This text of 462 F.2d 1098 (United States ex rel. Pembroke Steel Co. v. Phoenix General Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Pembroke Steel Co. v. Phoenix General Construction Co., 462 F.2d 1098 (4th Cir. 1972).

Opinion

PER CURIAM:

Both of these actions were brought by subcontractors under the provisions of the Miller Act, 40 U.S.C. §§ 270a-270d. The prime contract, dated December 2, 1968, was between Phoenix General Construction Company and the United States for performance of certain work at the Vertical Missile Packaging Building, Naval Weapons Station, Charleston, South Carolina. The subcontracts, made December 1968 were between Phoenix, on the one hand, and Pembroke Steel Company and Southern Detailing Company of Savannah, Inc., on the other.

Phoenix and its surety have resisted these suits on the ground that the subcontracts, in effect, stipulate that all disputes between the general and subcontractor must be submitted to the Government, and administratively decided before suit can be brought against Phoenix. In short, the defendants say that the plaintiffs waived their immediate right of action.

[1099]*1099Accordingly, the defendants moved the District Court to stay the prosecution of the suits until the administrative decision was rendered. They conceded that the contractual stipulations tolled the time limitations of the Miller Act. From the denial of their motion, the defendants appeal.

With the appellees, we agree that under the Miller Act the subcontractor has no claim upon the Government. As the Act prescribes, the only remedy is to proceed against the prime contractor and his surety. By law, the Government does not recognize the subcontractor, and there can be no submission to the Government for resolution of disputes between the subcontracting parties. While the right to sue the prime contractor may be waived “by clear and express provisions” in the subcontract, we observe no such waiver here, express or implied. United States for Use of B’s Co. v. Cleveland Electric Co., 373 F. 2d 585 (4 Cir. 1967); Beacon Construction Co. v. Prepakt Concrete Co., 375 F. 2d 977 (1 Cir. 1967). The District Court quite correctly declined the stay.

Affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
462 F.2d 1098, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-pembroke-steel-co-v-phoenix-general-construction-ca4-1972.