United States Ex Rel. B & B Welding, Inc. v. Reliance Insurance of New York

743 F. Supp. 129, 1990 U.S. Dist. LEXIS 10553, 1990 WL 115947
CourtDistrict Court, E.D. New York
DecidedAugust 3, 1990
DocketCV 90-0232
StatusPublished
Cited by1 cases

This text of 743 F. Supp. 129 (United States Ex Rel. B & B Welding, Inc. v. Reliance Insurance of New York) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Ex Rel. B & B Welding, Inc. v. Reliance Insurance of New York, 743 F. Supp. 129, 1990 U.S. Dist. LEXIS 10553, 1990 WL 115947 (E.D.N.Y. 1990).

Opinion

MEMORANDUM AND ORDER

WEXLER, District Judge.

Use-plaintiff B & B Welding, Inc. (“B & B”) brings this action under the Miller Act, 40 U.S.C. § 270b, against defendant Reliance Insurance Company of New York (“Reliance”), the surety on a payment bond on a contract entered into between the United States and Danaco Contractors, Inc. (“DCI”), as general contractor, for the construction of a chilled water facility at Brookhaven National Laboratory (“BNL”) in Brookhaven, New York (“the BNL Project”). B & B seeks to recover amounts owed it by DCI for materials and labor furnished on the BNL Project as a subcontractor for DCI. Presently before the Court is Reliance’s motion for summary judgment 1 on the ground that the action is barred by the Miller Act’s one-year statute of limitations. See 40 U.S.C. § 270b(b). For the reasons below, the motion is granted.

I. Background

The complaint alleges that DCI and the United States entered into'their contract sometime prior to June 28, 1987. In addition, upon entering the contract with the United States, DCI, as principal, and Reliance, as surety, delivered to the United States a payment bond guaranteeing payment to suppliers of material and labor in the prosecution of the BNL Project. Thereafter, on or about June 28, 1987, B & B entered into a contract with DCI to provide labor and materials for the project. The work B & B agreed to complete included, inter alia, the structural steel and metal roof and door decks. B & B alleges that it completed performance under the contract but that DCI still owes it $97,441.83. 2 Because DCI has failed to pay the amount allegedly due under the contract, B & B seeks to recover from Reliance as surety on the payment bond. B & B also states that it has satisfied all conditions precedent to bringing this action.

The complaint alleges that the date on which B & B last supplied labor or material was June 30, 1988. This action was commenced on January 23, 1990, nearly nineteen months later. Section 270b(b) of the Miller Act, however, provides:

Every suit instituted under this section shall be brought in the name of the United States for the use of the person suing, in the United States District Court for any district in which the contract was to be performed and executed ..., but no such suit shall be commenced after the expiration of one year after the day on which the last of the labor was performed or material was supplied by [such person]....

40 U.S.C. § 270b(b). It is apparent that based on the allegations in the complaint, this action is not timely. Faced with a statute of limitations defense, B & B argues that statements and representations made by representatives of Reliance to B & B’s attorney, Lawrence Fechner (“Fech-ner”), on June 23 and 30, 1989, and thereafter, caused B & B to delay commencing this action. Hence, B & B argues that Reliance should be estopped from asserting *131 the Miller Act’s statute of limitations as a defense.

In support of its estoppel argument, B & B contends that on June 23, 1989, Fechner spoke to George Brotherston (“Brother-ston”), who was hired as a consultant by Reliance, in an attempt to resolve B & B’s claim against DCI. By affidavit, Fechner states that Brotherston had set up a meeting at the BNL job site for June 28, 1989 between Reliance and representatives of B & B, and had requested that someone from B & B with signatory authority be present at the meeting “since checks would be issued at that time in settlement of existing claims.” Affidavit of Lawrence Fechner dated March 28, 1990, para. 12. However, at the June 28 meeting no checks were issued in settlement of the claim. Fechner was told the next day, June 29,1989, that B & B had not been paid at the June 28 meeting. Id. para. 14.

On June 30, 1989, Fechner spoke to Rick Levesque (“Levesque”), an attorney in Reliance’s bond claim department, who suggested to Fechner that he file a formal claim against the bond on behalf of B & B. Id. para. 16. Consequently, by letter dated July 18, 1989, Fechner submitted B & B’s formal claim to Levesque. Id. ex. D. In response, by letter to Fechner dated August 14, 1989, Levesque stated:

This will confirm receipt of your July 18, 1989 correspondence wherein you presented a claim in the amount of $113,-655.83 against the ... [payment] bond. To facilitate our investigation of your claim we request that you supply the following:
1. Copy of the subcontract and/or purchase order.
2. Invoices and delivery receipts.
3. A statement of account.
4. Copies of all correspondence_
While awaiting these documents we shall initiate our investigation by contacting DCI ... to determine its position.
If this matter has been or is in the process of being resolved, we would appreciate your notifying us.
... We specifically reserve any and all rights available under the provisions of the Miller Act relating to suit limitations.

Moreover, by letter dated September 27, 1989, Levesque advised Fechner that he had not yet received word on DCI’s position as to B & B’s claim, and reminded Fechner that Reliance’s position was that any claim by B & B against Reliance was barred by the Miller Act’s statute of limitations. Levesque again reiterated this in a letter to Fechner dated November 6, 1989. In the November 6 letter, Levesque also indicated that the June 28, 1989 meeting between Reliance and B & B was not scheduled for the purpose of resolving the claim, but was part of Reliance’s investigation into DCI’s obligations following termination of DCI by BNL. Nevertheless, as noted above, this action was not commenced until January 23, 1990.

Reliance maintains that the last day on which B & B performed labor or supplied material on the BNL Project was actually March 1, 1988, but in no event was it later than June 2, 1988, the date that B & B completed punch list work, i.e., work to repair or correct defects in original work. Reliance refers the Court to a letter dated August 5, 1989 from B & B’s president, Robert Benza (“Benza”), to DCFs vice-president, Dennis Nemick (“Nemick”), which reads in part:

Both of the punch lists referred by you were acknowledged by B & B, and work was completed and accepted by Mr. Bill Britz of BNL, as the work was performed in his presence. Please reference our Daily Job Report, dated June 2, 1988....
We have enclosed a copy of BNL’s punch list, dated May 20,1988, with an explanation next to each item.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Millgard Corp. v. White Oak Corp.
224 F. Supp. 2d 425 (D. Connecticut, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
743 F. Supp. 129, 1990 U.S. Dist. LEXIS 10553, 1990 WL 115947, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-b-b-welding-inc-v-reliance-insurance-of-new-york-nyed-1990.