United States ex rel. Tennessee Producers' Marble Co. v. Empire State Surety Co.

197 F. 429
CourtDistrict Court, S.D. Mississippi
DecidedMay 15, 1912
DocketNo. 6,568
StatusPublished

This text of 197 F. 429 (United States ex rel. Tennessee Producers' Marble Co. v. Empire State Surety Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Tennessee Producers' Marble Co. v. Empire State Surety Co., 197 F. 429 (S.D. Miss. 1912).

Opinion

NILES, District Judge.

In this cause, the court is called upon to decide questions as to two alleged breaches of a bond executed by a surety company for a building contractor. The suit is brought in the name of the United States, on the relation of the Tennessee Producers’ Marble Company and the State Bank & Trust Company, against the Empire State Surety Coñrpany; the United States being a nominal plaintiff.

Erom the record in this cause, it appears that one Harry A. Bishop of Chicago, 111., a mason contractor, entered into a contract with the federal government to build an annex and other additions to the United States courthouse and post office building at Jackson, Miss., on December 18, 1908.

As required by United States statutes, Bishop, before entering upon the contract, executed a bond in the penalty of $20,000 with the Empire State Surety Company as surety, conditioned upon the faithful performance and fulfillment of all the covenants and conditions of his said contract. Among; the stipulations embraced therein was:

“Now, if the said. Harry A. Bishop shall promptly make payment to all persons supplying him labor and materials in the prosecution of the work contemplated by said contract, then, this obligation to be void, otherwise, etc.”

■ Said bond was executed in compliance with the United States statutes in reference to government contracts. After entering upon the contract, Bishop sublet certain marble work provided for in said contract to the Southern Mantel & Tile • Company, a corporation, which marble work the Southern Mantel & Tile Company agreed to complete in accordance with the specifications of said contract for the sum of $1,596.70. The Southern Mantel & Tile Company, in turn, contracted with the Tennessee Producers’ Marble Company to do certain work and furnish the marble called for in the contract between the said Southern Mantel & Tile Company and Bishop, the contractor, for the sum of $1,150. The Tennessee Producers’ Marble Company, in accordance with its contract with the Southern Mantel & Tile Company, fully and completely finished its contract. In the meantime, $231.92 had been paid by the Southern Mantel & Tile Company on its contract with the Tennessee Producers’ Marble Company, leaving a balance due the latter of $918.08.

April 15, 1910, the Southern Mantel & Tile Company, through its president, assigned to the State Bank &' Trust Company,' Jackson, Miss., its “contract- covering work at Jackson post office with H. A. [431]*431Bishop of Chicago.” No notice of this assignment was given Bishop or the Empire State Surety Company until October 26, 1910, when Bishop was notified by letter of that date by the State Bank & Trust Company. Before notice of the assignment, Bishop had paid on his contract with the Southern Mantel & Tile Company the sum of $541.17, leaving a balance due on said contract of $1,084.53 and unpaid.

The Tennessee Producers’ Marble Company sues for the balance of its account for labor and material furnished the subcontractor, the Southern Mantel & Tile Company, amounting to $918.08. The State Bank & Trust Company, assignee of the Southern Mantel & Tile Company, brings their suit against the Empire State Surety Company, surety on the bond of Bishop, for the full amount of the contract, $1,575.

As to the claim of the Tennessee Producers’ Marble Company, the Empire State Surety Company denies liability on the ground that the marble company obligated itself to perform its contract with the Southern Mantel & Tile Company on or before June 1, 1910, but did not so complete until about September 15, 1910, thereby causing the Southern Mantel & Tile Company certain losses by reason of such delay, to the amount of about $500, which damages should be deducted from plaintiff’s recovery, and which damage the surety company pleads by way of offset thereto.

In answer to the claim against it by the State Bank & Trust Company, the surety company denies liability on the ground that the Southern Mantel & Tile Company, assignor of the State Bank & Trust Company, contracted with Bishop for certain work and material to be used in the said government building, in the sum of SE-SOS, and that Bishop had paid the Southern Mantel & Tile Company the sum of $544.63, as set forth, without notice of any assignment to the State Bank & Trust Company, and that the surety company is therefore entitled to a credit of the amount of said payments. Further, that the Southern Mantel & Tile Company contracted with the Tennessee Producers’ Marble Company, one of the plaintiffs in this suit, to do certain work, and furnish certain material to be used in the said annex to the federal building at Jackson, Miss., for the sum of $1,150, of which $231.92 had been paid by the Southern Mantel & Tile Company, leaving a balance of $918.08 due and unpaid to the Tennessee Producers’ Marble Company, and that this balance owing by the Southern Mantel & Tile Company to the Tennessee Producers’ Marble Company would have to be reduced from any balance which would otherwise be coming to the Southern Mantel & Tile Company, or the State Bank & Trust Company, its assignee. And, finally, that the assignee, the State Bank & Trust Company, has no right of action under the statute sued on in this cause.

The declaration of the Tennessee Producers’ Marble Company was filed in court on November 16, 1911, and afterwards, December 16, 1911, upon an order of the court, the State Bank & Trust Company was permitted to file its claim in this action.

[1] While there may be difficult questions raised in this contro[432]*432versy respecting the rights of the State Bank & Trust Company, assignee óf Southern Mantel & Tile Company, it is clear that the plaintiff Tennessee Producers’ Mai-ble Company is entitled under the statute (Act Feb. 24, 1905, c. 778, 33 Stat. 811 [U. S. Comp. St. Supp. 1911, p. 1071]) to recover its debt with interest for the proper amount of its account, as the work and material furnished was used in the United States courthouse and post office building at Jackson, and worth the sum charged. The right to so recover is admitted by all the parties to this action; but it is contended by the defendant surety company and the State Bank & Trust Company that the alleged damages sustained by the Southern Mantel & Tile Company should be deducted from the amount claimed by the marble company.

From the proof, it appears that there was some delay in the shipments of marble from the quarries of the Tennessee Producers’ Marble Company, which undoubtedly delayed the Southern Mantel & Tile Company in the completion of its contract. On the other hand, it also appears that the time of delivery of the marble was not specified in the contract; that the marble as- it came was accepted and used; and in a letter under date of December 1, 1910, to the maihle company, the Southern Mantel & Tile Company promised to pay the full amount of its debt. In this letter, no expression hinting at damage for delay occurs. As this letter was the last in point of time introduced, it is presumably the last word from this corporation before its untimely financial dissolution. This letter reads as follows: ■

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Smith v. Clopton
48 Miss. 66 (Mississippi Supreme Court, 1873)

Cite This Page — Counsel Stack

Bluebook (online)
197 F. 429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-tennessee-producers-marble-co-v-empire-state-mssd-1912.