United States ex rel. Attorney General v. Pittsburgh & L. E. R.

26 F. 113, 1886 U.S. Dist. LEXIS 4
CourtDistrict Court, W.D. Pennsylvania
DecidedJanuary 18, 1886
StatusPublished

This text of 26 F. 113 (United States ex rel. Attorney General v. Pittsburgh & L. E. R.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Attorney General v. Pittsburgh & L. E. R., 26 F. 113, 1886 U.S. Dist. LEXIS 4 (W.D. Pa. 1886).

Opinion

Aoheson, J.

While the jurisdiction of this court in this cause has not been called in question, but has been tacitly conceded by the defendant’s learned-counsel, it nevertheless is proper to examine the grounds upon which our authority rests. The subject-matter of the suit is a bridge constructed by the defendant over the Ohio river, near the town of Beaver, in the Western district of Pennsylvania, under the act of congress of December 17, 1872, (17 St. at Large, 398,) entitled “An act .authorizing the construction of bridges across the Ohio river, and to prescribe the dimensions of the same;” the complaint, in substance, being that the defendant’s said bridge has not been constructed in accordance with the limitations and provisions of said act, but in violation thereof; and that, as built and maintained, it is an unlawful obstruction to the navigation of said river, and a public nuisance. The sixth section of the act contains the provision following:

“And in case of any litigation arising from any obstruction, or alleged obstruction, to the navigation of said river, created by the construction of any [114]*114bridge under this act, the cause or question arising may be tried before the district court of the United States of any state in which any portion of said obstruction or bridge touches. ”

Nowj congress having legislated on the subject of the erection and maintenance of bridges over the Ohio river, and defined what shall be a lawful structure, I cannot doubt that the United States may maintain a suit to compel a company, assuming to exercise the authority conferred by the said act, to comply with the terms thereof, or to abate as a public nuisance an unlawful structure so erected, when an obstruction to the free navigation of the stream. Dugan v. U. S., 3 Wheat. 173; U. S. v. Tingey, 5 Pet. 115. And litigation between the government and such company, touching an obstruction to the navigation of the river created by the construction of a bridge under the said act, would seem clearly to present a cause within the terms of the above-quoted clause of the sixth section, and hence cognizable by the proper district court. But as an indictment against the bridge as a nuisance is not maintainable,. — no such proceeding having been authorized by congress, — the appropriate remedy is by an information at the suit of the attorney general in equity, as here adopted. State v. Wheeling Bridge Co., 13 How. 518; Story, Eq. Jur. § 921 et seq.; Wood, Nuis. 813.

Being thus assured of the jurisdiction of the court, I pass to a consideration of the merits of the case. As already stated, the bridge in question was erected under the above-recited act of congress, which prescribes the minimum height and width of the channel spans, and other requirements. The fourth section of the act provides that the person or company proposing to erect a bridge across the Ohio river shall submit to the secretary of war, for his examination, a design and drawings of the bridge and piers, and a map of the location, giving, for the space of at least one mile above and one mile below the proposed location, the topography of the banks of the river, the shorelines, at high and low water, the direction of the current at all stages, and other specified particulars, and shall furnish such other information as may be required for a full and satisfactory understanding of the subject; “and, if the secretary of war is satisfied that the provisions of the law have been complied with in regard to location, the building of the piers may be at once commenced; but, if it shall appear that the conditions prescribed by this act cannot be complied with at the location where it is desired'to'construct the bridge, the secretary of war shall, after considering any remonstrances filed against the building of said bridge, and furnishing copies of such remonstrances to the board of engineers provided for in this act, detail a board, composed of three experienced officers of the corps of engineers, to examine the case; and may, on their recommendation, authorize such modifications in the requirements of this act aS to location and piers as will permit the construction of the bridge, not, however, diminishing the width of the spans contemplated by this act: provided,[115]*115that the free navigation of the river be not materially injured thereby.” The defendant company having submitted to the secretary of war the design and drawings for its proposed bridge and piers, and a map of the location, and remonstrances having been filed by those interested in the navigation of the river against the building of the bridge, the secretary, not being satisfied with the proposed plan, etc., detailed a board of engineers, conformably to the provisions of the act, to examine the case. That board, after visiting the ground and hearing the parties interested, made report to the chief of engineers, on August 15, 1S77, which report was approved by the secretary of war on August 30, 1877. This report contains the following recommendations, viz.:

“And inasmuch as the river men whom they [the board] have consulted are almost unanimous in desiring that tlie bridge should be built further up stream, they would recommend that this be done, and that a site between 300 and 400 feet higher up be chosen, giving the company a margin of 100 feet in order to adapt their line to the ground in a manner as advantageous as possible. But, even with this change, the channel space will often be difficult to run, as tows, after Hanking around the Phillipsburg point, cannot always straighten up in time to run straight through tlie channel space. For these reasons, the board would recommend that the channel space be increased to 425 feet in the clear, and that a smooth guiding dike, 300 feet long, be built up stream from the left channel pier. This dike should be as high as the 15-foot stage in the river, and should bend gently towards the bank, so as to reduce the space for water behind it, and to deflect the current info the channel space. The left channel pier should be placed .150 feet from the bluff bank. The span next north of the channel space should be also made a through bridge.”

At a meeting of the board of directors of tlie defendant company, held September 5,1877, the foregoing recommendations of the board of engineers were acceded to by the company; and a written acceptance thereof, signed by tlie president of the company, and under its corporate seal, was immediately transmitted to the secretary of war, by whom it was received and filed. On September 12, 1877, the defendant’s engineer submitted a map exhibiting the plan and location of the proposed bridge, modified so as to conform to the above recommendations, to Maj. William E. Merrill, of the corps of engineers, and the officer in charge of the improvement of the Ohio river; who, finding it to conform to tlie above expressed views of the board of engineers, forwarded it to the chief of engineers, upon whose recommendation the secretary of war, on September 21,1877, approved the modified plan and location as shown on said map; and official notice of such approval was communicated to the president of the defendant company on September 24, 1877. Shortly thereafter the company began the erection of the piers of the bridge at the changed location, in conformity with the modified plan. The piers were ready for the superstructure early in July, 1878, and the bridge (save the dike) was completed by September 21, 1878, on which day the first train ran over it. In the mean time, about June 12,1878, after the piers [116]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Tingey
30 U.S. 115 (Supreme Court, 1831)
State of Penn. v. THE WHEELING &C. BRIDGE CO.
54 U.S. 518 (Supreme Court, 1852)

Cite This Page — Counsel Stack

Bluebook (online)
26 F. 113, 1886 U.S. Dist. LEXIS 4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-attorney-general-v-pittsburgh-l-e-r-pawd-1886.