United States ex rel. Spector v. Fusco-Amatruda Co.

239 F. Supp. 990, 1965 U.S. Dist. LEXIS 7487
CourtDistrict Court, D. Connecticut
DecidedApril 5, 1965
DocketCiv. No. 9385
StatusPublished
Cited by2 cases

This text of 239 F. Supp. 990 (United States ex rel. Spector v. Fusco-Amatruda Co.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Spector v. Fusco-Amatruda Co., 239 F. Supp. 990, 1965 U.S. Dist. LEXIS 7487 (D. Conn. 1965).

Opinion

ZAMPANO, District Judge.

In this action before the Court without a jury the plaintiff, Howard Spector, seeks recovery in contract. from The Fusco-Amatruda Company, hereinafter referred to as defendant, and The Travelers Indemnity Company, as surety, under the provisions of the Miller Act, 40 U.S.C. § 270 b.

During the year 1960, the defendant was awarded a government contract for the construction of navy barracks on an eleven acre tract owned by the government in New London, Connecticut. As part of the work the defendant was required to purchase and spread loam in preparation for the seeding of lawns. Bids were solicited from several subcontractors.

In early March, 1961, the plaintiff, Howard Spector, a contractor in the business of selling and spreading loam, conferred with Philip Fusco, the defendant’s job superintendent on the project, concerning a bid for the subcontract. There is no dispute that after some negotiations Spector and Fusco agreed on a price of $2.50 per cubic yard of loam delivered to the site. With respect to the cost of spreading the loam, however, there is a serious conflict as to the agreement between the parties.

Spector testified he quoted a price of $.75 per square yard of area covered by loam while Fusco insists the bid was $.75 per cubic yard of loam spread. Under the facts of this case, the cost of spreading the loam measured on a square yard basis is approximately nine times greater than the price figured on a cubic yard basis. The Court adopts neither party’s version of this conversation. Rather, it is found more probable that the terms “cubic” or “square” were not specified by either man and negotiations were carried out in the “talk of the trade” language of “yards” only.

Fusco then telephoned the defendant’s home office and both Fusco and Spector discussed the terms of the subcontract with Charles Torcellini, the defendant’s job coordinator. Torcellini thereafter drafted and caused to be typed a contract which was subsequently signed by the parties. The contract, in pertinent part, read as follows:

“a. Additional topsoil, as required to provide a minimum depth of 4-inches shall be furnished by the contractor from approved sources. The topsoil shall be a natural, fertile, friable surface soil, without toxic substances injurious to vegetative growth, and shall be obtained from a well-drained arable site. It shall be clean and free from clay lumps, stone, clods, stumps, weed clumps, roots, sticks, extraneous debris, other objectionable matter one inch or more in diameter, or any other material which might be harmful to plant growth.
“Payments for above topsoil loam to be net 30 days after delivery.
“Optional Agreement.
“You agree to furnish all labor, tools and equipment to machine spread and hand rake topsoil loam for sum of Seventy Five Cents ($0.75) per square yard of area. Spreading of topsoil loam is optional with our firm.”

It is noted that the written instrument contains the words “($0.75) per square yard of area.”

Spector began furnishing loam on June 21, 1961 and billed the defendant for these deliveries on June 30, 1961 and on July 31, 1961. Pursuant to the first invoice, he was paid the sum of $6,000 on account. Although Spector commenced spreading operations in June, it was not until August 18, 1961 that an invoice reflected a charge for this work.

In the meantime, on or about August 8, 1961, when his work was 90% completed, Spector telephoned Torcellini and [992]*992requested a partial payment of $13,000 for the spreading of loam operation. Torcellini replied there had to be a mistake because the total payment for the entire job, including loam and spreading, was estimated by the defendant at less than $13,000. After reviewing the price specifications in the written contract at Spector’s suggestion, Torcellini referred the matter to officers of the defendant.

On August 9, 1961, Thomas Amatruda, president of the defendant, met Spector on the job site to discuss the dispute. Amatruda reiterated to Spector that there was a mistake in the agreement with respect to the measurement scale to determine the price of spreading the loam. Spector replied, in effect, “a contract is a contract” and demanded payment pursuant to its terns. Moreover, Spector stated the reasonable value of the work he was required to perform to prepare the site for the spreading operations far exceeded the price offered by the defendant. Unable to resolve the disagreement, Spector stopped work and left the project. This lawsuit followed.

Plaintiff claims there is an unpaid balance for work performed under the terms of the written contract in the amount of $26,255.75. Defendant, seeking reformation of the contract, alleges defenses of a mutual mistake of the parties and, in the alternative, a unilateral mistake by the defendant which was known to the plaintiff and not disclosed to the defendant.

The evidence is abundant that the defendant never intended to enter a contract with the plaintiff for the spreading of loam based on a “square yard” price formula. In its long history as a general contractor it never paid a subcontractor for loam spreading operations by such a measurement. Its estimate for the loam and spreading costs was far less than the plaintiff’s charges under the terms of the contract. Moreover, the defendant rejected two bids for the same work from two other reputable subcontractors which were far less than the prices claimed by the plaintiff: Savin Bros. Construction Company bid $3.90 per cubic yard for furnishing and spreading the loam, ascribing $2.55 per cubic yard to furnish and place loam and $1.35 per cubic yard to spread it; Cosgrove Construction Company bid $4.00 a cubic yard for loam delivered and spread, of which $3.10 a cubic yard was for furnishing loam and $.90 a cubic yard was the charge to spread it. Obviously, defendant never intended to pay plaintiff approximately nine times more than it would have had to pay two other available and competent bidders. Additionally, the expert testimony introduced by the defendant was substantially uncontroverted that a charge of $.75 per square yard to spread loam on this project was unconscionably high.

Whether the burden of the faux pas is cast on a negligent or careless scrivener or upon a misunderstanding in the oral transmission of the terms of the agreement, a mistake was made in the contract by the defendant and the Court so finds.

However, this finding in and of itself does not entitle the defendant to the relief it seeks. A contract is not rendered unenforceable or subject to reformation by the mistake of one party in expressing his intention, if the other party has no knowledge of the mistake or if the other party has no reason to believe a mistake was made. Milford Yacht Realty Co. v. Milford Yacht Club, Inc., 136 Conn. 544, 72 A.2d 482 (1950); Snelling v. Merritt, 85 Conn. 83, 81 A. 1039 (1911); 3 Corbin, Contracts, § 608.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John C. Thomas v. Trans World Airlines, Inc.
457 F.2d 1053 (Third Circuit, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
239 F. Supp. 990, 1965 U.S. Dist. LEXIS 7487, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-spector-v-fusco-amatruda-co-ctd-1965.