Mr. Justice Yan Orsdel
delivered the opinion of the Oourt:
Plaintiff in the declaration specifically bases its right of recovery upon what it calls in the first count the renewed contract. It is alleged that on “the thirtieth day of April, 1907, the Commissioners of the District of Columbia, exercised the privilege of renewing said contract and did renew the same for a period from August 1st, 1907, to June 30, 1910.” In the second count it is alleged that plaintiff, through its proper officers, on April 30, 1907, exercised the right of continuing said contract in force for the further period of two years and eleven months.
It will be observed that, whether the exercise of the option by plaintiff be regarded as a renewal or continuation of the original contract, the recovery sought is for damages alleged to have been sustained subsequent to the expiration of the original contract period of two years. The only question, therefore, presented by this appeal is, whether the exercise of the option by plaintiff, without concurrent action by the surety company, ex[111]*111tended tbe bond for tbe further period of two years and eleven months.
We are familiar with the old rule of strict construction in favor of the surety, based upon the underlying principle that formerly parties became sureties, not for hire, but as a matter of accommodation, usually lending their names through motives of friendship; and hence a surety obligation would be construed most strongly in their favor. But the rule of strictissimi juris has no application to surety companies organized for the purpose of conducting an indemnity business at established rates of compensation. United States Fidelity & G. Co. v. Golden Pressed & Fire Brick Co. (United States Fidelity & G. Co. v. United States) 191 U. S. 416, 48 L. ed. 242, 24 Sup. Ct. Rep. 142. But the question before us is neither one of liberal nor of strict construction. It can be answered from the express language of the bond and contract, without the aid of technical rules of construction. The original contract expressly provided that it should extend for a period of two years, at the expiration of which time plaintiff had the option of renewing it. A renewal is defined in Anderson’s Law Dictionary as “the substitution of a new right or obligation for another of the same nature.” Bouvier defines it as “a change of something old for something new.” Following this distinction it has been held that where there is a covenant to renew a lease the lessor is bound to make a new lease to either the lessee or his assignee. Rutgers v. Hunter, 6 Johns. Ch. 215; Furnival v. Crew, 3 Atk. 83; Worthington v. Lee, 61 Md. 530.
Closely analogous to the case at bar are numerous decisions -where sureties have obligated themselves for the faithful performance by the lessee of a lease containing a renewal option. So far as we are advised, it has been held that the surety was not bound for the faithful performance of the covenants during the renewed term, unless he had specifically obligated himself by the terms of the bond. In Fasnacht v. Winkelman, 21 La. Ann. 727, plaintiff leased defendant Winkelman certain property for the period of one year from August 1, 1865, with the [112]*112privilege of renewing the lease for four years more at the same rental and under the same conditions. One Heuer became surety. In the bond he declared himself bound “jointly and in solido3 with and as security for the said lessee, for the punctual payment of the rent herein stipulated, and of all costs and damages resulting from any violation of any of the conditions of the foregoing lease, hereby consenting to be bound as if he were the principal obligor herein, and renouncing the plea and benefit of discussion or division granted by law to sureties.” Notice of the renewal of the lease was givén, and upon nonpayment of the rent during the renewal period suit was brought against both principal and surety. The surety answered separately, alleging that his responsibility ceased on July 31j 1866, and was not renewed. The court, upholding this contention, said: “There is no proof that Heuer consented to the exteusion or renewal of the lease; but plaintiffs say that by his contract he was as much their tenant as Winkehnan, and that the acts of the latter were his acts, of which he is not permitted to plead ignorance. This position is untenable. The lease was made to Winkelman as the tenant, and Heuer became has surety, bound, it is true, as if he were the principal obligor in the lease, but only for the term of that lease, to wit, one year. The faculty of renewing was a privilege or right, to be exercised by the lessee upon a given condition, and not an obligation assumed by the surety. He was liable to the same obligations as the debtor himself * * * during the lease, but he did not agree to be bound in the renewed or extended lease by the giving of the required notice to the lessors by the lessee. The clause in relation to the renewal only bound the lessors and the lessee to the same price and conditions, if the lease were renewed, as contemplated. The consent of the surety was necessary to bind him on the extended lease.” It is immaterial whether the option be that of the lessor or the lessee. The non-liability of the surety, where he has in no way concurred in the renewal, is the same. Brewer v. Thorp, 35 Ala. 9; Knowles v. Cuddeback, 19 Hun, 590; Liverpool Waterworks Co. v. Atkinson, 6 East, 507, 2 Smith; 654. [113]*113The familiar rules that a bond should bo construed fairly as to its intent and meaning; that where a contract is referred to in the bond it becomes a part of the bond, and that the surety is liable to the same extent as his principal, are well understood. The difficulty here is that the liability of the surety company had ceased before the alleged default occurred. The original contract had expired. Plaintiff and Bayly were not even proceeding under a renewed contract, as in the cases of the leases cited. Bayly ceased to perform any services on the date of the expiration of the original contract, which specifically provided that it was given “for the period of two (2) years, beginning August 1, 1905.” It is not contended that any default occurred within that time. The limitation of time fixed in the contract and specifically mentioned in the recital of the bond is controlling. It measured the life of the bond. The obligation assumed was for the fulfillment of the conditions of the contract during that period, and did not include a renewal contract which, in contemplation of law, “constitutes a separate and distinct contract for the period of time covered by such renewal.” De Jernette v. Fidelity & C. Co. 98 Ky. 558, 33 S. W. 828; Hartford F. Ins. Co. v. Walsh, 54 Ill. 164, 5 Am. Rep. 115; Brady v. Northwestern Ins. Co. 11 Mich. 425.
We are cited to certain decisions of the Supreme Court in cases involving Government contract for public works, where the bonds were executed in compliance with the conditions of special statutes providing, in some instances, that the bond shall be given to secure the Government against liability for mechanic’s liens and, in other instances, against breach of conditions arising from changes agreed upon between the contractor and the Government subsequent to the execution of the original contract and the giving of the bond.
Free access — add to your briefcase to read the full text and ask questions with AI
Mr. Justice Yan Orsdel
delivered the opinion of the Oourt:
Plaintiff in the declaration specifically bases its right of recovery upon what it calls in the first count the renewed contract. It is alleged that on “the thirtieth day of April, 1907, the Commissioners of the District of Columbia, exercised the privilege of renewing said contract and did renew the same for a period from August 1st, 1907, to June 30, 1910.” In the second count it is alleged that plaintiff, through its proper officers, on April 30, 1907, exercised the right of continuing said contract in force for the further period of two years and eleven months.
It will be observed that, whether the exercise of the option by plaintiff be regarded as a renewal or continuation of the original contract, the recovery sought is for damages alleged to have been sustained subsequent to the expiration of the original contract period of two years. The only question, therefore, presented by this appeal is, whether the exercise of the option by plaintiff, without concurrent action by the surety company, ex[111]*111tended tbe bond for tbe further period of two years and eleven months.
We are familiar with the old rule of strict construction in favor of the surety, based upon the underlying principle that formerly parties became sureties, not for hire, but as a matter of accommodation, usually lending their names through motives of friendship; and hence a surety obligation would be construed most strongly in their favor. But the rule of strictissimi juris has no application to surety companies organized for the purpose of conducting an indemnity business at established rates of compensation. United States Fidelity & G. Co. v. Golden Pressed & Fire Brick Co. (United States Fidelity & G. Co. v. United States) 191 U. S. 416, 48 L. ed. 242, 24 Sup. Ct. Rep. 142. But the question before us is neither one of liberal nor of strict construction. It can be answered from the express language of the bond and contract, without the aid of technical rules of construction. The original contract expressly provided that it should extend for a period of two years, at the expiration of which time plaintiff had the option of renewing it. A renewal is defined in Anderson’s Law Dictionary as “the substitution of a new right or obligation for another of the same nature.” Bouvier defines it as “a change of something old for something new.” Following this distinction it has been held that where there is a covenant to renew a lease the lessor is bound to make a new lease to either the lessee or his assignee. Rutgers v. Hunter, 6 Johns. Ch. 215; Furnival v. Crew, 3 Atk. 83; Worthington v. Lee, 61 Md. 530.
Closely analogous to the case at bar are numerous decisions -where sureties have obligated themselves for the faithful performance by the lessee of a lease containing a renewal option. So far as we are advised, it has been held that the surety was not bound for the faithful performance of the covenants during the renewed term, unless he had specifically obligated himself by the terms of the bond. In Fasnacht v. Winkelman, 21 La. Ann. 727, plaintiff leased defendant Winkelman certain property for the period of one year from August 1, 1865, with the [112]*112privilege of renewing the lease for four years more at the same rental and under the same conditions. One Heuer became surety. In the bond he declared himself bound “jointly and in solido3 with and as security for the said lessee, for the punctual payment of the rent herein stipulated, and of all costs and damages resulting from any violation of any of the conditions of the foregoing lease, hereby consenting to be bound as if he were the principal obligor herein, and renouncing the plea and benefit of discussion or division granted by law to sureties.” Notice of the renewal of the lease was givén, and upon nonpayment of the rent during the renewal period suit was brought against both principal and surety. The surety answered separately, alleging that his responsibility ceased on July 31j 1866, and was not renewed. The court, upholding this contention, said: “There is no proof that Heuer consented to the exteusion or renewal of the lease; but plaintiffs say that by his contract he was as much their tenant as Winkehnan, and that the acts of the latter were his acts, of which he is not permitted to plead ignorance. This position is untenable. The lease was made to Winkelman as the tenant, and Heuer became has surety, bound, it is true, as if he were the principal obligor in the lease, but only for the term of that lease, to wit, one year. The faculty of renewing was a privilege or right, to be exercised by the lessee upon a given condition, and not an obligation assumed by the surety. He was liable to the same obligations as the debtor himself * * * during the lease, but he did not agree to be bound in the renewed or extended lease by the giving of the required notice to the lessors by the lessee. The clause in relation to the renewal only bound the lessors and the lessee to the same price and conditions, if the lease were renewed, as contemplated. The consent of the surety was necessary to bind him on the extended lease.” It is immaterial whether the option be that of the lessor or the lessee. The non-liability of the surety, where he has in no way concurred in the renewal, is the same. Brewer v. Thorp, 35 Ala. 9; Knowles v. Cuddeback, 19 Hun, 590; Liverpool Waterworks Co. v. Atkinson, 6 East, 507, 2 Smith; 654. [113]*113The familiar rules that a bond should bo construed fairly as to its intent and meaning; that where a contract is referred to in the bond it becomes a part of the bond, and that the surety is liable to the same extent as his principal, are well understood. The difficulty here is that the liability of the surety company had ceased before the alleged default occurred. The original contract had expired. Plaintiff and Bayly were not even proceeding under a renewed contract, as in the cases of the leases cited. Bayly ceased to perform any services on the date of the expiration of the original contract, which specifically provided that it was given “for the period of two (2) years, beginning August 1, 1905.” It is not contended that any default occurred within that time. The limitation of time fixed in the contract and specifically mentioned in the recital of the bond is controlling. It measured the life of the bond. The obligation assumed was for the fulfillment of the conditions of the contract during that period, and did not include a renewal contract which, in contemplation of law, “constitutes a separate and distinct contract for the period of time covered by such renewal.” De Jernette v. Fidelity & C. Co. 98 Ky. 558, 33 S. W. 828; Hartford F. Ins. Co. v. Walsh, 54 Ill. 164, 5 Am. Rep. 115; Brady v. Northwestern Ins. Co. 11 Mich. 425.
We are cited to certain decisions of the Supreme Court in cases involving Government contract for public works, where the bonds were executed in compliance with the conditions of special statutes providing, in some instances, that the bond shall be given to secure the Government against liability for mechanic’s liens and, in other instances, against breach of conditions arising from changes agreed upon between the contractor and the Government subsequent to the execution of the original contract and the giving of the bond. In these cases the bondsmen obligated themselves, both by reference to the statute and by express covenant in the bond, that the contractor “should fulfill all the conditions and covenants of his contract, whatever changes in or additions to such contracts might thereafter be made; and second promptly make payment to all persons sup-, plying him labor and materials in the prosecution of the work.” [114]*114United States Fidelity & G. Co. v. Golden Pressed & Fire Brick Co. (United States Fidelity & G. Co. v. United States) 191 U. S. 416, 48 L. ed. 242, 24 Sup. Ct. Rep. 142; United States use of Hill v. American Surety Co. 200 U. S. 197, 50 L. ed. 437, 26 Sup. Ct. Rep. 168.
A distinction having an important bearing upon the question before us is presented in the Pauly Case, 170 U. S. 133, 144, 42 L. ed. 977, 981, 18 Sup. Ct. Rep. 552, where the court, through Mr. Justice Harlan, said: '“If, looking at all its provisions, the bond is fairly and reasonably susceptible of two constructions, one favorable to the bank and the other favorable to the surety company, the former, if consistent with the objects for which the bond was given, must be adopted, and this for the reason that the instrument which the court is invited to interpret was drawn by the attorneys, officers or agents of the surety company.” ■ The converse of this rule of construction, if such it may be called, would seem to be applicable to the present case, inasmuch as both the contract and bond were prepared “by the attorneys, officers or agents” of the District of Columbia.
■ The judgment is affirmed with costs, and it is so ordered.
Affirmed.