United States ex rel. Crane Service & Equipment Corp. v. Boston Steel Erection, Inc.

367 F. Supp. 699, 1973 U.S. Dist. LEXIS 10763
CourtDistrict Court, D. Massachusetts
DecidedDecember 6, 1973
DocketCiv. A. Nos. 68-752-C, 68-754-C to 68-756-C
StatusPublished
Cited by2 cases

This text of 367 F. Supp. 699 (United States ex rel. Crane Service & Equipment Corp. v. Boston Steel Erection, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Massachusetts primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Crane Service & Equipment Corp. v. Boston Steel Erection, Inc., 367 F. Supp. 699, 1973 U.S. Dist. LEXIS 10763 (D. Mass. 1973).

Opinion

OPINION

CAFFREY, Chief Judge.

The above-captioned cases, all arising out of the same fact situation, were consolidated for non-jury trial. All four eases were brought in this court on the basis of the so-called Miller Act, 40 U.S. C.A. §§ 270a-270d. Jurisdiction is premised on 40 U.S.C.A. § 270b. The parties plaintiff in the various cases are Crane Service & Equipment Corp., a Massachusetts corporation (hereinafter Crane); Boston Steel Erection, Inc., a Massachusetts corporation (hereinafter Boston Erection); Southern Mass. Construction, Inc., a Massachusetts corporation (hereinafter Southern); and James M.' Salah and Samuel Pecci, d/b,/a Salah & Pecci Contracting Co. (hereinafter Salah-Pecci).

In Civil Act 68-752, in which the plaintiff is Crane, the parties defendant are Boston Erection, Southern, Edward R. Marden Corp. (hereinafter Marden), Planet Insurance Company (hereinafter Planet), and American Reinsurance Company (hereinafter American).

In Civil Action 68-752, Crane’s Miller Act case against Boston Erection, Marden, Planet and American, a stipulation signed by counsel for Crane, Boston Erection, Southern, Marden, Planet and American has been filed. In pertinent part the stipulation recites:

“The use plaintiff Crane . . . did furnish labor and materials to . . Marden ... in the form of labor and (3) Manitowoc Truck Cranes. . These truck cranes and their operators . . . were used in the prosecution of the work . . . for the construction of a . . . aircraft maintenance hangar at the Naval Air Station in South Weymouth, Massachusetts. . . . There remain unpaid and owing to Crane Service & Equipment the sum of $8,392.61 for labor and material furnished by agreement with Boston Steel Erection, Inc. as aforesaid and the sum of $1,614.48 for labor and materials furnished by agreement with Southern Mass. . . .”

At the opening of the trial of these consolidated cases, the following colloquy appears on page 5 of the transcript:

“The Court: For the case we are not trying, the Crane Service.
Mr. Keating: That one we are not— The Court: Let us clarify it for the record, between you and Mr. Ganz, what the status of the Crane Service is. You made a stipulation, but no judgment has been entered in that case.
Mr. Ganz: No, your Honor, it would seem to me, to be helpful if we could regard ourselves as trying the Boston Steel Erection case. Crane Service had been disposed of by stipulation.
Even though no judgment as yet has been entered, I don’t see any problem so far as Crane Service is concerned.”

[701]*701Accordingly, on the basis of both the stipulation on file and the quoted representation of counsel, I find and rule that Marden and its sureties are liable to Crane in the amount of $8,392.61 on account of labor and materials furnished by Crane pursuant to its agreement with Boston Erection and that Marden and its sureties are also liable to Crane in the amount of $1,614.48 for labor and materials furnished by Crane by reason of its agreement with Southern Mass.

Judgment in favor of Crane will enter for the total of these two sums, namely, $10,007.09, which is the amount this Court finds is due and owing to Crane, plus interest and costs, as against Mar-den and its sureties. Civil Action 68-752 will not be discussed further in this opinion.

In Civil Action 68-754, in which the plaintiff is Boston Erection, the defendants are Marden, Planet and American. In Civil Action 68-755, in which the plaintiff is Southern, the defendants are Marden, Planet and American. In Civil Action 68-756, in which the plaintiffs are Salah-Pecci, the defendants are Mar-den, Planet and American. In the various eases the plaintiffs allege that they are subcontractors who have brought suit •against Marden, the general contractor, for breach of contract, and against the insurance companies as sureties of Mar-den pursuant to the provisions of the Miller Act.

On the basis of pendent jurisdiction a claim in tort for negligence has been brought only as against Marden in Civil Actions 68-754, 68-755 and 68-756, by way of an amendment to the complaints in those three cases.

After trial I find and rule as follows: On June 14, 1965 the United States entered into a written contract with the engineering firm of Desmond & Lord, Inc. for studies, preliminary sketches, estimates, drawings and specifications for the removal of a lighter-than-air hangar and the construction of a new aircraft maintenance hangar and certain other structures at the Naval Air Station, South Weymouth, Massachusetts. The contract also provided for Desmond & Lord to furnish engineering consultation during the course of the construction. Desmond & Lord entered into a subcontract with Albert Goldberg & Associates, Inc. to perform the structural engineering services for the hangar installation.

On June 15, 1966 the United States, acting through duly authorized representatives of the Department of the Navy, entered into a written contract with Marden under the terms of which Marden was to serve as general contractor for the erection of the new hangar. The plans and specifications which were incorporated by reference into the general contract between the United States and Marden contemplated that the construction of the new hangar would include the erection of precast concrete arches which were to be formed by uniting two half arches. Each completed arch would weigh approximately 110 tons and would consist of two half arches each of which would weigh approximately 55 tons.

On December 29, 1966 Marden submitted a written proposal regarding the method of arch erection to Desmond & Lord, Inc., which in pertinent part provided as follows:

“Re: Aircraft Maintenance Hangar, South Weymouth, Mass. — NBy 66498 Proposed Method of Arch Erection
We submit herewith our proposed method for the Arch erection at subject project. We have elected to construct the arches on the site and lift them into place as per the second option given in Paragraph 3B.3.B of the specifications.
1. Inserts will be cast into the arch to receive the lifting fittings all as detailed on the enclosed drawings by Simpson, Gumpertz & Heger, Inc.
2. The arches will be raised from the flat by use of the lifting fittings “A” and rotated to the vertical po[702]*702sition by use of the lifting fittings “B”.
3. Each half arch will be placed over the anchor bolts cast into the top of the buttress (Albert Goldberg & Associates, Inc. drawing Sk-1 and the top hinge connection will be made in accordance with Albert Goldberg & Associates, Inc. dwg. dated 12/3/66).
4. Rigid Steel bracing w/cables will be attached to one side (the west side) of the arch.
5. As each full arch is erected, it will be secured to the previously erected arch by three precast concrete roof planks, at six (6) locations, welded in place, all as shown on Durastone-Flexicore Approved dwg. No. 1 dated 12/29/66).” (Plaintiffs’ Ex. 26)

After correspondence between Desmond & Lord, Albert Goldberg & Associates, Lt.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
367 F. Supp. 699, 1973 U.S. Dist. LEXIS 10763, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-crane-service-equipment-corp-v-boston-steel-mad-1973.