United States Coal Co. v. Osborne

32 Ohio C.C. Dec. 314, 17 Ohio C.C. (n.s.) 599, 1910 Ohio Misc. LEXIS 445
CourtCuyahoga Circuit Court
DecidedMay 31, 1910
StatusPublished

This text of 32 Ohio C.C. Dec. 314 (United States Coal Co. v. Osborne) is published on Counsel Stack Legal Research, covering Cuyahoga Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Coal Co. v. Osborne, 32 Ohio C.C. Dec. 314, 17 Ohio C.C. (n.s.) 599, 1910 Ohio Misc. LEXIS 445 (Ohio Super. Ct. 1910).

Opinion

MARVIN, J.

Each of these three cases is an appeal from the judgment of the court of common pleas made in a single case, the appeals being taken by separate defendants. The plaintiff brought suit for an accounting and payment of certain moneys which it claims to be due to it from a large number of defendants, in-[315]*315eluding each of these appellants, to wit, the Dayton Coal Co., the Milton Coal Co. and the Superior Coal Co. The claim of the plaintiff is based upon its alleged rights growing out of the performance by it of the provisions of certain contracts, which it says were entered into between it and each of the defendants on May 8 and 11, 1906. And the plaintiff uses this language in declaring what the contract was:

“Desiring to have said Plum Run mine operated on their joint account and for their joint benefit, entered into a contract with this plaintiff, by the terms of which they agreed that the plaintiff should proceed to operate the said Plum Run mine and deliver or consign the coal removed therefrom to such persons and at such places as a committee of said defendants known as an executive committee should direct, and that the said defendants last above named, would pay to the plaintiff all the expenses of every character and description connected with such operation upon presentation to such executive committee of properly receipted bills or vouchers showing the amount thereof, the same to be paid as so presented, and the plaintiff to be permitted to receive and retain five cents per ton for all the coal so mined and shipped. Thereupon the plaintiff at once entered upon the performance of said contract and in pursuance thereof, expended large amounts of money, and incurred large obligations on behalf of said defendants in preparing for and carrying on said mining operations for and in delivering and consigning said coal as provided in said agreement. By agreement of all of the said parties to the said contract such operation continued until June 20, 1906, on which date the defendants, Frank M. Osborne, J. J. Roby, George M. Jones, J. C. McKinley, Thomas E. Young, J. P. Burton, Charles E. Maurer, Franklin Neff, John Simpson, Lute Horniekel, Hudson E. Willard, Pitt Townsend, William B. Murray, F. P. Jones, Clifford Ayres, John F.. Johnson, William J. Sampson and Alfred S. McGary, many of whom were parties to the said Plum Run mine thereafter operated on their joint account and for their joint benefit by this plaintiff, entered into a contract with the plaintiff whereby it was agreed that the said operation of said mine should be continued in the same manner as that in which it had been conducted under the said contract of May 11, 1906, and that the said defendants last above named would assume and pay all the expense thereof from and after the time of the termination of the operations under the said contract of May 11, 1906. This plaintiff proceeded to operate the said mines, and incurred in doing so many large expenses and also at the request of the said parties incurred fur[316]*316ther expense in an effort to operate another mine known as plaintiff’s Crow Hollow mine, which effort, however, was shortly abandoned.”

These contracts, if any were made, were made at a meeting of representatives of the plaintiff and the several defendants, all of whom were operators of coal mines in what is known as the ‘ ‘ Ohio district, ’ ’ and at a meeting of what is known as the Eighth district, at Cleveland, on May 11th.

At the time of entering into these contracts there was a general strike among the miners in the district so extensive that it prevented the safe operation of any of the mines owned by the several parties, and the purpose of the contracts was that some one of the mines should be opened and the miners who should be employed in such mine, together with the property connected with the mine, should be protected. To do this it was resolved that:

“A general committee of fourteen be appointed by this body, which committee shall have full power to act under these resolutions in the selection of mines to be operated, to take charge of the operation of the same; to appoint sub-committees in the several districts in which such mines may be located, and also have power to levy assessments upon our tonnage to pay any expenses incurred therein. And we hereby pledge ourselves to pay such assessments as may be levied under these resolutions. ’ ’

That committee of fourteen was selected. Several meetings of the representatives of the parties to this suit were held. Without stopping to enumerate the action taken at each of these several meetings, suffice it to say that the arrangement made was that this committee of fourteen should select, as the resolution provided, a mine or mines to be operated. It selected what was known as Plum Bun mine of the plaintiff, as the one to be opened. That was opened and operated, in pursuance of the resolution. A large expense was incurred in opening and operating this mine, including as was contemplated by the parties, the employment of guards to protect the miners and the property. Assessments were made upon the several parties represented at these meetings, including these several defendants, for their proportionate share, by tonnage, of the expenses thus incurred. [317]*317These expenses were paid by the plaintiff and it now seeks to recover, after an accounting, the part of such expense which it claims the several defendants should pay. There is no dispute here as to the amount expended by the plaintiff, nor as to the proportionate share of the several defendants, provided it shall be found that they are under obligation to pay any part of this expense. On the part of the defendants, however, it is urged that no legal contract was entered into by which they are bound to respond in any sum whatever. It is .urged, first, that the alleged contract is against public policy, and it is said in argument, as sustaining this view, that the bringing of guards to protect this mine, which would have to be operated by strike breakers, if operated at all, was a menace to the strikers, and was calculated to bring about strife and bloodshed, not contemplated by the contract; that there were employed as guards for the purpose of protecting the miners and property, men from the Pinkerton Detective Agency, and that the feeling against men of that agency was such among the strikers that it was known that the employment of these men was likely to bring about the results already mentioned.

Certainly the employment of men to guard the property and the employees who should be engaged in working such property was a matter in which neither the strikers nor any other citizen outside of the parties to this contract had any interest. It was not a menace to any law-abiding citizen to have the property thus guarded. One may surely employ whom he will to guard his property and protect his employees against any danger which he apprehends, whether such apprehension be well founded or not, and whoever undertakes to interfere with or to prevent those thus guarding property and persons is himself to blame if any bloodshed or' other trouble comes from such guard of property and persons. It is not for outsiders to say what number of men or how strong a guard shall be put over one’s property and employees. If one apprehends that his property, his family, or his employees are in danger of interference by outsiders having no interest in the matter, he may employ what force he will, and as long as such force confines itself to the guarding of the persons and property which they are employed to guard, it is not [318]

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
32 Ohio C.C. Dec. 314, 17 Ohio C.C. (n.s.) 599, 1910 Ohio Misc. LEXIS 445, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-coal-co-v-osborne-ohcirctcuyahoga-1910.