United Riggers & Erectors, Inc. v. Marathon Steel Co.

725 F.2d 87, 1984 U.S. App. LEXIS 26555
CourtCourt of Appeals for the Tenth Circuit
DecidedJanuary 11, 1984
DocketNo. 81-1717
StatusPublished
Cited by3 cases

This text of 725 F.2d 87 (United Riggers & Erectors, Inc. v. Marathon Steel Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Riggers & Erectors, Inc. v. Marathon Steel Co., 725 F.2d 87, 1984 U.S. App. LEXIS 26555 (10th Cir. 1984).

Opinion

LOGAN, Circuit Judge.

This diversity case arises out of a dispute between contractors erecting a coal preparation plant in Wyoming. Marathon Steel Company was the general contractor for the project, United Riggers & Erectors, Inc. was one of Marathon’s subcontractors, and Hartford Accident and Indemnity Company was the surety on United Riggers’ performance bond. We must decide whether the trial court erred in refusing to order United Riggers to reimburse Hartford for attorney’s fees and other costs it incurred in conducting a defense separate from United Riggers’ defense in litigation with Marathon.

Problems and delays plagued the construction project from the beginning. United Riggers was forced to begin working on its portion of the construction at a later date than planned, apparently in part because of problems caused by another Marathon subcontractor. This in turn resulted in delays and weather related problems for Marathon, United Riggers, and other subcontractors. Ultimately, Marathon terminated United Riggers’ subcontract because of dissatisfaction with its performance. Another Marathon subcontractor completed United Riggers’ portion of the project.

After terminating United Riggers, Marathon attempted to execute on United Riggers’ performance bond. Hartford contested Marathon’s right to the bond, claiming that United Riggers had not defaulted on its contract with Marathon and that in any event Hartford was released from the bond because United Riggers and Marathon had materially modified the contract without Hartford’s consent. However, Hartford did enter into an agreement to loan Marathon [89]*89$554,314 without interest and with a reservation of rights to enable Marathon to complete United Riggers’ portion of the project.

United Riggers subsequently filed suit against Marathon for breach of contract. Marathon counterclaimed against United Riggers and added Hartford as a third party defendant. Hartford responded by claiming it was entitled to indemnity from United Riggers in the event that Marathon recovered from Hartford. The jury found that United Riggers had not defaulted on its subcontract before being terminated, that United Riggers did not perform its work negligently, and that United Riggers had not been overpaid for the work it had performed. The jury also found that there had been no material modifications of the contract between Marathon and United Riggers that would entitle Hartford to be released from its obligations as surety. Because United Riggers was not liable to Marathon, Hartford, of course, suffered no loss on the bond.

Hartford then sought reimbursement from United Riggers for the attorney’s fees and other costs Hartford had incurred by hiring its own attorney to present its case. The district court concluded that Hartford’s decision to decline United Riggers’ offer to defend Hartford in the case and instead to hire its own attorney was unjustified because United Riggers could have adequately protected Hartford’s interests. The court also held that Hartford was not entitled to reimbursement because Hartford had not fulfilled its duty to request that United Riggers provide it with a defense. Hartford appeals from that decision.

In seeking reimbursement, Hartford relies on sections V and VII of the indemnity agreement between Hartford and United Riggers. Section V provides:

“The Indemnitors will indemnify the Surety against any and all liability, losses and expenses of whatsoever kind or nature (including but not limited to interest, court costs and counsel fees) which the Surety may sustain or incur (1) by reason of having executed any Bond issued hereunder, (2) by reason of the failure of the Principal or any of the other Indemnitors to perform or comply with the covenants and conditions of this Agreement or (3) in enforcing any of the covenants and conditions of this Agreement. The Indemni-tors will pay the Surety for all such losses or expenses as soon as liability therefor is asserted or exists, whether or not the Surety has made payment. Such payment shall be equal to the amount of the reserve set by the Surety; provided that in the case of any claim, demand or suit upon any of the Bonds, the Indemnitors may, subject to the provisions of Section VII, request the Surety to litigate or defend the matter.”

Section VII provides:

“The Surety shall have the right to adjust, settle or compromise any claim, demand, suit or judgment upon any of the Bonds, unless the Indemnitors (1) shall request the Surety to litigate such claim or demand, or to defend such suit, or to appeal from such judgment, and (2) shall deposit with the Surety, at the time of such request, cash or collateral satisfactory to the Surety in kind and amount, to be used in paying any judgment rendered or that may be rendered, with interest, costs, expenses and counsel fees, including those of the Surety.”

The parties agree that the law of California — the state in which the contract of indemnity was made — applies to this case. See generally Hall v. Chrysler Corp., 526 F.2d 350, 352 (5th Cir.1976). California law is clear that while an indemnitee is free to conduct its own defense, “absent some contractual privilege so to do or some showing of sufficient justification or need therefor, an indemnitee ordinarily may not refuse to join in or cooperate with the indemnitor’s proffered defense and still recover his separate and redundant attorneys’ fees and costs.” Buchalter v. Levin, 252 Cal. App.2d 367, 60 Cal.Rptr. 369, 371 (1967); accord Goodman v. Severin, 274 Cal.App.2d 885, 79 Cal.Rptr. 555, 562 (1969). In the instant case the district court found that Hartford was not justified in conducting a separate defense. We disagree.

[90]*90Hartford had two defenses to liability to Marathon. The first was that Hartford was not liable as surety for United Riggers because United Riggers had not defaulted on its subcontract. Assuming its continued financial solvency, United Riggers probably was capable of providing this defense. However, Hartford had reason to doubt United Riggers’ ability to satisfy a judgment and perhaps even its ability to remain solvent until the completion of the litigation. Hartford had requested collateral for its potential liability from United Riggers pursuant to section V of the indemnity agreement, but United Riggers was unable to supply that collateral. The reasons Marathon gave for terminating United Riggers’ subcontract included United Riggers’ failure to pay laborers and suppliers and its questionable financial ability to perform. Hartford was faced with liability of almost $1,000,000 on its performance bond if United Riggers was found in default and could not satisfy its obligation. These circumstances alone justified Hartford’s hiring separate counsel to defend itself. The district court’s factual findings to the contrary are clearly erroneous.

Hartford’s second defense was that Hartford had been released from liability under the performance bond because Marathon and United Riggers materially altered their contract without Hartford’s consent. The defense of material modification was adverse to United Riggers’ interests because United Riggers would be left without the performance bond to pay its liability to Marathon if Hartford succeeded on that theory. The existence of separate defenses is sufficient justification for the decision of a surety to hire its own legal counsel, see Buchalter v. Levin, 60 Cal.Rptr. at 372; Safeway Stores, Inc. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mele v. Commissioner
1988 T.C. Memo. 409 (U.S. Tax Court, 1988)
No. 81-1717
725 F.2d 87 (Tenth Circuit, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
725 F.2d 87, 1984 U.S. App. LEXIS 26555, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-riggers-erectors-inc-v-marathon-steel-co-ca10-1984.