United States ex rel. Moretrench American Corp. v. McClure Electrical Constructors, Inc.

402 F. Supp. 701, 1975 U.S. Dist. LEXIS 11786
District Court, N.D. Florida·Decided June 20, 1975·No. No. PCA 74-105·Published

Opinion

DANIEL HOLCOMBE THOMAS, District Judge.

The above-styled cause was heard by the Court without a jury and taken under submission on April 23, 1975. Having considered the testimony, exhibits, stipulations and arguments of counsel, the Court makes the following findings of fact and conclusions of law.

FINDINGS OF FACT

1. This action was brought under the Miller Act, 40 U.S.C. 270a-270d, by the use plaintiff Moretrench American Corporation (Moretrench) seeking to recover from the defendants McClure Electrical Constructors, Inc. (McClure) and the Travelers Indemnity Company (Travelers) the sum of $16,643.18 as the balance due on a rental contract for a wellpoint system, including certain service and repair invoices, furnished by Moretrench to McClure.

2. The defendant McClure, and thereby Travelers, asserts in defense a failure of consideration on the part of Moretrench in that allegedly the well-point system did not function properly. McClure therefore claims that it is entitled to a substantial offset against the amount owed Moretrench under the rental contract. However, McClure does not assert any counterclaim against Moretrench for any damages beyond the aforementioned offset.

3. Ranger Construction Company (Ranger), a general contractor, entered [703]*703into a contract with the United States America to perform construction work on an aircraft assembly hangar at the Naval Air Rework Facility, Pensacola, Florida. The defendant Travelers was surety on the payment bond furnished to the United States government by Ranger pursuant to the requirements of 40 U.S. C. § 270b(a). In pursuit of its general contract, Ranger entered into an electrical subcontract with the defendant McClure. Subsequently, on July 17, 1973, McClure entered into a contract with Moretrench in which Moretrench agreed to rent to McClure a wellpoint system to be used in the performance of its electrical subcontract and McClure agreed to pay the rental price as set forth in the contract. The Pensacola area has a high water table and sandy, marshy soil. Use of a wellpoint system was necessary in order for McClure to proceed with its subcontract which involved a large amount of underground electrical work. of

4. Under the rental contract McClure agreed to pay rent at the following rates, plus tax: $3,815.00 for the first 30 day period; $2,225.00 for the second 30 day period; and $1,981.00 for each succeeding 30 day period.1 Other pertinent provisions of the contract which read as follows:

8. This agreement (together with the supplemental conditions, etc., as printed on the back of this sheet) contains all of the agreement between Lessor and Lessee and is to be binding upon the heirs, executors, administrators, successors, and assigns of both parties hereto, when approved by Lessor at its Main Office at Rockaway, New Jersey. No representations or statements have been made by Lessor concerning the Goods except as herein stated, and no warranty, express or implied, by Lessor, arises apart from this writing.
19. Lessee will pay, upon receipt of invoice, for labor parts, transportation and living expenses, in connection with any on-job repairs required, unless such repairs are required as the result of defects in the equipment when originally furnished. Lessee will also pay for any on-job services by others, when such services are not authorized by the Lessor in writing.
23. The liability of Lessor to Lessee is expressly limited to the free replacement (f. o. b. point of shipment) of any defective part or parts of the equipment furnished under or subsequent to this agreement on receipt by Lessor of said defective part or parts f. o. b. Rockaway, New Jersey, provided such defect is not caused by misuse or neglect on the part of Lessee.
Lessor makes no warranty of merchantability of the Goods or of their fitness for any purpose, nor any other warranty of any kind, express or implied, except that Lessor agrees to replace, without charge, f. o. b. point of shipment, any part or parts adjudged by the Lessor to be defective; provided such defect is not caused by misuse or neglect on the part of Lessee. Said guaranty to be Lessee’s sole and exclusive remedy. The Lessor shall not be liable for damages due to delays arising from goods or equipment supplied hereunder nor will any allowance be granted for repairs or alterations made by the Lessee without the written consent of the Lessor.

5. A stipulation was entered by all parties that, assuming the wellpoint system was satisfactory, the unpaid amount due on the rental contract from McClure to Moretrench would be $16,643.18. This figure takes into account payments made by. McClure totaling $2,245.15.

6. The wellpoint system was delivered to McClure in July 1973, with the rental period commencing on the 26th of that month. On March 4, 1974, More-trench terminated' the rental contract for failure to pay rent, and the equip[704]*704ment was returned to Moretrench by McClure on March 15, 1974.

7. On several occasions between July 26, 1973, and March 4, 1974, the well-point system either failed to operate or, although operating, failed to perform to the' satisfaction of McClure. A factual dispute arose between the parties as to the reasons for the failure. It is this factual dispute which constitutes the heart of this litigation.

8. In support of its right to an offset, McClure presented the testimony of its president, Mr. T. D. McClure, and its on-the-job superintendent, Mr. G. L. Gates. These witnesses testified that during the rental period, McClure experienced numerous “down” days during which it could not proceed with its underground construction work due to the failure of the wellpoint system either to operate or, if operating, to sufficiently drain the construction area. As asserted by McClure, these “down” days were as follows: August 7, 8, 20, 21, 22 and 23; September 5, 8, and 19; October 16 and 22; November 13, 16, 17, 19, 25, 26, 27, 28, 29 and 30; and December 3, 4, 5, 6, 7, 10, 11, 12, 13, 14, 17, 18 and 19. After December 19, 1973, McClure ceased using the Moretrench equipment but did not return it to Moretrench until after Moretrench terminated the contract on March 4, 1974.

9. McClure asserts that on each above listed “down” day the wellpoint system failed to function properly due solely to the poor quality of the equipment furnished by Moretrench. However, based upon the evidence as presented at trial, the Court finds that on some of. the occasions cited the malfunctioning of the system resulted from either improper maintenance or improper use of the equipment, both matters within the responsibilities of McClure as set out in the contract. In specific, the Court makes the following findings as to the cause of particular “down” days:

(a) Due to faulty equipment:
Fuel pump — August 7, 8
Vacuum pump — December 3, 4, 5, 6, 7, 10, 11, 12
Power takeoff unit (clutch) — December 13, 14 2
Engine — December 18, 19
(b) Due to improper use or maintenance :

Free access — add to your briefcase to read the full text and ask questions with AI

United States ex rel. Moretrench American Corp. v. McClure Electrical Constructors, Inc., 402 F. Supp. 701, 1975 U.S. Dist. LEXIS 11786 (N.D. Fla. 1975).

402 F. Supp. 701 (United States ex rel. Moretrench American Corp. v. McClure Electrical Constructors, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ivy H. Smith Company v. Moretrench Corporation
253 F.2d 688 (Fifth Circuit, 1958)