United Gas Pipe Line Company v. Federal Power Commission

350 F.2d 689
CourtCourt of Appeals for the Fifth Circuit
DecidedOctober 8, 1965
Docket21693_1
StatusPublished
Cited by7 cases

This text of 350 F.2d 689 (United Gas Pipe Line Company v. Federal Power Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Gas Pipe Line Company v. Federal Power Commission, 350 F.2d 689 (5th Cir. 1965).

Opinion

JOHN R. BROWN, Circuit Judge:

The question here is whether on expiration of the underlying gas sales contract with the seller still committed under the Natural Gas Act, the pipeline purchaser may be compelled to take deliveries at unilaterally increased prices until such time as the FPC approves abandonments. The FPC gave an affirmative answer. We agree and enforce.

Although decision is far from easy, the facts out of which the problem emerges are simple, neither complex nor conflicting.

In January 1953 Producer 1 and Pipeline 2 contracted for the sale and purchase of gas from Producer’s Johnson Bayou Field, Louisiana. This contract was for a primary term of ten years from January 31, 1953, and was subject to termination after the primary term upon notice by either party. During the term of the contract the specified contractual rate was 10.077^ per mcf including tax reimbursement. The contract was filed with the FPC and accepted as Producer’s Rate Schedule No. 115. Producer sought and obtained a certificate of public convenience and necessity authorizing the sale of gas to Pipeline in accordance with its filed rate schedule (of which the contract was the embodiment) and commenced initial delivery of gas on January 31, 1955. 3 Pipeline also sought and obtained a certificate of public convenience and necessity authorizing the construction of facilities necessary to take the gas from Continental. 4 Both Producer and Pipeline did in fact construct facilities in Johnson Bayou Field to permit the sale, purchase and taking of such gas. The Johnson Bayou gas comes from two wells completed on Producer’s lease in the field. The facilities installed by Producer were more extensive 5 than those of Pipeline. 6 The delivery point of the gas is located ■ at a valve at the j'uncture of Producer’s 2y2 inch flow line and Pipeline’s 4 inch pipeline. These facilities were used continuously for delivering and taking the gas from the time of initial delivery on January 31, 1953, until Pipeline shut off the valve and ceased taking gas on January 31, 1963.

As permitted under the contract, within ninety days prior to the expiration of the primary term of the contract, Producer gave notice to Pipeline of termination of the contract at the end of the primary term. This notice of termination was acknowledged by Pipeline. The contract expired according to its terms on January 31, 1963. Producer’s effective rate schedule was not terminated, however.

*691 During the last months of the contractual term, Producer and Pipeline endeavored to negotiate a new contract. These negotiations were unsuccessful. In brief, Pipeline’s position was essentially an offer to extend the old contract either on a relatively long-term basis at the same price and other terms, or, on a day-to-day basis at the same price and other terms. Producer sought a new long-term contract with an increased price reaching 18.75$ mcf but within the range of the applicable current South Louisiana price level under General Policy No. 61-1 for “old” gas. When negotiations broke down, Pipeline advised Producer that it did not need the gas, and that it would support an application by Producer for abandonment of the certificate. Producer declined and gave the notice of termination.

After giving notice of termination, Producer filed in December 1962 a notice of change in rate pursuant to § 4(e) effectuating a unilateral change in rate under its Rate Schedule No. 115 effective January 31, 1963. This provided for an increased rate to 15.75$ per mcf including tax reimbursement. 7 Producer’s existing rate schedule remained effective and unchanged in all other respects.

FPC accepted the rate change to become effective without suspension. Although Pipeline opposed the filing of the unilateral rate change and unsuccessfully sought rehearing of the approval order, Pipeline did not take timely review of this order. The order permitting the rate increase to become effective thus became final. 8

On learning of the final order approving the rate increase, Pipeline notified Producer just two days prior to the expiration date (January 31, 1963) that it would not continue to purchase gas from Johnson Bayou Field after that date. Pipeline did not request permission from FPC to cease operating the facilities used in taking gas or to abandon the service, or the purchase, transmission and resale of Johnson Bayou gas. In accordance with its notice, Pipeline ceased taking the gas on January 31, 1963.

Almost immediately Producer petitioned the FPC to direct Pipeline “ * * to show cause why it should not be required to continue to take deliveries of gas produced * * * in the Johnson Bayou Field * * * at the currently filed and effective rate * * Declining this relief, the FPC did direct Pipeline to show cause “why it should not be required to apply for and obtain the permission and approval of the * * * Commission before ceasing the operation of all or any portion of the facilities heretofore operated by [it] to purchase natural gas from” the Producer. After a hearing the Examiner’s initial decision dismissed the show cause order, but on review and oral argument, the Commission, 9 by divided vote, 10 in an opinion by Commissioner O’Connor held that the Pipeline’s refusal to make any use, for an indefinite time, of the facilities for the purchase of gas constituted an abandonment under § 7(b) and it ordered Pipeline to resume purchasing gas at the rate specified in Rate Schedule No. 115.

There was great reoccupation with cessation. 11 Undertaking to answer the attacks which are reiterated here by the Pipeline 12 and stressing the importance *692 of § 7(b), 13 the opinion emphasized that this section “frames the relevant issue, not in terms of whether this Commission has the power to compel continued purchases, but whether the ‘public convenience and necessity’ dictates that pipe lines cease purchasing * * (Emphasis the Commission’s.)

But it seems quite clear that the FPC hardly thought that the impact of its decision was any different by casting it in terms of a requirement that permission be obtained to cease performance rather than an order compelling continuation of an activity. Thus, describing the contention that although the producer must continue to sell while the Pipeline-Purchaser need not buy, as “paradoxical results” to which “we cannot subscribe,” the FPC concluded “that if the power to compel the continuation of sales is not to be reduced to mere illusion, the power to compel

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
350 F.2d 689, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-gas-pipe-line-company-v-federal-power-commission-ca5-1965.