United States ex rel. Goodman v. R. P. Farnsworth & Co.

218 F. Supp. 791, 1962 U.S. Dist. LEXIS 4533
CourtDistrict Court, W.D. Louisiana
DecidedAugust 17, 1962
DocketCiv. A. No. 7393
StatusPublished
Cited by2 cases

This text of 218 F. Supp. 791 (United States ex rel. Goodman v. R. P. Farnsworth & Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Goodman v. R. P. Farnsworth & Co., 218 F. Supp. 791, 1962 U.S. Dist. LEXIS 4533 (W.D. La. 1962).

Opinion

HUNTER, Judge.

This case involves:

(a) A conventional assignee’s claims against the prime contractor for a subcontractor’s retainage in a federal construction project, and

(b) The prime contractor’s opposition thereto pegged on the contention that the amount of the retainage was exceeded by the prime’s backcharges against the sub for defective work.

The suit is brought under the Miller Act (40 U.S.C.A. § 270a et sequa). Defendant, R. P. Farnsworth & Company, Inc. was the government’s prime contractor, and defendant Aetna Casualty and Surety Company was its surety.

James Thames, doing business as the Dixie Paving Company, was one of Farnsworth’s subcontractors. One contract was dated June 18, 1956 for excavation and pouring slabs and driveways for the housing and was in the final amount of $268,204 (Exh. D-2). Thames’ other subcontract was dated August 22, 1956, in the amount of $108,501 and was for certain street paving work (Exh. D-l).

[792]*792In October of 1956 by means of a takeover agreement, Farnsworth completely bought Thames out for the uncompleted portions of the subcontracts, even to the purchase of materials and equipment on the job site. The terms of the agreement which was entered into on October 31, 1956, are shown in Exhibit D-3. In pertinent part, this agreement provided that Farnsworth would hold $15,556.93 of the funds due Dixie for completed work as security against defects later found in Dixie’s work at the time of the government’s inspection, as follows:

“11 — FARNSWORTH shall retain the unpaid balance of $15,556.-93 which is 10% of the $155,-569.25 total value of the work done by THAMES under said subcontracts. Said retainage consists of $14,010.64 of the $140,126.35 value of work done under the June 18, 1956 subcontract, and $1,546.29 of the $15,462.90 value of the work done under the August 22,1956 subcontract.
“This retained $15,556.93 shall be paid by FARNSWORTH to THAMES and GREAT AMERICAN jointly within five days after receipt of the final payment due on the May 29, 1956 prime contract which shall become due after completion of all work and final written acceptance thereof by the CORPS OF ENGINEERS, UNITED STATES ARMY.
“12 — FARNSWORTH shall give written notice to THAMES and GREAT AMERICAN of any defects in the work done by THAMES within five days of the discovery thereof, and THAMES and GREAT AMERICAN shall have five days from receipt of such notice in which to inspect the work complained of. FARNSWORTH shall be entitled to correct the defective work at THAMES’ expense and may at its option deduct the cost thereof from the money retained.
“13 — FARNSWORTH shall be entitled also to deduct from the retained money an amount sufficient to pay any unpaid claims which may be presented for debts incurred by THAMES in connection with the work done by him before October 29, 1956.
“14 — Should the cost of correcting any such defective work covered by, and any such unpaid claims against, the June 18, 1956 subcontract exceed the $14,010.64, retained by FARNSWORTH thereunder, then THAMES and/or GREAT AMERICAN, as his surety, shall pay or cause to be paid the excess to FARNSWORTH.
“15 — Should the cost of correcting any such defective work covered by, and any such unpaid claims against, the August 22, 1956 subcontract exceed the $1,546.29 retained by FARNSWORTH thereunder, then THAMES shall pay the excess to FARNSWORTH.”

At the time Dixie terminated its work and Farnsworth took over, all of the street paving and sixty-seven separate duplex concrete slabs had already been poured. Farnsworth knew generally that some of this work might be found defective and it is for that reason that retainage was held under the October 31st agreement (Tr. pgs. 123-124).

In December, 1956 Dixie (Thames), conventionally assigned to plaintiff Goodman its interest in the $15,556.93 retainage. Goodman as well as Thames were both represented by Mr. Charles Peters, prominent attorney of Shreveport, Louisiana.

Later when Dixie’s work began to be inspected by the government’s engineers, defects were found. The concrete did not meet required specifications for levelness nor did it come within the owner’s tolerance of thereof (Tr. [793]*79311-12). The government engineers proceeded to notify Farnsworth by letter dated April 18, 1957 that defects existed and corrective work had to be done immediately (Exh. D-4).

Farnsworth, in turn, performed immediately remedial work on twelve slabs at a cost of $870.00. This was done without notification to Dixie. However, on April 22nd, Farnsworth notified Dixie of the government’s demand for sending via air mail and special delivery its April 22nd letter which read in pertinent part as follows:

«* * * y0U are hereby notified that we have, today, received a letter (copy enclosed) dated 18 April 1957 from the Resident Engineer, U. S. Corps of Engineers, advising us that some of the slabs do not meet the contract requirements and that corrective work is necessary prior to laying asphalt tile floors.
* * * in order not to delay progress of the job, it has been necessary for us to undertake corrective work on the first several slabs immediately and without notification to you * * *
“We have checked * * * slabs throughout the Airmen’s area and it appears that some corrective work work will have to be done on most of them to meet the Corps of Engineers requirements. Accordingly, it is requested that you and the Great American Surety Company representative make an inspection, if that is your desire, so that the progress of the job will not be delayed.”

Dixie received Farnsworth’s April 22nd notice letter on April 23rd. On April 26th Thames, Peters and the plaintiff all visited the job site where they inspected and discussed the work with Farnsworth’s superintendent Pope, and General Adjustment Bureau’s local manager, Durrett. Durrett was present as a representative of Great American Indemnity Company, the surety on Thames’ bond (Tr. 5, 18-19, 45-47; Cunningham deposition, pgs. 3-19). At this conference evidence of slab defects was observed by all parties and it was agreed that Farnsworth should perform the necessary corrective work.

After concluding the on-site inspection in Lake Charles on April 26, 1957 and returning to Shreveport, neither Thames, Goodman, nor the attorney Peters ever did anything further toward correction of the defective work themselves. They did not return to the site. They did not make any further inspections. They did not have anyone else other than Farnsworth perform for them any corrective work. They did not communicate with Durrett or anyone alse about remedial progress, but on April 29, 1957, Mr. Gallinghouse, attorney for Farnsworth, wrote the following letter to Mr. Peters, attorney for Goodman and Thames:

“Charles M. Peters, Esq.
“Sklar Building
“Shreveport, Louisiana
“Re: Farnsworth — Dixie
“Our file 11,760
“Dear Charlie:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Farnsworth & Company
319 F.2d 858 (Fifth Circuit, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
218 F. Supp. 791, 1962 U.S. Dist. LEXIS 4533, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-goodman-v-r-p-farnsworth-co-lawd-1962.