United States Ex Rel. McLain v. Fluor Enterprises, Inc.

681 F. App'x 355
CourtCourt of Appeals for the Fifth Circuit
DecidedMarch 10, 2017
Docket16-30328
StatusUnpublished
Cited by1 cases

This text of 681 F. App'x 355 (United States Ex Rel. McLain v. Fluor Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. McLain v. Fluor Enterprises, Inc., 681 F. App'x 355 (5th Cir. 2017).

Opinion

PER CURIAM: *

Relators Terry D. McLain and J. Len Hodges filed the instant qui tam action under the False Claims Act (“FCA”), 31 U.S.C. § 3729, alleging that defendants Fluor Enterprises, Inc. (“Fluor”), CH2M Hill' Constructors, Inc. (“CH2M”), and Shaw Environmental, Inc. (“Shaw”) submitted to the government false claims for payments for temporary housing units (“THUs”). Their false claim allegation is based on defendants’ failure to comply with Louisiana liquefied petroleum (“LP”) statutes when installing tens of thousands of THUs through their subcontractors in the aftermath of Hurricanes Katrina and Rita.

The district court granted summary judgment in favor of Fluor, Shaw, and CH2M (collectively, “the Contractors”) and dismissed the relators’ complaint. The re-lators timely appeal. Their primary argument is that the installation contracts at issue were “null” under Louisiana law, and any claims for payment based on those *357 null contracts were therefore “false” claims in violation of the FCA. We AFFIRM. ,

I.

In the wake of Hurricane Katrina—one of the most destructive natural disasters in our nation’s history—hundreds of thousands of individuals were left without then-homes. Less than a month later, Hurricane Rita wreaked additional havoc on an already storm-ravaged coast. On the day Katrina made landfall, August 29, 2005, FEMA issued Solicitation No. HSFEHQ-05-R-0046, which requested proposals to provide disaster relief services under FEMA’s Individual Assistance program. Between September 2005 and November 2006, FEMA facilitated the installation of over 100,000 THUs in areas along the Gulf Coast that were impacted by Hurricanes Katrina and Rita. After their proposals were accepted, defendants Fluor, CH2M, and Shaw entered into contracts with FEMA to “haul and install” THUs for Louisiana residents who were displaced by the devastation from the hurricanes. Inside the trailers, appliances and plumbing—from the stoves, to the refrigerators, to the running water—were fueled by LP gas. The contracts between FEMA and the Contractors were “cost-reimbursement contracts on a cost-plus-fbced-fee basis.” Under these contracts, CH2M, Shaw, and Fluor were entitled to receive payment for works in progress and other costs associated with fulfilling the obligations of the contracts they had with the Government.

FEMA directed each of the Contractors to work to get as many “heads in beds” as quickly as possible. Fluor, CH2M, and Shaw worked through subcontractors to install these housing units. The subcontracts with the installers contained language requiring the subcontractor installers to perform work “in accordance with all applicable federal, state, and local codes and regulations.” In pertinent part, the subcontracts contained some variation of the following language:

All work performed shall be in accordance with all applicable federal, state and local codes and regulations. The provisions herein and typical details shall not be construed as lowering standards established by local laws, ordinances or regulations.
The contractor [the installers] must be, or have employed, registered licensed technicians ... to conform to State and local requirements for installing and/or hooking up systems or repairing defects involving their particular trade. It is the contractor’s responsibility to obtain all proper licenses and permits to set-up the units. Locally required permits shall be applied for within 3 working days of work order issuance. Units shall be ready to occupy within 3 days of permit issuance.
The contractor shall be responsible for obtaining necessary permits associated with placing and installing the unit and utility installation. Permits shall be applied for within 3 working days of work order issuance. Unit shall be ready to occupy within 3 days of permit issuance ....

In January 2006, the Liquefied Petroleum Gas Commission (“LPGC”) communicated to CH2M, Shaw, and Fluor that their THU installations were not in compliance with Louisiana LP regulations due to the subcontractors’ lack of Class II LP gas installation permits. 1 Nevertheless, FEMA *358 instructed the Contractors to continue the installations in accordance with the regulatory requirements and then retrofit THUs that had already been installed to render them compliant with the regulations. Fluor, Shaw, and CH2M'also began applying for the proper permits once the LPGC asserted that they were violating the Louisiana LP gas regulations. 2 Although each defendant received citations related to these violations, CH2M, Shaw, and Fluor worked with the LPGC to reach Settlement Agreements that, inter alia, dismissed the citations, acknowledged that a dispute existed as to whether “certain rules and regulations promulgated by the LPGC” applied to the Contractors, and in the case of CH2M, noted that CH2M had “in good faith achieved compliance with the LPGC’s rules and regulations.”

Relators McLain and Hodges, both LPGC inspectors, filed the instant qui tarn action under seal in the Eastern District of Louisiana on December 21, 2006. The government investigated the allegations pursuant to 31 U.S.C. § 3730(b) and declined to intervene in December 2012. The case was later unsealed and the First Amended Complaint was served upon the defendants in early 2013.

Over the course of almost two years, a number of Counts from the First Amended Complaint were dismissed. In an Order dated August 8, 2013, the district court dismissed Counts 3, 5, 6, and 9. In November 2014, the district court issued an Order addressing Motions to Dismiss by Fluor and CH2M, Motions for Summary Judgment by Fluor and Shaw, and a Motion to Strike and Amend the Complaint by the relators. The motions for summary judgment were granted in part and denied in part, while the remaining motions were denied. The court granted the relators leave to file a Second Amended Complaint “setting forth specific facts showing that the defendants failed to obligate their subcontractors to comply with state LP gas statutes and regulations." U.S. ex rel. McLain v. Fluor Enterprises, Inc., No. 06-11229, 2015 WL 5321692, at *1 (E.D. La. Sept. 11, 2015); see also U.S. ex rel. McLain v. Fluor Enterprises, Inc., 60 F.Supp.3d 705, 722 (E.D. La. 2014).

The Second Amended Complaint is the operative complaint in this case. In the district court’s September 2015 Order, it acknowledged that the relators went outside the scope of the leave given to them by the court, alleging not simply a theory of nullity, but also that “defendants misrepresented to FEMA that their subcontractors and staff had the proper training and licensing needed to perform LP gas installations or were in the process of receiving these qualifications.” McLain, 2015 WL 5321692 at *2. Furthermore, in its Order, the district court granted summary judgment to each Contractor as to the “nullity” claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Killion v. Truist Bank
N.D. Texas, 2025

Cite This Page — Counsel Stack

Bluebook (online)
681 F. App'x 355, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-mclain-v-fluor-enterprises-inc-ca5-2017.