United Builders, Inc. v. Hala

258 A.2d 115, 5 Conn. Cir. Ct. 508, 1968 Conn. Cir. LEXIS 241
CourtConnecticut Appellate Court
DecidedJune 28, 1968
DocketFile No. CV 5-675-7653
StatusPublished

This text of 258 A.2d 115 (United Builders, Inc. v. Hala) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Builders, Inc. v. Hala, 258 A.2d 115, 5 Conn. Cir. Ct. 508, 1968 Conn. Cir. LEXIS 241 (Colo. Ct. App. 1968).

Opinion

Kosicki, J.

The plaintiff sued the defendants for work and services performed and materials furnished in the remodeling of the defendants’ house in North Haven. The first count alleges an oral contract and the second one is based on quantum meruit for the services, labor and materials furnished. Upon a trial to the court, judgment was rendered for the plaintiff to recover of the defendants $3010 on the complaint and for the defendants to recover of the plaintiff $650 on their counterclaim.

[510]*510The defendants have not moved to correct the court’s finding on appeal. Practice Book §§ 981, 985 & Form 819 (B). The conclusions of the trial court must be tested by the finding and not by the evidence. Klahr v. Kostopoulos, 138 Conn. 653, 655. The defendants cannot bypass the finding. The court’s conclusions must prevail unless they are legally or logically inconsistent with the facts found or invoke the application of some erroneous rule of law material to the case. Yale University v. Benneson, 147 Conn. 254, 255; Monick v. Greenwich, 144 Conn. 608, 611; Jack Torosian, Inc. v. Guastamachio, 139 Conn. 754, 757; Bridgeport Hydraulic Co. v. Sciortino, 138 Conn. 690, 692. Therefore the finding riiust stand.

The finding discloses the following facts found and the conclusions reached by the court. The plaintiff is a Connecticut corporation organized in June, 1961, by Paul Collins and John Fazzone, who are the principal owners. From June, 1961, to June, 1966, the plaintiff performed about 600 jobs consisting of remodeling kitchens, building garages, basement playrooms, room additions and dormers, and applying house sidings. The plaintiff always entered into formal written contracts with its customers. Before May, 1966, Collins and the defendant Edward Hala had known each other for about three or four years. During that month Edward Hala consulted with Collins concerning the remodeling of a house at 1 Leona Street in North Haven which Edward Hala was contemplating buying.1 He wanted from Collins an estimate of the cost of certain work which he in[511]*511tended to have performed on the premises. Collins was reluctant to furnish an estimate without going over the house thoroughly and checking labor and material costs with his subcontractors. It appears nowhere in the record that any plans, drawings or specifications of the proposed construction were at any time submitted to the plaintiff or that the plaintiff had full access to the premises for the purpose of structural inspection. At Hala’s insistence, the plaintiff on June 15, 1966, gave the defendants an estimate (exhibit A) for certain work to be performed at an estimated cost of $5800. By oral stipulation, handwritten material is not included in the exhibit. About mid-July, Edward Hala authorized the plaintiff to proceed with the work. Collins asked that the matter be reduced to a formal written contract. This Hala refused to do, but he authorized the plaintiff to perform the work on the basis of cost of labor and materials furnished plus a 10 percent profit on them for the plaintiff. The plaintiff finally agreed to this arrangement and proceeded with the work on July 22, 1966. The work was completed about the middle of September, 1966.

The plaintiff provided the defendants with a progress report on August 5, 1966, which indicated that the cost of the work was exceeding the “estimate” given on June 15, 1966. The plaintiff’s actual cost for materials and labor in performing the work required by the defendants was $9372.73. The agreed profit to the plaintiff of 10 percent amounted to $937.27. The plaintiff substantially performed the work required in a workmanlike manner. There were some imperfections or deficiencies which needed correction, such as repairing a bannister, amounting to $100; correcting sliding doors and tracks, which would cost $200; and rectification of molding and trim, at a cost of $250. There were also needed some sanding and taping of the walls built [512]*512by tbe plaintiff, which would entail a further expense of $100. The defendants had paid the plaintiff a total of $7300.

The trial court concluded that the parties entered into a contract for the performance of certain work in remodeling the defendants’ house on a “cost-plus” basis, that is, the defendants were to pay the plaintiff a sum equal to the actual cost of labor and materials plus a profit of 10 percent based on that cost. The total cost of the work amounted to $10,310. Crediting the defendants with the payment of $7300 already made, the defendants owed the plaintiff a balance of $3010. On the counterclaim, the defendants were entitled to recover $650, leaving a net balance in favor of the plaintiff of $2360.

In their argument on appeal, the defendants expressly abandoned any attempt to correct the finding, as well they might, in view of the rules of law we have alluded to above. The assignment of errors presents only two claims for our review. The first claim, briefly stated, is that the finding and the plaintiff’s exhibits fail to sustain the court’s ultimate conclusion that the defendants owe the plaintiff $3010. Stated verbatim, the reasons given by the defendants for this assignment are: (1) “Plaintiff’s Exhibit A is an estimate for certain work; (2) the plaintiff’s subsequent exhibits indicate that a portion of the work specified in Exhibit A was never done; and (3) as a matter of law, plaintiff’s gross claim must be limited to a sum reasonably approximating the estimate for the work actually done, less payments made by the defendants.”

As to the first two reasons quoted above, the defendants cannot, in this oblique manner, seek to lay a foundation for disturbing the subordinate facts in order to import a point of law which does not appear in the conclusions of the court or in any document [513]*513before ns on appeal. "We cannot say that there was no evidence reasonably supporting the findings, and they must stand. Zieky v. Beckerman, 112 Conn. 688, 689. No correction in the facts found can be contemplated without the transcript, and that is not before us. McCulley v. Marino, 24 Conn. Sup. 229, 231, 1 Conn. Cir. Ct. 517, 518. The conclusions reached by the court must stand unless unsupported by the finding. Bridgeport Hydraulic Co. v. Sciortino, 138 Conn. 690, 692. The trier is the sole arbiter of the credibility of the witnesses. Metz v. Hvass Construction Co., 144 Conn. 535, 537. “It is the privilege of the trier to adopt whatever testimony he reasonably believes to be credible.” Grote v. A. C. Hine Co., 148 Conn. 283, 287.

The cases cited by the defendants in support of their contention that exhibit A was a firm or contractual estimate for the work to be done are not in point. “ ‘The law does not make a contract when the parties intend none, nor does it regard an arrangement as completed which the parties thereto regard as incomplete.’ ” New Haven Tile & Floor Covering Co. v. Roman, 137 Conn. 462, 464. Much reliance is placed on the decision in Miller Franklin & Co. v. Gentry, 230 Mo. App. 892. In that case, suit was brought by the plaintiff for engineering services rendered a receiver appointed by a federal court to administer a firm then in receivership. Bracket estimates (low and high) were given the receiver by the plaintiff, dealing separately with cost of services and the living expenses of personnel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Misisco v. La Maita
192 A.2d 891 (Supreme Court of Connecticut, 1963)
Guerrieri v. Merrick
143 A.2d 644 (Supreme Court of Connecticut, 1958)
Oborski v. New Haven Gas Co.
197 A.2d 73 (Supreme Court of Connecticut, 1964)
Yale University v. Benneson
159 A.2d 169 (Supreme Court of Connecticut, 1960)
Grote v. A. C. Hine Co.
170 A.2d 138 (Supreme Court of Connecticut, 1961)
Metz v. Hvass Construction Co.
135 A.2d 363 (Supreme Court of Connecticut, 1957)
Spencer v. Board of Zoning Appeals
104 A.2d 373 (Supreme Court of Connecticut, 1954)
Lavoie v. Marshall
109 A.2d 508 (Supreme Court of Connecticut, 1954)
New Haven Tile & Floor Covering Co. v. Roman
78 A.2d 336 (Supreme Court of Connecticut, 1951)
Klahr v. Kostopoulos
88 A.2d 332 (Supreme Court of Connecticut, 1952)
Bridgeport Hydraulic Co. v. Sciortino
88 A.2d 379 (Supreme Court of Connecticut, 1952)
Monick v. Town of Greenwich
136 A.2d 501 (Supreme Court of Connecticut, 1957)
State v. Silver
93 A.2d 154 (Supreme Court of Connecticut, 1952)
Jack Torosian, Inc. v. Guastamachio
97 A.2d 116 (Supreme Court of Connecticut, 1953)
Zieky v. Beckerman
153 A. 163 (Supreme Court of Connecticut, 1931)
McCulley v. Marino
189 A.2d 510 (Connecticut Superior Court, 1962)
Miller Franklin & Co. v. Gentry
79 S.W.2d 470 (Missouri Court of Appeals, 1935)
City of Fort Myers v. State
95 Fla. 704 (Supreme Court of Florida, 1928)
Lambert v. Sanford
12 A. 519 (Supreme Court of Connecticut, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
258 A.2d 115, 5 Conn. Cir. Ct. 508, 1968 Conn. Cir. LEXIS 241, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-builders-inc-v-hala-connappct-1968.