This text of United Brotherhood of Carpenters v. Tappan Zee Constructors, LLC (United Brotherhood of Carpenters v. Tappan Zee Constructors, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Brotherhood of Carpenters v. Tappan Zee Constructors, LLC, (2d Cir. 2015).

Opinion

15‐1002 United Brotherhood of Carpenters v. Tappan Zee Constructors, LLC

UNITED STATES COURT OF APPEALS FOR THE SECOND CIRCUIT ______________

August Term, 2015

(Argued: August 19, 2015 Decided: October 20, 2015)

Docket No. 15‐1002 ____________

UNITED BROTHERHOOD OF CARPENTERS AND JOINERS OF AMERICA,

Petitioner‐Appellant,

‐v.‐

TAPPAN ZEE CONSTRUCTORS, LLC,

Respondent‐Appellee.

______________

Before: RAGGI AND WESLEY, Circuit Judges.1

1 Judge Cabranes was initially assigned to this matter and subsequently recused himself. Pursuant to this Court’s Internal Operating Procedure E, after a matter has been assigned to a three‐judge panel, if for any reason a panel judge ceases to participate in consideration of the matter, the two remaining judges may decide the matter if they agree.

Appellant United Brotherhood of Carpenters and Joiners of America, on behalf of itself and local unions Dockbuilders Local 1556 and Carpenters Local 279, appeals from a judgment entered on March 31, 2015, in the United States District Court for the Southern District of New York (Carter, J.). Before the District Court, Appellant sought (1) enforcement of an initial arbitration award issued on May 4, 2014; and (2) vacatur of a subsequent award issued on May 13, 2014. Appellee cross‐petitioned seeking enforcement of the award issued on May 13, 2014. We hold that, absent any provision in the arbitration agreement to the contrary, the arbitrator had the authority to determine that he could issue a second decision reaching a result directly contrary to the earlier award. We therefore AFFIRM the District Court’s judgment denying the Appellant’s petition and granting the Appellee’s cross‐petition.

JAMES M. MURPHY, DeCarlo & Shanley, Los Angeles, CA (Daniel M. Shanley, Spivak Lipton LLP, New York, NY, on the brief), for Petitioner‐Appellant United Brotherhood of Carpenters and Joiners of America.

WILLIS J. GOLDSMITH (Joshua Grossman, on the brief), Jones Day, New York, NY, for Respondent‐Appellee Tappan Zee Constructors, LLC.

WESLEY, Circuit Judge:

This case arises from the disputed assignment of certain construction work

on the Tappan Zee Hudson River Crossing Project (the “Project”) to replace the

Tappan Zee Bridge across the Hudson River in New York. The work is governed

by the New York State Thruway Authority Project Labor Agreement Covering

2 the Tappan Zee Hudson River Crossing Project (the “Project Labor Agreement”

or “PLA”).

Appellee Tappan Zee Constructors, LLC (“TZC”) was awarded the

contract to design and build the Project on December 17, 2012. After winning the

contract, TZC divided assignments for three different categories of formwork

between two local unions, Dockbuilders Local 1556 (“Dockbuilders”) and

Carpenters Local 279 (“Carpenters”), both of which are represented by the

Appellant, an umbrella labor organization called the United Brotherhood of

Carpenters and Joiners of America (“UBC”). The Dockbuilders were assigned

the “formwork, up to and including the pile caps” (“pile formwork”). Joint App.

133. The Carpenters were assigned the “formwork from the top of the pile caps

up to and including the pier caps” (“pier formwork”) and the “formwork for all

columns including the main span tower forms” (“column formwork”). Id.

The Dockbuilders disputed the assignment of the pier and column

formwork to the Carpenters. Pursuant to Article 10, Section 3 of the PLA, all

jurisdictional disputes on the Project are resolved under the National Plan for the

Settlement of Jurisdictional Disputes in the Construction Industry (the “Plan”),

the purpose of which is to expeditiously resolve disputes over construction work

3 assignments without strikes, work stoppages, or other disruptions. In

accordance with the Plan, UBC submitted the dispute over the assignment of the

pier and column formwork to the Plan Administrator on January 13, 2014. The

following day, UBC requested and the Plan Administrator agreed to hold in

abeyance any action on the dispute while the unions discussed settlement.

During settlement negotiations, the Dockbuilders and the Carpenters

agreed that both the pier and column formwork should be assigned to the

Dockbuilders. UBC informed TZC of this agreement on April 7, 2014, and on

April 14, 2014, the Plan Administrator accordingly directed TZC to reassign the

pier and column formwork from the Carpenters to the Dockbuilders.

TZC opposed the unions’ settlement agreement. The Dockbuilders’ hourly

rate of $92.47 is considerably higher than the Carpenters’ hourly rate of $70.11;

reassignment of the pier and column formwork thus would cause the cost of the

Project to increase by a total of nearly $7.3 million. Pursuant to the PLA, any

jurisdictional dispute that remains unresolved by initial meetings “shall proceed

to final and binding arbitration in accordance with the principles and procedures

set forth in the rules of the Plan.” Joint App. 109 (PLA Art. 10, Sec. 3(C)).

Adhering to PLA procedure, TZC informed the Plan Administrator on April 15,

4 2014 that it disagreed with the proposed reassignment and requested that the

dispute be submitted to arbitration. J.J. Pierson was designated arbitrator of the

dispute under the Plan and conducted a hearing on April 28, 2014.

Pursuant to the Plan, in resolving a jurisdictional dispute such as the one

here, an arbitrator is required to address three criteria: (a) “whether a previous

agreement of record or applicable agreement . . . governs”; (b) “if the Arbitrator

finds that the dispute is not covered by an appropriate or applicable agreement

. . . he shall then consider the established trade practice in the industry and

prevailing practice in the locality”; and (c) “if none of the above criteria is found

to exist, the Arbitrator shall then consider that because efficiency, cost or

continuity and good management are essential to the well being of the industry,

the interests of the consumer or the past practices of the employer shall not be

ignored.” Joint App. 61 (Plan Art. 5, Sec. 8). An arbitrator must “set forth the

basis for his decision and . . . explain his findings regarding the applicability of”

these three criteria. Joint App. at 62 (Plan Art. 5, Sec. 8). Article 10, Section 3(D)

of the PLA required Pierson to “render a short‐form decision within 5 days of the

hearing based upon the evidence submitted at the hearing, with a written

5 decision to follow within 30 days of the close of the hearing.” Joint App. 110

(PLA Art. 10, Sec. 3(D)).

On May 4, 2014, Arbitrator Pierson issued his short‐form award in a four‐

page decision titled “AWARD” (“May 4th Award”). In this decision, Arbitrator

Pierson stated that he resolved the matter on the basis of Article 5, Section 8(b) of

the Plan. Specifically, he found that “an established trade practice in the

industry and prevailing practice in the locality” required assignment of the

disputed formwork to the Dockbuilders. Joint App. 20. On May 5, 2014, the Plan

Administrator forwarded the decision to the parties under a transmittal letter

enclosing “a copy of Arbitrator Pierson’s Award” and explaining that

“Arbitration [sic] Pierson has stated that he expects to provide his full Opinion

soon.” Joint App. 184.

On May 6, 2014, TZC notified the Plan Administrator of its intent to appeal

the arbitrator’s decision. The Plan Administrator responded acknowledging

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
United Brotherhood of Carpenters v. Tappan Zee Constructors, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-brotherhood-of-carpenters-v-tappan-zee-cons-ca2-2015.