-topped from relying on the Miller Act’s one-year limitations period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
339 F. Supp. 2d 799, 2004 U.S. Dist. LEXIS 20644, 2004 WL 2327924, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-united-rentals-inc-v-hartford-fire-insurance-txwd-2004.