United Merchants & Manufacturers, Inc. v. Spare Parts (In re United Merchants & Manufacturers, Inc.)

126 B.R. 149, 1991 U.S. Dist. LEXIS 4799
CourtDistrict Court, S.D. New York
DecidedApril 15, 1991
DocketNo. 89 Civ. 2617 (JES)
StatusPublished
Cited by3 cases

This text of 126 B.R. 149 (United Merchants & Manufacturers, Inc. v. Spare Parts (In re United Merchants & Manufacturers, Inc.)) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Merchants & Manufacturers, Inc. v. Spare Parts (In re United Merchants & Manufacturers, Inc.), 126 B.R. 149, 1991 U.S. Dist. LEXIS 4799 (S.D.N.Y. 1991).

Opinion

MEMORANDUM OPINION AND ORDER

SPRIZZO, District Judge:

Plaintiff-Appellant United Merchants and Manufacturers, Inc. (“UMM”) appeals from an order of the United States Bankruptcy Court for the Southern District of New York (Blackshear, J.), which, upon consideration of whether a less severe sanction than dismissal would be appropriate, adhered to its original decision dismissing plaintiff’s complaint for failure to prosecute. UMM had appealed that original decision to this Court (Leisure, J.), which in an Opinion and Order dated May 20, 1988, affirmed the bankruptcy court’s findings but remanded the action to the bankruptcy court to consider whether some lesser sanction might be appropriate. For the reasons that follow, the decision of the bankruptcy court is affirmed.

[150]*150BACKGROUND

The underlying facts are set forth in Judge Leisure’s Opinion and Order, see United Merchants and Manufacturers, Inc. v. Spare Parts, 86 B.R. 764, 765-66 (S.D.N.Y.1988), and will not be repeated here.

In the first appeal, Judge Leisure reviewed the bankruptcy court’s dismissal in light of the following factors enunciated by the Second Circuit: (1) the length of the delay; (2) whether plaintiff had notice that the action would be dismissed; (3) the prejudice to the defendant from the lack of prosecution; (4) whether an adequate balance has been struck between the plaintiff’s due process rights and the court’s need to control its calendar; and (5) whether the court has adequately assessed the efficacy of lesser sanctions. See id. at 766 (quoting Alvarez v. Simmons Market Research Bureau, Inc., 839 F.2d 930, 932 (2d Cir.1988) (in turn quoting Harding v. Federal Reserve Bank of New York, 707 F.2d 46, 50 (2d Cir.1983)).

The district court agreed with the bankruptcy court’s finding that the plaintiff had done nothing for over five and one-half years despite the fact that plaintiff had the burden of prosecuting the action. See United Merchants, supra, 86 B.R. at 766-67. The court also agreed with the bankruptcy court that prejudice to the defendants could be presumed from the lengthy delay of five years, even though no actual prejudice was demonstrated. See id. at 767. Moreover, Judge Leisure noted that “UMM cannot be heard to claim that it is deprived of due process, for any deprivation is the result of its own course of conduct, carefully chosen and followed.” Id.1 However, since dismissal pursuant to Rule 41(b) is a harsh sanction, Judge Leisure remanded the case to the bankruptcy court for further consideration of whether some lesser sanction might be appropriate.

On remand, the bankruptcy court adhered to its original decision to dismiss the action, stating “[ajfter giving further consideration to lesser sanctions, this Court is convinced that any sanction other than dismissal would be an inappropriate remedy considering UMM’s calculated and carefully conceived strategy of inaction in the adversary proceeding.” Opinion and Decision On Remand From District Court at 7 (October 3, 1988) (“Remand Opinion”) (Joint Appendix (“JA”) 521).

DISCUSSION

The only issue before this Court is whether the bankruptcy court abused its discretion in adhering to its original decision to dismiss on remand. See Link v. Wabash Railroad Co., 370 U.S. 626, 633, 82 S.Ct. 1386, 1390, 8 L.Ed.2d 734 (1962); Harding, supra, 707 F.2d at 50; Lyell Theatre Corp. v. Loews Corp., 682 F.2d 37, 43 (2d Cir.1982); In re Stuart, 88 B.R. 247, 249 (9th Cir. BAP 1988). Since that issue involves the bankruptcy court’s discretionary control over the management of its docket, the scope of this Court’s review is “extremely narrow.” Theilmann v. Rutland Hospital, Inc., 455 F.2d 853, 855 (2d Cir.1972). The test, therefore, is not what this Court would have done under the same circumstances, but whether, in light of the record as a whole, the bankruptcy court’s decision was reasonable.

On remand, the Bankruptcy Court was faced with only one question, i.e., whether a sanction short of dismissal would have been effective or appropriate in view of the extensive delay in this case. Plaintiff argued that since its failure to prosecute was the result of clerical errors in its in-house counsel’s office and since the defendant had failed to answer two letters seeking to set a discovery schedule, the “draconian” sanction of dismissal should not be applied. Plaintiff also suggested a few alternatives, including an immediate trial and limiting further discovery to that needed by the defendants.

[151]*151The bankruptcy court rejected plaintiffs first argument because it was an attempt to relitigate its earlier decision, which had been affirmed by the District Court, that “UMM’s plan of inaction was the result of ‘its own willful delay’ with clear and foreseeable consequences.” Remand Opinion at 7 (quoting United Merchants, supra, 86 B.R. at 767) (JA.519). Moreover, the court explicitly considered and rejected UMM’s suggestion that the matter be set down for an immediate trial, which would have imposed on the defendants the burden of plaintiff’s protracted delay by requiring them to hastily prepare for the trial. See Remand Opinion at 9 (JA.521). Given the circumstance that UMM had made a strategic decision not to prosecute the action, this Court cannot say that the bankruptcy court abused its discretion in adhering to its previous decision to dismiss the action with prejudice. This is especially so since dismissal is a far more effective sanction to deter such dilatory litigation tactics than the other sanctions suggested by UMM.

Nor do the cases relied upon by UMM require a contrary result. Both Youngblood v. Citrus Associates of the New York Cotton Exchange, Inc., 99 F.R.D. 570 (S.D.N.Y.1983) and Lank v. New York Stock Exchange, 405 F.Supp. 1031 (S.D.N.Y.1975), rev’d on other grounds, 548 F.2d 61 (2d Cir.1977), are cases where the district court, exercising its discretion in the first instance, denied a motion to dismiss for failure to prosecute. They were not cases in which a district court was required to apply an abuse of discretion standard to a bankruptcy court’s order. Moreover, in Youngblood there was a stipulation between the parties, approved by the Court, which placed the case on the Court’s sus-pensé docket pending a decision by a regulatory agency as to whether to exercise its jurisdiction over the matter. After that agency declined jurisdiction, the action remained dormant because of a change in plaintiff’s counsel, the death of some of the parties, settlement negotiations, and the pendency of a controlling case before the Supreme Court. See 99 F.R.D. at 574-76. That case therefore, unlike this one, did not involve a unilateral decision by the party having the burden to prosecute to delay the proceedings for strategic reasons thereby placing the burden of going forward on the adverse party. In

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
126 B.R. 149, 1991 U.S. Dist. LEXIS 4799, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-merchants-manufacturers-inc-v-spare-parts-in-re-united-nysd-1991.