United Construction Co. v. United States

120 F. Supp. 760, 128 Ct. Cl. 262, 1954 U.S. Ct. Cl. LEXIS 130
CourtUnited States Court of Claims
DecidedMay 4, 1954
DocketNo. 49526
StatusPublished

This text of 120 F. Supp. 760 (United Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Construction Co. v. United States, 120 F. Supp. 760, 128 Ct. Cl. 262, 1954 U.S. Ct. Cl. LEXIS 130 (cc 1954).

Opinion

Jones, Chief Judge,

delivered the opinion of the court:

This case involves a construction contract. The issue relates to the proper classification of materials that were excavated in carrying out the terms of the contract.

The contract, dated March 12,1945, was for the construction of certain irrigation trenches and installations for the Bureau of Reclamation at the Deschutes Project in the State ■of Oregon. The plaintiff was to furnish all materials, with •designated exceptions, and to perform all work required for the completion of the laterals and sublaterals.

[264]*264The specifications called for submission of unit prices on 17 items of work. Pertinent details of the specifications are set out in finding 1.

The contract price for common excavation in laterals was-30 cents per cubic yard, and for rock $2.25 per cubic yard. In the excavation for structures the price for common excavation was 75 cents, and for rock $4 per cubic yard.

According to the specifications the rock excavation included.

All solid rock in place which cannot be removed until loosened by blasting, barring, or wedging, and all boulders or detached pieces of solid rock more than one-half cubic yard in volume. Solid rock under this class, as-distinguished from soft or disintegrated rock under common excavation, which also requires blasting before removal, is defined as sound rock of such hardness and texture that it cannot be loosened or broken down by hand drifting picks. No material except boulders or detached pieces of solid rock, will be classified as rock excavation, which is not actually loosened by blasting before removal, unless blasting is prohibited, and barring, wedging, or similar methods are prescribed by written order of the-contracting officer.

Common excavation included “all material other than rock excavation.”

Based upon the plaintiff’s bid for the 17 contract items and the defendant’s estimate of quantities, the consideration in the-contract was estimated to total $101,395. The work was to be completed within 100 calendar days.

■ The contract contained the standard provisions in reference to disputes, by the terms of which all questions of fact, arising under the contract were to be decided by the contracting officer, subject to an appeal to the head of the department, or his authorized representative.

The plaintiff acknowledged receipt of notice to proceed on April 12, 1945. The work was not completed until May' 25, 1946; extensions of time were granted by findings of the contracting officer to cover the entire period of prolonged operations.

During the performance of the work disputes arose over the classification of material. Plaintiff complained that the estimated quantities of rock excavation were inadequate and. that hardpan, disintegrated rock and cemented gravel should [265]*265be paid for as rock excavation. There were nnmerons discussions between the contracting officer and the various contractors on the project, which included plaintiff. Substantial quantities of compact material, such as cemented gravel and hardpan were encountered and their excavation was required under the contract. In computing the quantities for payment of monthly estimates during the progress of the work these materials were generally classified as common -excavation and paid for at the contract price applicable thereto in accordance with the provisions of Paragraph 33 •of the specifications which defined common excavation in the ■following terms:

All materials other than rock excavation; including, but not restricted to earth, gravel, and also such hard and compact material as hardpan, cemented gravel, and soft or disintegrated rock, which cannot be removed efficiently by team-drawn scrapers or excavating machinery until loosened by blasting; also all boulders or detached pieces of solid rock not exceeding one-half cubic yard in volume.

Following the discussions the construction engineer consulted the Chief of Engineers of the Bureau of Reclamation, who was the contracting officer, in an effort to ascertain whether, regardless of the provisions of the specifications, the hardpan, cemented gravel and disintegrated rock should be excavated and paid for as rock excavation. Following ■this inquiry it was decided that the construction engineer should be permitted to consider and classify certain of these materials as rock excavation, recompute the quantities of •excavation that had been made under the strict terms of the contract, and pay for the quantities thus ascertained at the •contract price applicable to solid rock.

There were also disputes as to the total quantities involved in some of the areas of excavation and a resurvey was made under the personal supervision of the construction engineer. Representatives of the contractor accompanied the construction engineer and his party on the resurvey of the main lateral system on July 18, 1946, and made no objection to the method of reclassification used.

The construction engineer personally examined all disputed .areas of excavation, dug into the slopes back to undisturbed [266]*266materials, examined the spoil banks and consulted all available field records made throughout the progress of the work.

The construction engineer undertook to determine the quantities and percentages of rock and common excavation and to determine what part of the material such as hardpan should be included in the classification of rock excavation under the liberal classification authorized and adopted. In reclassifying, the construction engineer included considerable quantities of hardpan, cemented gravel, and similar materials as rock rather than as common excavation. This action resulted in an increase of the quantity of rock excavation in laterals from 6,068 to 18,293.9 cubic yards, and in the rock excavation for structures from 897 to 2,840.7 cubic yards. The quantities of common excavation were accordingly decreased.

The effect of this reclassification increased the total payment made under the contract to $138,159.85 instead of the amount which had been estimated as $101,395.

In connection with the final settlement and final voucher the contractor executed a release on the contract dated September 5, 1946; in executing this release, however, it excepted nine claims totaling $236,374.24. The items of exceptions are set out in finding 4.

Plaintiff had especially contended that it should be paid for 7,855.3 cubic yards of rock excavation in laterals and for 2,459.5 cubic yards in structures. These claims and the other items excepted from the release were reiterated in a letter from the plaintiff dated September 21, 1946, in which an early determination of plaintiff’s claims by the contracting officer and the head of the department was requested.

In order to give plaintiff full opportunity to present all the facts and supporting data a conference was held in Denver on March 26 and 27, 1947, which was attended by representatives of the plaintiff. Thereafter the contracting officer sent a representative to the project to make a detailed examination of the work. On the basis of all the information obtained it was the decision of the contracting officer that all excavated materials had been properly classified by the construction engineer; that the quantities of rock excavation determined by him were accurate and that no ad[267]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mayor of Mobile v. Emanuel
42 U.S. 95 (Supreme Court, 1843)

Cite This Page — Counsel Stack

Bluebook (online)
120 F. Supp. 760, 128 Ct. Cl. 262, 1954 U.S. Ct. Cl. LEXIS 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-construction-co-v-united-states-cc-1954.