United States Ex Rel. Administrator of Environmental Protection Agency v. CITGO Petroleum Corp.

711 F. App'x 237
Court of Appeals for the Fifth Circuit·Decided February 14, 2018·No. 16-30515·Unpublished

Opinions

PER CURIAM:*

This case stems from the spillage of wastewater into navigable waters at a CITGO plant in Lake Charles, Louisiana. CITGO has conceded liability and the only issue in this protracted litigation is the amount of the resulting civil penalty, which the district court has determined on two separate occasions. The parties appealed both. On first appeal, we vacated and remanded for further proceedings. Now, we AFFIRM. '

BACKGROUND

The underlying facts of this case are set out in our initial decision. See United States ex rel. v. CITGO Petro. Corp. (“CIT-GO I”), 723 F.3d 547, 549-50 (5th Cir. 2013), Pertinent to this appeal, CITGO conceded liability for the spillage of waste-water into navigable waters at a Louisiana plant. Id. After a two-week bench trial, the district court fined CITGO $6 million. Id. at 550. The United States appealed that penalty, arguipg that the district court failed to make the necessary fact-finding on the economic benefit to CITGO of delaying necessary prevention measures. Id. at 551. We agreed, and remanded in order to make “a reasonable approximation” of the economic benefit to CITGO. Id.

On remand, the district court conducted a thorough analysis and concluded that CITGO realized an economic benefit of $91.7 million. See United States v. Citgo Petro. Corp., Civ. Action No. 08-893, 2015 WL 9692957, at *6 (W.D. La. Dec. 23, 2015). In reaching that number, the district court considered the costs of CITGO providing a third and fourth waste water tank, an aeration filter, and an API separator. Id. at *5. The court then applied a rate of 10.04% weighted average cost of capital (“WACC”).to those funds over a number of years. Id. at *6. Finally, after finding CITGO acted with gross negligence, the court considered all the remaining Clean Water Act (“CWA”) penalty factors, ultimately deciding to depart downward from the economic benefit determination to impose a fine of $81 million. Id. at *7-8. Both parties timely appealed.

STANDARD OF REVIEW

“The assessment of civil penalties under the CWA is left to the district court’s discretion.” CITGO I, 728 F.3d at 551. The exercise of that discretion is guided by the factors articulated in the CWA. See id. (citing 33 U.S.C. § 1321(b)(8)). The Supreme Court has described the process of weighing the penalty factors as “highly discretionary.” Tull v. United States, 481 U.S. 412, 425, 107 S.Ct. 1831, 95 L.Ed.2d 365 (1987). Accordingly, this court reviews the district court’s WACC determination for abuse of discretion, United States v. Allegheny Ludlum Corp., 366 F.3d 164, 184 (3d Cir. 2004), and factual findings in support of the penalty calculation for clear error, Sierra Club, Lone Star Chapter v. Cedar Point Oil Co., 73 F.3d 546, 573 (5th Cir. 1996).

DISCUSSION

Both parties have appealed the district court’s civil penalty. We address CITGO’s arguments first before turning to the government’s. None of the parties’ arguments have merit and we affirm in full.

I. CITGO’s Assertions

CITGO presents two arguments on appeal. First, CITGO claims that the district court failed to properly consider the least costly alternative to prevent the spillage. Second, CITGO claims the district court erred in applying a 10.04% WACC rate. Neither argument has merit. .

a. Least Costly Alternative

The district court determined that the “least costly alternative would have been to provide adequate [storage] capacity.” Citgo Petro., 2015 WL 9692957, at *5. This determination is supported by the government expert’s testimony that CITGO needed “more than 20 million gallons of additional water capacity.” To meet that need, the court found that CITGO should have installed a third and fourth water tank, as well as an aeration tank and API separator. Id. CITGO contends this analysis was error because only a third storage tank was needed to prevent overflow.

According to CITGO, a third tank would have provided 10.7 million gallons of capacity, which, combined with the storage dike’s 11.8 million gallons of capacity, would have provided sufficient storage to prevent overflow. This calculation, however, is based on a scenario where- “all tanks were operated at the minimum level and all conditions were perfect.” There is ample record evidence that this best-case-scenario does not conform to the realities of running the plant.

The government’s expert testified that a fourth tank was necessary “no matter what” because tanks must be taken out of service periodically for maintenance. Therefore,'a fourth tank was mandatory in order to ensure that a third tank was always operational. Further, CITGO planned to use the dike’s capacity to compensate for lost storage when a tank was taken out for maintenance. Because of these issues, even assuming that a third tank and the dike would mathematically provide sufficient storage, in reality, CIT-GO was not always “maintaining that reserve capacity.”

Compounding these issues, CITGO “failed to maintain the limited capacity it had, allowing the tanks to fill with sludge and waste.” See Citgo Petro., 2015 WL 9692957, at *7. Accumulation of this debris was the result of inadequate filtration systems and led to the storage tanks having a functional storage capacity below the best-case-scenario capacity asserted on appeal by CITGO. To remedy this issue, the government’s expert testified that CITGO needed a fifth API separator and another aeration tank.

In short, CITGO’s argument is based on mathematical calculations of storage capacities at “optimum conditions.” The district court credited the government’s expert that such calculations are “disconnect[ed]” from the “real world” operation of the plant. There is no clear error in that determination.

b. The WACC Determination

CITGO next contends that the district court abused its discretion when it applied a 10.04% WACC to determine the present value of the economic benefit calculation. In CITGO’s view, the 10.04% rate was not based on sound methodology and was unreasonable because CITGO could have obtained the same funding at a much lower cost.

Free access — add to your briefcase to read the full text and ask questions with AI

United States Ex Rel. Administrator of Environmental Protection Agency v. CITGO Petroleum Corp., 711 F. App'x 237 (5th Cir. 2018).

711 F. App'x 237 (United States Ex Rel. Administrator of Environmental Protection Agency v. CITGO Petroleum Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related