United States ex rel. Kirby v. John A. Johnson & Sons

137 F. Supp. 881, 1954 U.S. Dist. LEXIS 2212
CourtDistrict Court, E.D. Tennessee
DecidedNovember 4, 1954
DocketCiv. No. 1620
StatusPublished
Cited by1 cases

This text of 137 F. Supp. 881 (United States ex rel. Kirby v. John A. Johnson & Sons) is published on Counsel Stack Legal Research, covering District Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Kirby v. John A. Johnson & Sons, 137 F. Supp. 881, 1954 U.S. Dist. LEXIS 2212 (E.D. Tenn. 1954).

Opinion

ROBERT L. TAYLOR, District Judge.

This is an action to recover amounts allegedly due Ross Construction Company, hereinafter referred to as Ross, from John A. Johnson & Sons, Inc., hereinafter referred to as Johnson, other defendants being surety companies. Ross was a subcontractor with Johnson, prime contractor with the Atomic Energy Commission, hereinafter referred to as the Government, for construction work at Oak Ridge, Tennessee. Several subcontracts had been entered into between Ross and Johnson, but those on which sums are claimed by Ross as due and unpaid will be considered separately. In addition to accounts that arose under written contracts, certain claims are made with respect to items based either upon oral contract or upon usage between [883]*883the parties. These, too, will be considered apart from the others.

Miscellaneous Claim for $860.13

It appears that Ross and Johnson, in accordance with custom among contractors and subcontractors, operated on a give and take arrangement as to fuel, grease, and other materials, one borrowing from another as need arose and convenience was best served. While accounts thus created between borrowers usually kept themselves within reasonable balance, it is alleged by Ross that end of relations between Ross and Johnson left Johnson owing Ross $860.13. Plaintiff’s exhibit 16 is filed in support of this claim. However, exhibit 16, made up of two yellow sheets, does not consist of original entries, its original source being a number of cards attached to it. Comparison of the yellow sheets with the cards leaves the claim unsupported, except in the sum of $385.25.

Johnson admittedly has no records for or against this claim, but would repel the claim on the ground that Ross made no demand for payment. Failure of demand for payment might in orderly dealings be at least persuasive as a defense, but the record in this and other connections shows that both parties dealt with each other in a surprisingly unbusinesslike manner, neither giving the other notice in a number of situations when notice should have been given.

This claim should be allowed in the sum of $385.25.

50-House Subcontract Claim for $1,098.00

This claim is based upon oral contract for moving dirt for use in filling around 50 houses, payment to be made by Johnson to Ross on an hourly rental for machinery used in the work by Ross. This claim is supported by plaintiff’s exhibit 15, which consists of one yellow sheet with attached cards. The items on the yellow sheet add up to the amount claimed. However, they are not original entries, but are derived from the cards, which support- only $574 of the total.

Johnson’s defense follows the pattern of the preceding claim and is rejected for the reasons there stated.

This claim should be allowed in the sum of $574.

Contract No. 101 — Claim for $39,349.86

This contract relates to work done by Ross in connection with construction of 500 houses. It has been stipulated by the parties that there remains due Ross on this contract the sum of $39,349.86 from Johnson.

Contract No. 125 — Claim for $3,583.59

This contract relates to work done by Ross in connection with construction of what is known as the Bulk Shielding Plant. Proof of most significance in relation to this claim is in explanation of plaintiff’s exhibit 5 and defendant’s exhibit 32. Johnson admits that there remains due Ross $2,536.24 under this contract. The parties disagree as to items designated as “borrow fill” and “rock excavation.”

Ross! exhibit 5, a collective exhibit consisting of statements of work done and applications for payment, shows 5,100 cubic yards as the quantity of borrow fill. Defendant’s exhibit 32 shows the same quantity, but from this quantity Johnson deducts 686 cubic yards which it says represented rock furnished by Johnson. This deduction caused a difference of $686 between the amount claimed for this work and that which is admittedly due.

Plaintiff’s statement and application for payment bear date of June 19, 1951. They bear designation as estimate No. 4 (final). But estimate No. 3, statement and application for payment dated November 6, 1950, shows borrow fill completed as of that date as 4,648 cubic yards, which is only 452 cubic yards less than the final estimate. This discrepancy casts serious doubt on Johnson’s claim that it furnished 686 cubic yards of the total of 5,100. Moreover, testimony of witnesses is to the effect that Ross com[884]*884pleted the 5,100 'cubic yards and that any work done by Johnson under this heading was in the nature of additional work made necessary by rains and not chargeable to Ross. This item of set-off, accordingly, should be disallowed.

The second point of disagreement relates to rock excavation. Ross’ statement and application for payment dated June Í9, 1951, exhibit 5, shows the quantity of rock excavation completed as of that date as 389 cubic yards. Johnson’s exhibit 32 shows 323.3 cubic yards. The difference as between the two exhibits represents the sum of $361.-35.

On November 6, 1950, Ross submitted statement and application in which rock excavation is shown as 347 cubic yards completed as of that date. The statement and application of September 8, 1950, shows this same yardage. Johnson’s estiihate of 323.3 cubic yards purportedly was based upon the Government’s final estimate. But the Government’s final estimate, filed as exhibit 33, does not contain the figure 323.3 under any heading. Nor does it list any item of work that can be identified as corresponding to the rock excavation items shown in exhibits 5 and 32. Exhibit 5 was notice to Johnson that Ross was claiming, from September 8, 1950, considerably more than 323.3 cubic yards, and from June 19, 1951, 389 cubic yards. The Government’s final estimate, dated May 9, 1952, recites: “Type of Contract, Lump-Sum-Unit Price.” Absence from this -final estimate of any item that can be identified as the rock excavation in question leaves room for an inference that, the rock excavation in question was a lump-sum item and re-' quired no final estimate.

In further proof of Ross’ claim for $3,583.59 is plaintiff’s exhibit 7. This is a ledger entry of June 19, 1951, which shows that the balance due on the Bulk Shielding Plant is $3,583.59. Although evidence is in conflict and both inadequate and difficult to follow, there is a preponderance in favor of Ross in support of the full amount claimed.

Accordingly, this claim should be allowed in the amount of $3,583.59.

Contract No. 112 — Claim for $22,124.97

This contract relates to work done by Ross in connection with construction of a high school building. Ross claims $22,124.97 as due and unpaid on this contract. Extensive proof has been introduced, much of which is incapable of exact application. However, two exhibits point to an answer to this particular claim.

Johnson admits that the amount due Ross on contract 112 is $11,112. Ross’ ledger sheet, exhibit 10, shows a balance, due of $19,061.35, the Jast entry thereon being June 1, 1951. Yet the statement of work done and the application for payment dated June 1, 1951, are not in accord with the ledger balance. The statement and application, exhibit 9, show value of work completed as of June 1, 1951, as $105,508.34. With this figure reduced by retainage of $6,-938.66 and previous payments of $91,-233.77, the amount applied for is $7,-335.91.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
137 F. Supp. 881, 1954 U.S. Dist. LEXIS 2212, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-kirby-v-john-a-johnson-sons-tned-1954.