United Arab Shipping Co. v. PB Express, Inc.

2011 Ohio 4416
CourtOhio Court of Appeals
DecidedSeptember 1, 2011
Docket96162
StatusPublished

This text of 2011 Ohio 4416 (United Arab Shipping Co. v. PB Express, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Arab Shipping Co. v. PB Express, Inc., 2011 Ohio 4416 (Ohio Ct. App. 2011).

Opinion

[Cite as United Arab Shipping Co. v. PB Express, Inc., 2011-Ohio-4416.]

Court of Appeals of Ohio EIGHTH APPELLATE DISTRICT COUNTY OF CUYAHOGA

JOURNAL ENTRY AND OPINION No. 96162

UNITED ARAB SHIPPING COMPANY PLAINTIFF-APPELLEE

vs.

PB EXPRESS, INC. DEFENDANT-APPELLANT

JUDGMENT: REVERSED AND REMANDED

Civil Appeal from the Cuyahoga County Court of Common Pleas Case No. CV-688180 BEFORE: Sweeney, P.J., Cooney, J., and S. Gallagher, J.

RELEASED AND JOURNALIZED: September 1, 2011

ATTORNEY FOR APPELLANT

John M. Manos, Esq. 739 East 140th Street Cleveland, Ohio 44110

ATTORNEY FOR APPELLEE

Susan Hartman Muska, Esq. One South St. Clair Street, Suite 2-C Toledo, Ohio 43604-8786

JAMES J. SWEENEY, P.J.:

{¶ 1} Defendant-appellant PB Express, Inc. (“PB”) appeals the court’s judgment in

favor of plaintiff-appellee United Arab Shipping Co. (“United”). After reviewing the facts of

the case and pertinent law, we reverse and remand to the trial court.

{¶ 2} United contracted with PB to transport shipping containers to and from a port in

Savannah, Georgia. The transactions between the parties are governed by the Uniform

Intermodal Interchange and Facilities Access Agreement (“UIIA”). Pursuant to the UIIA, PB

had an allotted amount of time to complete each transport without being required to pay per

diem use charges.

{¶ 3} In the spring of 2008, fuel costs rose to unprecedented levels, and the

independent contractors who PB hired to transport the containers were delayed or not responding to transport requests. As a result, containers were not transported within the

allotted time, and United invoiced PB $25,342.50 in per diem use charges. PB refused to pay

the charges, arguing that the independent contractors’ refusal to work was beyond its control.

{¶ 4} On March 24, 2009, United filed suit against PB to collect the outstanding debt.

On October 27, 2010, the case was tried to the bench. PB stipulated to United’s account but

argued that it was exempt from paying the per diem use charges under the force majeure

clause of the UIIA. The court granted judgment to United, finding that “[t]he actions by the

independent truck drivers were dictated by economic hardship and do not constitute a strike,”

rendering the UIIA’s force majeure clause inapplicable.

{¶ 5} PB appeals and raises one assignment of error for our review.

{¶ 6} “I. The trial court’s restrictive interpretation of the force majeure clause is

contrary to law because the cause for delay was a work stoppage beyond the appellant’s

control similar to a strike.”

{¶ 7} The standard of review to be applied to the instant case is twofold. Contract

interpretation is a matter of law, which courts review under a de novo standard. Taylor Bldg.

Corp. of Am. v. Benfield, 117 Ohio St.3d 352, 2008-Ohio-938, 884 N.E.2d 12, ¶35. “When a

trial court makes factual findings, however, supporting its determination [regarding contract

interpretation] * * *, those factual findings should be reviewed with great deference.” Id. at

¶37. {¶ 8} The force majeure clause in the UIIA states as follows:

{¶ 9} “In the event [PB] is unable to [transport the containers] within the free time * *

* as a result of Acts of God, war, insurrections, strikes, fire, flood or any like causes beyond

[PB’s] control, [PB] shall be exempted from the per diem charges to the extent of, and for the

duration of, the condition that prevented the redelivery of the [containers].”

{¶ 10} In its judgment entry, the trial court made the following findings of fact

pertinent to this appeal, which are supported by competent, credible evidence in the record:

{¶ 11} “5. In the Spring of 2008, fuel costs rose to unprecedented levels.

{¶ 12} “6. The independent truck drivers [PB] had previously hired were delayed or

not responding to [PB’s] requests for interchange transport * * *.

{¶ 13} “7. As a result, equipment remained at the port beyond the scheduled time for

departure. [United] charged [PB] per diem service fees totaling $25,342.50.

{¶ 14} “* * *

{¶ 15} “9. The UIIA contains a force majeure provision, which would exempt [PB]

from per diem charges in the event of a strike.”

{¶ 16} Additionally, the trial court came to the following conclusions of law:

{¶ 17} “10. Black’s Law Dictionary defines a strike as: ‘An organized cessation or

slowdown of work by employees to compel the employer to meet the employees’ demands; a

concerted refusal by employees to work for their employer, or to work at their customary rate of speed, until the employer grants the concessions that they seek.’ Black’s Law Dictionary

(9 ed. 2009). ht

{¶ 18} “11. ‘A party cannot be excused from performance merely because performance

may prove difficult, burdensome, or economically disadvantageous.’ Stand Energy Corp. v.

Cinergy Services, Inc., (2001), 144 Ohio App.3d 410, citing State ex rel. Jewett v. Sayre

(1914), 91 Ohio St. 85; Millers Cove Energy Co., Inc. v. Moore (C.A.6, 1995), 62 F.3d 155.

{¶ 19} “12. The actions by the independent truck drivers were dictated by economic

hardship and do not constitute a strike.

{¶ 20} “13. The UIIA’s force majeure provision is inapplicable, and therefore, [PB]

is not exempted from the per diem fees charged by [United].”

{¶ 21} Upon review, we find that the independent contractors’ refusal to work excused

PB’s performance under the language of the UIIA’s force majeure clause, “* * * as a result of

* * * strikes * * * or any like causes beyond [PB’s] control.” The motivation or reasoning

behind the refusal to work is not a part of the definition of “strike” cited by the trial court. In

fact, we venture to say that many strikes are dictated by economic hardship; regardless,

cessations of work until demands are met constitute strikes. See, generally, Sterling & Welch

Co. v. Duke (1946), 67 N.E.2d 24, 28 (stating that “[i]n all labor disputes there is what is

known as an allowable area of economic conflict, the principal weapon of economic conflict

being that of the strike”). {¶ 22} The facts of Stand Energy Corp., upon which the trial court relied in reaching its

decision, are distinguishable from the facts at hand. In Stand, the plaintiff refused to perform

under the contract, which would have required it to “purchase power at high market prices and

provide it to Cinergy at a low contract price,” because of “unseasonably hot temperatures * *

*, record demand for power and unprecedented high hourly prices for electric power. * * * At

trial, Stand Energy’s president testified that she had relied upon force majeure to preserve the

economic vitality of the company, and to save the jobs of fifty employees.” Id. at 417. The

court held that “[t]he inability to purchase a commodity at an advantageous price is not a

contingency beyond a party’s control,” and may not subsequently constitute a force majeure.

Id. at 416. In Stand, there was no evidence of a refusal to work by employees or independent

contractors.

{¶ 23} In the instant case, however, the court did not find, and the evidence does not

show, that PB failed to perform because of high gas prices. Rather, the court found that PB

failed to perform because its independent contractors “were delayed or not responding” to

work orders.

Free access — add to your briefcase to read the full text and ask questions with AI