United States ex rel. Industrial Contractors Corp. v. William Clairmont, Inc.

341 F. Supp. 940, 1972 U.S. Dist. LEXIS 14367
CourtDistrict Court, D. Nebraska
DecidedApril 3, 1972
DocketCiv. No. 71-0-324
StatusPublished
Cited by3 cases

This text of 341 F. Supp. 940 (United States ex rel. Industrial Contractors Corp. v. William Clairmont, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Nebraska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Industrial Contractors Corp. v. William Clairmont, Inc., 341 F. Supp. 940, 1972 U.S. Dist. LEXIS 14367 (D. Neb. 1972).

Opinion

MEMORANDUM AND ORDER

DENNEY, District Judge.

This matter comes before the Court on the motion of defendants for an Order staying this action pending the outcome of allegedly applicable contract dispute settlement procedures [Filing # 21],

The first claim of the complaint in this action is brought pursuant to the Miller Act, 40 U.S.C.A. § 270a et seq., against defendant, Clairmont, as prime contractor, and defendant, National Surety, as surety, upon the payment bond thereunder. The second and third claims seek recovery against defendant Clairmont only, in breach of contract and tort (negligence), respectively.

Defendant Clairmont is presently pressing an administrative claim against the government for additional compensation under the prime contract. Defendants argue that certain provisions of the prime contract and subcontract bind plaintiff to await the outcome of the administrative claim procedure and that it would be unfair to require Clairmont to pursue that administrative claim and defend in this action at the same time.

On the other hand, it is plaintiff’s position that the damages sought are not the type of added compensation within the contemplation of the contractual terms and that plaintiff may well cease to exist as a viable business entity if it cannot speedily pursue its claims in this Court.

For the purposes of determining the motion for a stay, the Court will accept the following facts from defendants’ brief in support of the motion as true. The contract and subcontract appended thereto are also accepted as being valid.

Defendant Clairmont entered into Contract No. DACW45-70-C-0042 with the United States through the Corps of Engineers of the United States Army on December 2, 1969. The project which the government sought to pursue was the construction of a new railroad bridge over the Missouri River near Bellevue, Nebraska. Other related temporary and permanent facilities were included in the project.

The government railroad bridge, authorized by the Flood Control Act of 1944, was to be completed, according to [942]*942the contract, as set forth in Paragraph 1 of the Special Provisions of the contract which, unfortunately, were not attached to defendants’ brief. However, the completion date of Industrial Contractors’ work, as set forth in the subcontract, was to be September 15,1970.

For whatever reasons, the work of Industrial Contractors was not completed until subsequent to the contract date. Plaintiff alleges that, due to the acts and omissions of defendant Clairmont, added expenses were incurred in the completion of the subcontract work and that plaintiff was damaged in the amount of $103,262.03. Plaintiff, in its first claim, in addition to the above amount, seeks recovery of $6,039.00, allegedly due under the subcontract as a retained percentage of compensation earned.

Defendants allege that the disputes1 provision of the prime contract is incorporated by reference into the subcontract via the subcontract incorporation2 and changes3 clauses, [943]*943and that plaintiff is contractually bound thereby to await the outcome of the administrative claim which Clairmont has presented to the government.

Defendant recognizes the principle that a disputes clause in a prime government contract will not be held incorporated by reference into a subcontract unless the disputes clause is stated to be incorporated by express language set forth in the subcontract. United States for Use and Benefit of T/N Plumbing & Heating Co. v. Fryd Construction Corp., 423 F.2d 980 [5th Cir. 1970], cert. denied, 400 U.S. 820, 91 S.Ct. 38, 27 L.Ed.2d 48; H. W. Caldwell & Son, Inc. v. United States for Use and Benefit of John H. Moon & Sons, Inc., 407 F.2d 21 [5th Cir. 1969]; United States for Use of B’s Company v. Cleveland Electric Company of South Carolina, 373 F.2d 585 [4th Cir. 1967]; Central Steel Erection Co. v. Will, 304 F.2d 548 [9th Cir. 1962]; and Fanderlik-Locke Co. v. United States for Use of Morgan, 285 F.2d 939 [10th Cir. 1960], cert. denied, 365 U.S. 860, 81 S.Ct. 826, 5 L.Ed.2d 823 [1961].

The language of the changes clause of the subcontract does not persuade the Court that the subcontractor has waived his Miller Act rights. The very title of the clause indicates, as does the language thereafter, that it concerns itself with changes in the work directed by the owner (government) to be performed by the subcontractor. Nowhere in the clause is there any indication that the clause contains a comprehensive dispute settlement procedure, nor is any reference made to the disputes clause of the prime contract.

The following quote from Warrior Constructors, Inc. v. Harders, Inc., 387 F.2d 727, 729 [5th Cir. 1967] sets forth eloquently the law and reasoning behind it in cases such as this:

It is well established that the purpose of the Miller Act is to provide security for those who furnish labor and material in the performance of government contracts, and a liberal construction should be given the Act to accomplish this purpose. The benefits of the Act are not intended for the prime contractor who is required to furnish bond to effectuate its provisions. Since there is no contract, express or implied, between a subcontractor and the goverment, there is no procedure by which the claim of a subcontractor can be presented against the United States except as it may become a claim of the prime contractor. A subcontractor has no standing before the Contracting Officer or the Board of Contract Appeals, and no provision is made for the hearing of disputes between a prime contractor and a subcontractor. The remedy for a subcontractor seeking to recover for labor and materials furnished on a government contract is under the Miller Act, and it has been held that when a prime contractor has a claim for the same amounts pending under the “disputes clause” of the prime contract, a subcontractor’s claim under the Miller Act is not affected.
To insure payment in full for such materials and labor, a general contractor is required to furnish sufficient bond to secure the contract. The right to sue on the surety bond is a right created by statute, and in absence of a novation or clear expression to the contrary, the -contention that there has been a waiver or release of that right must fail. If a subcontractor is not paid, his only remedy is suit under the Act, within the one year period specified by the Act, and no drastic curtailment of these rights will be read into a general agreement absent clear expression to that effect. [Footnotes omitted]

Here, plaintiff asserts that its claim is not based upon changes ordered by the government, but upon delay and malfeasance of the prime contractor. It is obvious that this aspect of plaintiff’s claim will not and could not be presented to the government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
341 F. Supp. 940, 1972 U.S. Dist. LEXIS 14367, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-industrial-contractors-corp-v-william-clairmont-ned-1972.