United Natural Gas Co. v. Pennsylvania Public Utility Commission

33 A.2d 752, 153 Pa. Super. 252, 1943 Pa. Super. LEXIS 65
CourtSuperior Court of Pennsylvania
DecidedApril 22, 1943
DocketAppeals, 12 and 30
StatusPublished
Cited by8 cases

This text of 33 A.2d 752 (United Natural Gas Co. v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Natural Gas Co. v. Pennsylvania Public Utility Commission, 33 A.2d 752, 153 Pa. Super. 252, 1943 Pa. Super. LEXIS 65 (Pa. Ct. App. 1943).

Opinion

Opinion by

Keller, P. J.,

This appeal is concerned (1) with tbe interpretation of a regulation contained in Circular No. 9-A of tbe Public Service Commission — tbe predecessor of tbe present Public Utility Commission — relative to tbe gas pressure to be maintained by a natural gas company at its *254 consumer’s meter outlet; and (2) whether under that regulation — or otherwise — the Commission may reasonably order a natural gas company to furnish and install, at its own expense, the regulator equipment necessary to furnish natural gas service from a high-pressure transmission main to a rural consumer, whose property is not located along a low-pressure distribution line, and therefore requires the installation of a separate regulator to reduce the pressure so as to be safe for household use.

The complainants in this case, Mr. and Mrs. Parrett, reside and are the owners of property in Bradford Township, McKean County, two and three-quarters miles west of the City of Bradford, on the ‘West Branch Road’ leading from Bradford to Corydon. The respondent (appellant) is a natural gas company operating and doing business in the City of Bradford.

For some time prior to 1941 the Parretts, along -with some forty other persons located along said highway, had been receiving natural gas service from a high-pressure transmission line, operated by one Melhuish, who was producing some gas west of Bradford. The service was inadequate and unsatisfactory and failed to furnish gas to the consumers when and as needed. Accordingly Melhuish applied to the Public Utility Commission for leave to discontinue the service and at the same time have the United Natural Gas Company, this appellant (hereinafter called United) begin the furnishing of natural gas service, from a high-pressure transmission line, to his customers, many of whom, including the Parretts, joined in asking the Commission to approve the application. See Nos. A. 59930 and A. 59931.

In their petition, these consumers set forth that they were willing to be supplied by United under its usual conditions; and in that connection, they all, including the Parretts, signed written applications to United, asking it to supply them with natural gas from its high-pressure main, and agreed to pay for the furnishing, *255 laying and installation of all regulators and appliances necessary for tlie service, including pipes, fittings, valves, etc., the estimated cost to each customer not to exceed $50, $20 of which was paid on account.

A distinction must be made between high-pressure transmission mains used to transport natural gas, under pressures ranging from 50 to 75 pounds per square inch up to 300 pounds; medium-pressure lines, carrying pressures of 15 to 25 pounds per square inch; and low-pressure distribution lines which carry gas with a pressure of about four to eight ounces per square inch, for use by. consumers. To reduce the high pressure to a pressure adapted and safe for household consumption regulators must be used; and where an individual consumer located along a transmission main, but not along a distribution line, seeks gas service by tapping the transmission main, a regulator must be installed and “housed” to supply him with safe gas service. In fact, several regulators might be required if the pressure in the transmission main was above 75 pounds — e. g., if the pressure was 300 pounds, one regulator would step down the pressure to 150 pounds; another from 150 pounds to 75 pounds, and a third, from 75 pounds to four ounces, in order to furnish safe gas service to an individual consumer. It was the settled practice of natural gas companies — without objection by the Public Service Commission — to require the consumer, so located, to pay the cost of the necessary regulator and its installation.

In the transmission main used in this case only one step-down process was necessary, but a separate regulator had to be installed and housed for each individual customer’s service line.

In order to furnish the desired gas service promptly, the change from Melhuish to United had to be made in midwinter and under difficult weather conditions — for Melhuish’s equipment was in bad shape. The bill sent to the Parretts amounted to $15..07, of which $18.60 *256 was for labor. They filed a complaint with the Public Utility Commission, alleging that the charge was too high.

At the hearing, held pursuant to said complaint, the only item of the bill that was objected to by complainants was the charge for labor. The regulator owned and used by the Parretts on the old line was not in good working order, and while the cost of a new one was $22, the company accepted the old regulator plus a charge of $5 — that is, it allowed complainants $17 on their old regulator. Mr. Parrett testified with reference to the bill, “There is a labor charge of eighteen dollars and something [$18.60, itemized]; I will admit the meters are very reasonable [there was no charge for the meter], and the fittings, and such as that, because we handle those ourselves; and the regulator, that was very satisfactory” (p. 61a).

The testimony introduced by United should have satisfied the Commission as to the correctness of the labor charge; it was not rebutted by any definite evidence. To accommodate the consumers, the work was done in midwinter, when the ground was frozen, and the excavation was very hard, through a generally rocky formation. The regulator had to be ‘housed’, to keep it from deteriorating, and the reasonableness of the charge for this housing, $12, was not questioned.

The commission itself introduced no testimony, and did not suggest at the hearing that Circular No. 9-A, hereinafter referred to, applied to the case, nor did it question the validity or legality of the contracts made, before the installations, by United with its new customers, by which they (the customers) agreed to pay for the furnishing, laying and installation of the necessary regulator equipment.

Without any notice to the respondent of its intention to rule the case on a matter not alleged in the complaint, or raised at the hearing, the Commission, on February 10, 1912, handed down its report (1) sustain *257 ing the complaint, on the ground that Circular No. 9-A of the Public Service Commission, promulgated in 1914, applied and required the respondent to furnish and install at its expense all regulating equipment necessary to render service, regardless of the location of its pipelines; and ordering the respondent (2) to cease and desist from charging an applicant for service, or a consumer, for the installation of regulating equipment; and (3) henceforth to furnish and install at its expense all regulating equipment necessary to render service as required in Circular No. 9-A.

Although the order was filed on February 10, it was not served on respondent until February 18.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Popowsky v. Pennsylvania Public Utility Commission
853 A.2d 1097 (Commonwealth Court of Pennsylvania, 2004)
Durham Terrace, Inc. v. Hellertown Borough Authority
16 Pa. D. & C.2d 231 (Northampton County Court of Common Pleas, 1957)
City of Covington v. Sohio Petroleum Company
279 S.W.2d 746 (Court of Appeals of Kentucky (pre-1976), 1955)
Rydal-Meadowbrook Ass'n v. Pennsylvania Public Utility Commission
98 A.2d 481 (Superior Court of Pennsylvania, 1953)
Ridley Township v. Pennsylvania Public Utility Commission
94 A.2d 168 (Superior Court of Pennsylvania, 1953)
Altoona v. Pennsylvania Public Utility Commission
77 A.2d 740 (Superior Court of Pennsylvania, 1951)
Fayette County Gas Co. v. Pennsylvania Public Utility Commission
33 A.2d 761 (Superior Court of Pennsylvania, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
33 A.2d 752, 153 Pa. Super. 252, 1943 Pa. Super. LEXIS 65, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-natural-gas-co-v-pennsylvania-public-utility-commission-pasuperct-1943.