United States Casualty Co. v. United States

67 F. Supp. 950, 107 Ct. Cl. 46, 1946 U.S. Ct. Cl. LEXIS 72
CourtUnited States Court of Claims
DecidedOctober 7, 1946
Docket45093
StatusPublished
Cited by7 cases

This text of 67 F. Supp. 950 (United States Casualty Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Casualty Co. v. United States, 67 F. Supp. 950, 107 Ct. Cl. 46, 1946 U.S. Ct. Cl. LEXIS 72 (cc 1946).

Opinion

JONES, Judge.

This is a suit to recover $16,200 liquidated damages assessed at the rate of $200 a day lor a period of 81 days’ delay in the completion of a construction contract in Puerto Rico.

The contract called for the construction of an auditorium for the University of Puerto Rico by Pedro A. de Castro, an individual contractor. Notice to proceed was received by the contractor on August 14, 1936. The stipulated time was 270 calendar days, thus fixing the completion date as May 11, 1937. The work was properly begun within the time specified, but was completed 81 days late.

The contractor was killed in an airplane accident October 18, 1936. The plaintiff as surety had executed a performance bond.

The contractor’s widow was appointed administratrix on October 20, 1936, and by letter dated October 24, 1936, advised defendant of that fact and asserted that the work was being delayed and would be further delayed as a consequence of her husband’s death, and requested an extension of 90 days for the proper and full completion of the contract.

The administratrix was unable to obtain the technical assistance and financial backing necessary to carry on the work. Consequently, on November S, 1936, she advised defendant in writing that she “must refuse further to prosecute the work.” On November 9, 1936, defendant notified the administratrix of its intention to terminate the rights of the contractor and the contractor’s estate under the contract unless within 10 days she would furnish assurance that she would continue to prosecute the work.

On November 11, 1936, the administratrix replied stating that she refused to prosecute the project further, and that she waived the 10 days’ notice. On November 13 defendant acknowledged receipt, advising the administratrix that all the rights of the contractor and the contractor’s estate under the contract were thereby terminated as of November 11, 1936.

Defendant by letter dated November 13, 1936, addressed to the plaintiff at San Juan but actually delivered by hand to plaintiff at Baltimore, Maryland, on November 18, 1936, notified plaintiff that all rights of the contractor and the contractor’s estate had been terminated as of November 11, 1936, and advised plaintiff that it had the right to take over and proceed with the performance of the contract. In the same letter defendant advised plaintiff that it had 10 days from the time of the mailing of the *952 notice within which to take over and proceed with the performance of the contract.

On the same date, November IB, 1936, plaintiff advised defendant that it would exercise its right to take over and proceed with the performance of the contract.

On the same date the plaintiff made an agreement with Luis R. Gonzalez to take over the contract work, and filed with the defendant its request for an extension of 60 days’ time in which to complete the work, claiming as a basis that the death of the contractor and the consequent negotiations for the transfer of the contract, and for securing the services of men with the necessary training and experience, had delayed and would continue to delay the progress of the work; that such delay would amount to more than 60 days, but it was believed that with the extension of 60 days it would be able to complete the project to the satisfaction of all concerned.

The project was completed in a satisfactory manner but the defendant refused to grant any extension of time and assessed the full liquidated damages at $200 a day for the entire 81 days’ delay in completion and withheld this amount from the contract price. The plaintiff sues for the recovery of this amount.

The form of the contract differs in some respects from the regular standard form customarily used in Government contracts.

The terms forbid the transfer of the contract or any part thereof unless such assignment or transfer was expressly authorized by the administrator and unless the sureties upon the performance and payment bond consented thereto or waived their right to notice of such assignment or transfer.

On the question of liquidated damages Article 16 of the contract reads in part as follows:

“(Par. 32) An extension of time equal to the time lost by delay shall be allowed to the Contractor for the completion of the project, if, during the progress of the project,

* * * * * *

“(b) the work should be delayed on account of, unforeseen causes beyond the control and not due to any fault or negligence of the Contractor, including, but not restricted to, Acts of God, acts of the public enemy, acts of the Administrator, acts of another contractor in the performance of a contract with the Administrator, fire, floods, epidemics, quarantine restrictions, strikes, or freight embargoes: “Provided, That the Contractor shall, within forty-eight (48) hours from the beginning of the cause of such delay submit to the Administrator written notice of such delay and proof satisfactory to the Administrator as to the impossibility of prosecuting the work for any of the above causes.”

Delay Due to Death of Contractor.

Plaintiff asserts that the death of the contractor was an unforeseen cause of delay, according to the terms of the quoted provision.

The contracting officer referred plaintiff’s request for an extension of time to-the chief architect of the project and to the general • counsel of the agency. The chief architect reported his findings and recommended that the 60 days’ extension of time be granted.

The contracting officer denied the request on the ground that he had no legal authority to grant such an extension of time, but stated that if plaintiff desired, the-claim would be presented to the Comptroller General who was the final administrative authority upon matters of that type.

Plaintiff thereupon submitted further-grounds upon which it believed an extension of time should be granted. It discussed! these grounds with the members of the legal staff of the defendant’s agency who-agreed that if such grounds did not appear to warrant the granting of an extension of time the whole matter would be referred to the office of the Comptroller General of the United States for final decision.

On March 1, 1937, the contracting officer set forth the essential, facts in a letter to-the Acting Comptroller General and requested an opinion as to whether under the-contract he was authorized to grant an. extension of time. In somewhat involved, language the Acting Comptroller General, advised that the terms of the contract did, not permit a remission of liquidated damages.

*953 Delay in Approval of Plans.

The plaintiff also requested an extension of 50 days in the time for completion on the ground that the chief architect had failed over a period of 50 days to review and return shop drawings required for the manufacture of steel.

On October 14, 1936, the chief architect of the project received from one of de Castro’s subcontractors a set of plans which were in the form of blue prints rather than original drawings. The contract required that such plans should be submitted to and approved by the chief architect.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sun Oil Co. v. United States
572 F.2d 786 (Court of Claims, 1978)
New York Shipbuilding Corporation v. The United States
385 F.2d 427 (Court of Claims, 1967)
Anthony Grace & Sons, Inc. v. The United States
345 F.2d 808 (Court of Claims, 1965)
Stein Bros. Mfg. Co. v. The United States
337 F.2d 861 (Court of Claims, 1963)
Stein Bros. Mfg. Co. v. United States
337 F.2d 861 (Court of Claims, 1963)
Brister & Koester Lumber Corp. v. United States
188 F.2d 986 (D.C. Circuit, 1951)

Cite This Page — Counsel Stack

Bluebook (online)
67 F. Supp. 950, 107 Ct. Cl. 46, 1946 U.S. Ct. Cl. LEXIS 72, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-casualty-co-v-united-states-cc-1946.