United States ex rel. J. E. Sadler & Co. v. W. H. French Dredging & Wrecking Co.

52 F.2d 235, 1931 U.S. Dist. LEXIS 1626
CourtDistrict Court, D. Delaware
DecidedAugust 26, 1931
DocketNo. 3
StatusPublished
Cited by6 cases

This text of 52 F.2d 235 (United States ex rel. J. E. Sadler & Co. v. W. H. French Dredging & Wrecking Co.) is published on Counsel Stack Legal Research, covering District Court, D. Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. J. E. Sadler & Co. v. W. H. French Dredging & Wrecking Co., 52 F.2d 235, 1931 U.S. Dist. LEXIS 1626 (D. Del. 1931).

Opinion

NIELDS, District Judge.

The W. H. French Dredging & Wrecking Company, Inc., on July 7, 1927, entered into a contract with the United States government for the performance of certain dredging work. Before commencing work under the contract, the contractor, pursuant to the provisions of section'270, title 40, USCA, entered into the usual contractor’s bond. This action was brought July 23,1929, in the name of the United States for the use of George W. Clark and Gertrude Sadler, copartners, trading as J. E. Sadler & Co., against W. H. French Dredging So Wrecking Company, Inc., the contractor* and United States Fidelity So Guaranty Company, its surety. Harry Bose and Norbom Engineering Company have intervened.' No action has been instituted by the United States in its own behalf upon the bond of the contractor.

No service was had upon the dredging company and it has not appeared. The ease was tried to the court without the intervention of a jury.

' Findings of Fact.

General.

•1. That W. H.. French Dredging So Wrecking Company, Inc., entered into a contract with the United States of America on July 7,1927, for dredging the old entrance to the inland waterway from the Delaware river to Chesapeake Bay,'known as the Chesapeake and Delaware Canal.

2. That the bond contemplated by section 270, title 40, USCA, was duly given by the contractor.

3. That the bond provided that the contractor “shall promptly make payments to all persons supplying the principal with labor and materials in the prosecution of the work provided for in said contract.”

4. That the work contemplated by the contract was completed on or about May 3, 1928.

5. That on January 17, 1929, the Comptroller General of the United States issued his “Certificate of Settlement,” in which it is stated: “I certify that I have examined and settled the elaim(s) of-the United States against W. H. French Dredging & Wrecking Co., Inc., * * * debtor and find the sum of Two Thousand Nine Hundred Sixty-two Dollars and Twenty-five cents is due the United States from the above-named debtor.”

6. That in arriving at this balance, the Comptroller General took into consideration a certain contract between the same parties for dredging work in the Onancoek river, Va., under which there was found a balance due the United States of $3,330.10, and the contract in question in this suit under which there was found a balance due the contractor of $367.85, leaving a net balance due the United States of $2,962.25.

7. That there was endorsed across the face of the above-mentioned certificate of settlement dated January 17, 1929, the words and figures, “Cancelled. See A-24614, O. M. 6/20/29.”

8. That on August 22, 1929, the Comptroller General of the United States issued his “Certificate of Settlement” in which it is stated: “I certify that I have examined and settled the claim (s) of Bobert W. Buffin s, * * Trustee in Bankruptcy for W. H. French Dredging and Wrecking Company, Inc., Bankrupt, against the United States * * * and find that the sum of three hundred sixty-seven dollars and eighty-five cents is due from the United States to said claimant.”

Claim of J. E. Sadler & Co.

1. That claimant furnished materials and supplies which were consumed in the prosecution of the work provided for in the contract in question, and were necessary to and formed an integral part of the work.

[237]*2372. That claimant notified the United States Fidelity & Guaranty Company, surety, by written notice dated July 18, 1928, of the amount and nature of its claim and demanded payment.

3. That the balance due the claimant is the sum of $2,806.51, with interest from July 23, 1929, the date of the institution of this suit.

Claim of Harry Rose.

1. That claimant furnished groceries and provisions to the dredging company, and such supplies were consumed in feeding the crews of the dredges employed by the contractor in the prosecution of the work provided for in the contract in question, and were necessary to and formed an integral part of the work.

2. That the amount due claimant for such supplies is the sum of $1,497.10, with interest from October 7, 1929, the date of the filing of the petition of intervention.

Claim of Norbom Engineering Co.

1. That there is no satisfactory evidence that the materials alleged to have been furnished to the dredging company were ordered by a responsible official of that company, or that such materials were delivered to and used on the dredges in prosecuting the, work provided for in the contract in question.

The act of Congress (40 USCA § 270) provides that: “If no suit should be brought by the United States within six months from the completion and final settlement of said contract, then the person or persons supplying the contractor with labor and materials shall, * * * be furnished with a certified copy of said contract and bond, upon which he or they shall have a right of action,” ■etc. The act also provides that suit by a creditor must be brought “within one year after the performance and final settlement” of a contract. It is admitted that work under the contract was completed on or about May 3, 1928. It is likewise admitted that no suit was brought by the United States on its own behalf.

As the defendant does not raise any question as to the furnishing of the materials and supplies or that the prices charged therefor were reasonable and proper, there are but two questions for decision: First, was the suit brought prematurely; and, second, if not, were the labor or materials furnished to the contractor by the respective claimants labor' and materials within the meaning of the above-mentioned act of Congress. The determining factor in answering the first question is when was “final settlement” made as that term is used in the act of Congress. The only evidence as to when final settlement was made is embodied in the two certificates of the Comptroller General (Plaintiff’s Exhibit No. 2 and Defendants’ Exhibit No. 2) and papers annexed thereto. The plaintiff and interveners contend that the date of final settlement was January 17, 1929, the date of the issuance of the first certificate of settlement. . On the other hand, the surety company contends that this certificate was canceled June 20, 1929, and that final settlement was not had until the issuance of the second certificate on August 22, 1929.

The general rule for ascertaining the date of “final settlement,” as those words are used in this act, has been definitely determined by the Supreme Court in Illinois Surety Co. v. U. S. to use of Peeler, 240 U. S. 214, 36 S. Ct. 321, 323, 60 L. Ed. 609. In that case, Chief Justice Hughes said: “The pivotal words are not ‘final payment,’ but ‘final settlement,’ and in°view of the significance of the latter term in administrative practice, it is hardly likely that it would have been used had it been intended to denote payment. * * •* We think that the words ‘final settlement’ in the act of 1905 had reference to the time of this determination when, so far as the government was concerned, the amount which it was finally bound to pay or entitled to receive was fixed administratively by the proper authority.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Golden West Construction Company v. United States
304 F.2d 753 (Tenth Circuit, 1962)
United States ex rel. Shlager v. MacNeil Bros.
27 F. Supp. 180 (D. Massachusetts, 1939)
United States v. Seaboard Surety Co.
26 F. Supp. 681 (D. Montana, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
52 F.2d 235, 1931 U.S. Dist. LEXIS 1626, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-j-e-sadler-co-v-w-h-french-dredging-ded-1931.