United Electrical Contractors, Inc. v. Southwest Sound and Electronics, Inc.

Court of Appeals of Texas·Decided May 27, 2009·No. 04-08-00126-CV·Published

Opinion

i i i i i i

MEMORANDUM OPINION

No. 04-08-00126-CV

UNITED ELECTRICAL CONTRACTORS, INC., Appellant

v.

SOUTHWEST SOUND AND ELECTRONICS, INC., Appellee

From the 37th Judicial District Court, Bexar County, Texas Trial Court No. 2006-CI-19005 Honorable John D. Gabriel, Jr., Judge Presiding1

Opinion by: Marialyn Barnard, Justice

Sitting: Rebecca Simmons, Justice Steven C. Hilbig, Justice Marialyn Barnard, Justice

Delivered and Filed: May 27, 2009 REVERSED AND REMANDED Southwest Sound and Electronics, Inc. was granted a partial summary judgment awarding it damages for its breach of contract claim against United Electrical Contractors, Inc. A final judgment was entered after a bench trial on the issue of attorneys’ fees. On appeal, United contends the trial court erred by: (1) granting a traditional motion for summary judgment on Southwest’s

… The Honorable Michael Peden granted a partial summary judgment, and the Honorable John D. Gabriel

1

signed a final judgment after a bench trial regarding the issue of attorneys’ fees.

breach of contract claim because a fact issue was raised with regard to the scope of work Southwest was required to perform; (2) granting a no-evidence motion for summary judgment on United’s affirmative defenses of payment and compromise and settlement; and (3) awarding Southwest $25,000 in attorneys’ fees. We reverse the trial court’s judgment and remand the cause to the trial court for further proceedings.

BACKGROUND

United’s bid for a renovation project at an elementary school was accepted by a school district. Southwest submitted a bid of $9,231.00 to United for the intercom system portion of the project. Southwest’s bid specifically stated, “SECTION(S) / SYSTEM(S): 16730 INTERCOM.” The bid also referred to section 16723 of the project manual, but the project manual does not contain a section 16723. Ray Alaniz, a Southwest employee, testified that this reference was a typographical error and was intended to refer to section 16730.

United accepted Southwest’s bid with a purchase order that described the work as follows:

SECTION : 16730 - INTERCOM COMPLETE INSTALLATION AND RENOVATIONS TO EXISTING INTERCOM SYSTEM AS PER DRAWINGS & SPECIFICATIONS FOR THE ABOVE REFERENCED PROJECT

In March of 2003, the contract administrator for the school district, Paul Kniestedt, sent a request to United asking it to “provide this office with a cost to provide and install 15 speakers and intercom stations in existing portable classrooms.” Southwest submitted a bid to United of $6,842.76 for materials and labor to install the 15 additional speakers. United then submitted a bid to Kniestedt of $8,204.10 to add the 15 speakers, which included $6,555.00 as the amount for material and labor for the installation of the speakers.

At some point either before or after March of 2003, the school district had decided to move the portable classrooms because the anticipated attendance at the elementary school would not require their use. Kniestedt used the bid submitted by United as a basis for a change order credit in the amount of $6,555.00.2 The change order was based on one sentence at the end of the twelve pages comprising section 16010 of the project manual requiring United to include in its base bid, “All costs to install and provide 15 each additional speakers and intercom stations in existing portable building.”3 United then processed a change order deducting $6,555.00 from its contract with Southwest based on its contention that the single sentence from section 16010 of the project manual was included in its contract with Southwest.

Upon completion of the work required by section 16730, Southwest submitted an invoice to United for $9,138.40. On July 18, 2006, Southwest’s attorney sent United a demand letter for payment in the amount of $9,138.40. On October 17, 2006, Southwest’s attorney sent United a

2 … United’s President, Philip Garcia, was upset with Kneistedt, believing he had “tricked” United regarding the contract. In his deposition, Garcia stated:

And then he turned around – and we just overlooked that one sentence in the specifications, and tricked us and flipped it to a credit. W e gave him a price. And then Paul, laughing, and said, “Hey, it’s going to be a credit now.” And he tricked us.

I don’t want to say conniving. I mean, it’s a nice word for conniving. But he tricked us into giving him a price of 15 additional – it says “additional speakers”. It don’t say the speakers and the – And then he turned it into a credit. And I said, “Paul, that’s not right.” And all Paul said was, with a grin, “For the good of the children.”

3 … Section 16010 of the project manual contains the details regarding the electrical requirements for the project describing the work as including, “Furnishing of all required materials, equipment, tools, scaffolding, labor and transportation necessary for the complete installation of the electrical systems as shown on the drawings and as specified herein.” On page twelve of section 16010, a provision entitled “Additional Materials” states:

Include in the Base Bid:

All costs to install and provide 5 additional communication outlet or signal locations, all required boxes and conduits as directed by the Architect.

All costs to provide 5 additional electrical outlets, all required wiring, conduit, labor and devices as directed by the Architect.

All costs to provide 5 additional light fixtures equal in value to Metalux Model BT-P410-32-TBW -

120EB81, all required lamps, wiring, switches, conduit, labor and devices as directed by the Architect.

All costs to install and provide 15 each additional speakers and intercom stations in existing portable buildings.

second demand letter for payment, stating that a lawsuit would be filed on October 23, 2006, if no response was received.

After Southwest had filed the underlying lawsuit, Southwest’s attorney sent a third demand letter on June 5, 2007, demanding payment of $9,138.40 within thirty days. On June 20, 2007, United tendered a check in payment of the June 5, 2007 demand. On July 10, 2007, Southwest’s attorney sent United’s attorney a letter returning the check. The letter stated that the June 5, 2007 letter was sent in error and that the actual amount required to settle the matter was $25,000.00 based on the attorney’s fees that had been incurred. United subsequently amended its answer in the underlying lawsuit to assert payment and compromise and settlement as affirmative defenses.

Southwest filed a traditional motion for summary judgment with regard to its breach of contract claim and a no-evidence motion for summary judgment with regard to United’s affirmative defenses. With regard to the affirmative defenses, the no-evidence motion states that United can offer no evidence that indicates “That [United] has any excuse or other affirmative defense that excuses their performance of the contract, namely paying [Southwest].” The trial court granted summary judgment in favor of Southwest and also awarded Southwest attorneys’ fees after a bench trial.

STANDARD OF REVIEW

Courts review traditional and no-evidence motions for summary judgment de novo. Valance Operating Co. v. Dorsett, 164 S.W.3d 656, 661 (Tex. 2005); Eastin v. Dial, No. 04-06-00377-CV, 2009 WL 196215, at *4 (Tex. App.—San Antonio Jan. 28, 2009, no pet. h.). A no-evidence motion for summary judgment should be granted if the non-movant fails to present more than a scintilla of probative evidence to raise a genuine issue of material fact on the challenged element. Ford Motor

Free access — add to your briefcase to read the full text and ask questions with AI

United Electrical Contractors, Inc. v. Southwest Sound and Electronics, Inc., (Tex. Ct. App. 2009).

United Electrical Contractors, Inc. v. Southwest Sound and Electronics, Inc. (United Electrical Contractors, Inc. v. Southwest Sound and Electronics, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Ford Motor Co. v. Ridgway
135 S.W.3d 598 (Texas Supreme Court, 2004)
Valence Operating Co. v. Dorsett
164 S.W.3d 656 (Texas Supreme Court, 2005)
Peter C. Browning v. Jeff P. Prostok
165 S.W.3d 336 (Texas Supreme Court, 2005)
Frost National Bank v. L & F Distributors, Ltd.
165 S.W.3d 310 (Texas Supreme Court, 2005)
Coker v. Coker
650 S.W.2d 391 (Texas Supreme Court, 1983)
Brownlee v. Brownlee
665 S.W.2d 111 (Texas Supreme Court, 1984)
Eastin v. Dial
288 S.W.3d 491 (Court of Appeals of Texas, 2009)
Garner v. Fidelity Bank N.A.
244 S.W.3d 855 (Court of Appeals of Texas, 2008)
Callaghan Ranch, Ltd. v. Killam
53 S.W.3d 1 (Court of Appeals of Texas, 2001)
Ebner v. First State Bank of Smithville
27 S.W.3d 287 (Court of Appeals of Texas, 2000)
Aquila Southwest Pipeline, Inc. v. Harmony Exploration, Inc.
48 S.W.3d 225 (Court of Appeals of Texas, 2001)
American Tobacco Co., Inc. v. Grinnell
951 S.W.2d 420 (Texas Supreme Court, 1997)
Hussong v. Schwan's Sales Enterprises, Inc.
896 S.W.2d 320 (Court of Appeals of Texas, 1995)