United States ex rel. Robert S. Green, Inc. v. C. & W. Const. Co.

20 F. Supp. 879, 1937 U.S. Dist. LEXIS 1489
District Court, D. Maryland·Decided October 5, 1937·No. No. 6046·Published·Cited by 1 cases

Opinion

WILLIAM C. COLEMAN, District Judge.

This is a case arising under the Heard Act, 40 U.S.C.A. § 270 (repealed in 1935 [49 Stat. 794, 40 U.S.C.A. § 270a and note et seq.] except with respect to certain current contracts, such as those in the present proceeding), providing for the protection of persons furnishing material and labor for the construction of public works.

The present plaintiff, the Pennsylvania Railroad Company, is one of many interveners, pursuant to the terms of this act, against the construction company and its surety, and claims that it has furnished “labor” for the construction company in connection with the erection of certain government buildings at Aberdeen, Md. That is, it would have this court construe [880] the word “labor” as used in this act to cover freight and demurrage charges for goods transported by it for the contractor. The defendant company has demurred to the petition of this intervener on the ground that the freight and demurrage charges do not constitute “labor” within the meaning of the act. This court feels that the demurrer should be sustained.

The precise question appears, from the reported cases, to be original in this circuit. At least, the Circuit Court of Appeals for this circuit has never passed upon this precise point arising under the Heard Act. Nevertheless, we believe that that court, in the case of Maryland Casualty Company v. Ohio River Gravel Company, 20 F.(2d) 514; Id. (C.C.A.) 21 F.(2d) 744, has expressed itself very definitely as. supporting the view which we now take in sustaining the demurrer. The Circuit Court of Appeals there was dealing with a state statute and also with a case where the claimant of the freight charges was not, as here, the common carrier itself, but the seller of materials on which he was required to pay freight as part of their cost. The case of Mandel v. United States, a decision of the Third Circuit Court of Appeals, reported in 4 F.(2d) 629, in which certiorari, by the Supreme Court, was denied (see 268 U.S. 698, 45 S.Ct. 515, 69 L.Ed. 1163), and similar decisions were carefuly considered, and this factual distinction stressed as the basis for allowing recovery of the freight charges.

In the Mandel Case the precise question which we now have before us was at issue, and the claim was brought” in the precise way, namely, by a railroad company. There the court said, 4 F.(2d) 629, at page 631: “The question therefore is: Was the claim of the railroad for freight and demurrage recoverable tinder the statutory bond, conditioned that the contractors ‘shall promptly make payments to all persons supplying him or them labor and materials in the prosecution of the work provided for in such contract’? The court below allowed these items but we cannot accede to this view. The words ‘labor and material,’ used by Congress in this statute, are plain words of well-understood meaning, and in the common use and acceptance car demurrage and car freight are not described or embraced by the words ‘labor and material.’ Moreover, there is no call for the exercise of judicial construction to give to demurrage and freight the protection of this statutory bond. There was a real hardship to labor and material men who worked upon, or furnished material for, a structure or improvement on government property. They could have no lien and no way of protecting themselves. Accordingly the statute required from the contractor a statutory bond and approved surety responsibility for the protection of unprotected labor and material. But the railroad required no such protection. It could refuse to deliver to the contractor until both freight and demurrage were paid. Hence neither the words of the bond allow, nor the spirit and purpose of the law require, that judicial construction to enlarge or construe the words ‘labor and material’ so as to include freight and demurrage.”

From the language employed in the Ohio River Gravel Company Case by the Fourth Circuit Court of Appeals, particularly when that case was before it on rehearing (see 21 F.(2d) 744), there can be no doubt that its ruling was not intended to apply to the present state of facts. The court there said, pages 744, 745:

“We have carefully considered all of the questions raised in the petition for rehearing, but we see no reason to grant the petition as all of them were given careful consideration on the original hearing. We desire to notice, however, the statement in the petition that the decision of the court with respect to the freight included in the claim for sand and gravel conflicts with the decision of the Supreme Court in the case of Title Guaranty & Trust Co. v. Crane Co., 219 U.S. 24, 31 S.Ct. 140, 55 L.Ed. 72, and with the holdings of the Circuit Courts of Appeals of the Third and Fifth Circuits in Mandel v. U. S., 4 F.(2d) 629, and U. S. v. Hyatt, 92 F. [442] 445.
“In the Crane Case, the appeal was by the surety company from a decree allowing a claim for cartage by a transfer company, but disallowing a claim for freight which it had paid. The Supreme Court affirmed the allowance of the claim for cartage, but -the question as to freight was not before it, as the transfer company did not appeal. On that aspect of the case, however, the case before the Circuit Court of Appeals of the Ninth Circuit, Title Guaranty & Trust Co. v. Puget Sound Engine Works, 163 F. 168, was different from the case at bar, in that the person who paid the freight was not the furnisher [881] of materials, nor did he make payment thereof under such circumstances that it became in reality a part of the price of the materials, as in the case at bar.
“The same distinction exists with respect to the cases cited from the Third and Fifth circuits, both of which related to claims by railway companies for freight charges. We were careful to point out this distinction in our original opinion, but that part of the opinion was evidently overlooked by counsel.
“We have examined with some care the cases dealing with the point involved and with kindred points, and we are satisfied, not only that our decision is correct, but also that there is nothing in it which conflicts with any decision of the Supreme Court or of any Circuit Court of Appeals.”

Free access — add to your briefcase to read the full text and ask questions with AI

United States ex rel. Robert S. Green, Inc. v. C. & W. Const. Co., 20 F. Supp. 879, 1937 U.S. Dist. LEXIS 1489 (D. Md. 1937).

20 F. Supp. 879 (United States ex rel. Robert S. Green, Inc. v. C. & W. Const. Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related