United States Ex Rel. Belt Con Construction, Inc. v. Metric Construction, Inc.

376 F. Supp. 2d 1073, 2004 U.S. Dist. LEXIS 28188, 2004 WL 3413271
CourtDistrict Court, D. New Mexico
DecidedOctober 11, 2004
DocketCOV 02-1398 JB/LAM
StatusPublished

This text of 376 F. Supp. 2d 1073 (United States Ex Rel. Belt Con Construction, Inc. v. Metric Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. Belt Con Construction, Inc. v. Metric Construction, Inc., 376 F. Supp. 2d 1073, 2004 U.S. Dist. LEXIS 28188, 2004 WL 3413271 (D.N.M. 2004).

Opinion

MEMORANDUM OPINION AND ORDER

BROWNING, District Judge.

THIS MATTER comes before the Court on the Plaintiffs Motion for Partial Summary Judgment, filed July 19, 2004 (Doc. 60). The Court held a hearing on this motion on September 2, 2004. The primary issue is whether Defendant Metric Construction Co., Inc. (“Metric”) can maintain a counterclaim for actual damages, which may include liquidated damages it paid the United States of America. Because the Court finds that Metric did not waive or release its claim against Use Plaintiff Belt Con Construction Inc. (“Belt Con”) for delaying the project when it entered into a compromise settlement with the General Services Administration, and because there is a genuine issue of material fact whether Belt Con caused Metric to pay liquidated damages, the Court will deny the Plaintiffs Motion for Partial Summary Judgment.

FACTUAL AND PROCEDURAL BACKGROUND

On or about October 1, 1999, Metric entered into a contract with the United States to perform the labor and to furnish the materials for the construction of dormitories and physical training and security buildings at the FLETC Campus in Arte-sia, New Mexico. See Plaintiffs Complaint ¶ 5, at 2 (filed November 5, 2002)(Doc. 1); Defendants’ Answer and Counterclaim ¶ 1, at 6 (filed April 29, 2004)(Doc. 57). On or about October 1, 1999, pursuant to the terms of the contract, Metric, as principal, and Defendant Safeco Insurance Company of America (“Safeco”), as surety, executed and delivered to the United States them bond, conditioned, as required by the Miller Act, for the protection of all persons supplying labor and materials in the prosecution of the *1075 work provided in the contract. See Plaintiffs Complaint ¶ 6, at 2; Defendants’ Answer and Counterclaim ¶ 6, at 2, On or about January 28, 2000, Belt Con entered into a subcontract with Metric, whereby Belt Con agreed to furnish certain labor and materials required for the construction project. See Plaintiffs Complaint ¶ 7, at 2-3. Defendants’ Answer and Counterclaim ¶ 2, at 6. Belt Con thereafter entered into performance of its subcontract, furnishing labor and materials as prescribed therein. See Plaintiffs Complaint If 8, at 3.

The original subcontract price in the subcontract between Belt Con and Metric was $3,094,000.00. See Plaintiffs Complaint ¶8, at 3; Defendants’ Answer and Counterclaim ¶ 8, at 2. That price was adjusted to $3,143,000.00 by additions and deductions for changes in the work. See Plaintiffs Complaint 1Í 8, at 3; Defendants’ Answer and Counterclaim ¶ 8, at 2. Metric has paid Belt Con $2,999,748.30 of the subcontract price. See Plaintiffs Complaint ¶8, at 3; Defendants’ Answer and Counterclaim ¶ 8, at 2.

Belt Con asserts that there is a balance due on the subcontract of $143,251.70. See Plaintiffs Complaint ¶ 8, at 3. Belt Con also asserts Metric disrupted its work, causing Belt Con to incur additional costs: (i) for inefficiencies associated with work performed out of sequence; (ii) for not having access to work areas; (iii) because of interference from other contractors; (iv) for repair costs for damages by others; and (v) for additional overhead costs totaling $241,334.97. See Plaintiffs Complaint ¶ 8, at 3. Belt Con further maintains it is entitled to $46,429.28 in penalty interest because Metric did not make payments to Belt Con as Metric was paid by the United States for work performed by Belt Con, made late payments, and underbilled the United States for work performed by Belt Con in violation of the Prompt Payment Act, 31 U.S.C. § 3905. See Plaintiffs Complaint ¶ 8, at 3. Belt Con also maintains Metric has been paid the full contract balance on its contract with the United States, but has not paid Belt Con the balance owing on its subcontract and thus Belt Con is entitled to penalty interest on $143,251.70 as provided in the Prompt Payment Act from the date such payment was due until paid.- See Plaintiffs Complaint ¶ 8, at 3-4. In total, Belt Con claims Metric owes Belt Con $431,015.95, interest payments as provided in the Prompt Payment Act on $143,251.70, and attorneys fees. See Plaintiffs Complaint ¶ 8, at 3.

The Defendants deny owing any money to'Belt Con. See Defendants’ Answer and Counterclaim ¶¶ 8, 9, at 2. The Defendants allege that Belt Con failed to comply with the reasonable directives of Metric, failed to perform its work in a timely and reasonable manner, and otherwise acted negligently and/or intentionally in a such a manner as to delay the project. See id. ¶ 3, at 6. The defendants assert that there is no balance of $143,251.70 due to Belt Con because the United States assessed liquidated damages against Metric as a result of delay and other breaches of contract on the part of Belt Con. See id. ¶ 8, at 2. The Defendants contend Belt Con’s conduct caused Metric damages in an amount of $229,924.80. See id. ¶ 5, at 7.

PROCEDURAL BACKGROUND

Belt Con brought this action under the Miller Act, 40 U.S.A. §§ 270a-270d, for $431,015.95, interest, attorneys fees, and costs. The Defendants brought a counterclaim against Belt Con for $299,294.80. This amount includes $171,600.00 for liquidated damages. Belt Con moves for an Order granting it partial summary judgment against the Defendants on their counterclaim for liquidated damages.

*1076 STANDARDS FOR SUMMARY JUDGMENT

Summary judgment is proper when there is no genuine issue of material fact in a particular case. See Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Fed.R.Civ.P. 56(c). “Summary judgment is proper only if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Quaker State Minit-Lube, Inc. v. Fireman’s Fund Ins. Co., 52 F.3d 1522, 1527 (10th Cir.1995). “All facts and reasonable inferences must be construed in the light most favorable to the nonmoving party.” Id. For a nonmoving party to overcome a motion for summary judgment, the non-moving party must base its affidavits upon personal knowledge and set forth facts that would be admissible in evidence. Affidavits with conclusions and self-serving statements are not sufficient. See Hall v. Bellmon, 935 F.2d 1106, 1111 (10th Cir.1991).

ANALYSIS

There is a genuine issue of material fact concerning the Defendants’ counterclaim against Belt Con. Accordingly, summary judgment for Belt Con is not appropriate.

I.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hall v. Bellmon
935 F.2d 1106 (Tenth Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
376 F. Supp. 2d 1073, 2004 U.S. Dist. LEXIS 28188, 2004 WL 3413271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-belt-con-construction-inc-v-metric-construction-nmd-2004.