Union Hill Homes Ass'n, Inc. v. RET DEVELOPMENT

83 S.W.3d 87, 2002 Mo. App. LEXIS 1755, 2002 WL 1966541
CourtMissouri Court of Appeals
DecidedAugust 27, 2002
DocketWD 60091
StatusPublished
Cited by28 cases

This text of 83 S.W.3d 87 (Union Hill Homes Ass'n, Inc. v. RET DEVELOPMENT) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Union Hill Homes Ass'n, Inc. v. RET DEVELOPMENT, 83 S.W.3d 87, 2002 Mo. App. LEXIS 1755, 2002 WL 1966541 (Mo. Ct. App. 2002).

Opinion

EDWIN H. SMITH, Judge.

This case arises out of a dispute between Union Hill Homes Association, the appellant, and RET Development Corporation, the respondent, relating to the construction by the respondent of single-family residences on three lots: 2978 Grand (owned by the respondent), 2913 Walnut, and 2911 Walnut, located in the Union Hill subdivision of Kansas City, Missouri. On September 17, 1998, the appellant’s board of directors passed a resolution approving site plans submitted by the respondent for the construction of the three residences. However, the board’s approval was subject to the condition that plans for landscaping, grading, sprinkler systems, etc., as well as samples of exterior building materials to be used, would have to be submitted to and approved by the appellant’s Architecture Review Committee. In an apparent attempt to ensure the respondent’s compliance with the requirements of the resolution, the resolution further provided that the respondent would give the appellant a *89 lien on each of the three lots. The resolution also included a provision that any ensuing disputes between the parties would be arbitrated pursuant to the rules of the American Arbitration Association.

On August 18, 1999, the appellant filed an application in the Circuit Court of Jackson County for a temporary restraining order (TRO), Case Number 99-CV-216360, to prohibit the respondent from further construction activities on the Union Hill properties. In support of its application, the appellant alleged that the respondent was engaging in landscaping, grading, and exterior building activities on the three subject properties without having first submitted the plans and samples pertaining to such activities for approval by the Architecture Review Committee, as required by the board resolution of September 17, 1998. On August 25, 1999, the respondent filed a motion asking the court to dismiss the appellant’s application for TRO and compel arbitration of the appellant’s claims pursuant to the arbitration provision in the September 17, 1998, resolution. The record does not indicate that the motion was ever ruled upon.

On August 27, 1999, the trial court took up and heard the appellant’s application for TRO. After a recess in the hearing, the parties advised the court that they had reached a written settlement agreement, denominated “Agreement for Restrictive Covenant (2978 Grand)” (the Agreement). However, the parties requested that the court retain jurisdiction of the case pending the effectuation of the Agreement. The court agreed to retain the case on its docket until October 15, 1999, at which time the case was to be dismissed, unless otherwise requested by one or both of the parties.

The Agreement provided that, although the respondent had agreed to sell the real property at 2978 Grand to Mike and Pamela Whitman, the respondent would not convey title until the respondent had submitted plans on all three lots to the appellant for review and approval as required by the September 17, 1998, resolution; the improvements on all three lots were completed in accordance with the approved plans; and the respondent had repaired or paid for any damages resulting from its construction activities on the three lots. The Agreement also provided that, upon the respondent’s compliance with these requirements, the appellant would execute a certificate of completion that such construction and repairs had been completed in accordance with the plans. The Agreement further provided that the parties, prior to instituting a court proceeding, would attempt to resolve any dispute regarding the appellant’s issuance of the certificate of compliance through non-binding mediation.

On October 12, 1999, three days before the deadline established by the trial court for dismissing the pending case unless otherwise requested by one or both of the parties, the appellant filed a motion to retain the case on the docket, alleging that, although some progress had been made toward effectuating the Agreement, there continued to be conflict between the parties concerning the respondent’s construction activities that “may require prompt referral to this Court for guidance or determination.” The record does not indicate that the appellant’s motion was ever ruled upon, but in any event, the record indicates that the case was not dismissed on October 15,1999.

In November of 1999, as a result of the mediation provision in the Agreement, the parties engaged in four days of mediation that resulted in a “Memorandum of Agreement” (the Memorandum) that was signed by the appellant on November 11, 1999, and by the respondent on November 12, *90 1999. The Memorandum provided that the respondent would complete grading, irrigation, and landscaping requirements; as well as complete trim, column, and deck work; replace a driveway; and finish work on a circle drive light, a circle drive retaining wall, and a sidewalk entry. The Memorandum further provided that, if such work was completed as required, the appellant would then issue a certificate of compliance releasing its restrictive covenant on 2978 Grand.

On January 19, 2000, the respondent filed a motion with the trial court to enforce the Memorandum. The respondent alleged, in its motion, that the appellant had failed to perform its obligations under the Memorandum by refusing to issue the certificate of compliance that would release its restrictive covenant on 2978 Grand. The respondent further alleged that the appellant’s failure to issue the certificate of compliance and release the restrictive covenant prevented it from closing with the Whitmans on the residence.

On January 21, 2000, the trial court held an evidentiary hearing on the respondent’s •motion to enforce the Memorandum. On that same date, the trial court entered its judgment ordering the parties to fully perform under that agreement, finding that the Memorandum was a valid and binding contract on the parties.

On February 4, 2000, the respondent filed a motion to hold the appellant in contempt, alleging that the respondent had performed all acts required by the Memorandum, but that the appellant still refused to issue the certificate of compliance. The motion further alleged that, because the certificate had not been issued, the respondent could not close on the residence at 2978 Grand, and as a result, the respondent was incurring damages in the amount of $42.51 per day in interest on a construction loan, as well as attorney’s fees and expenses.

On June 5, 2000, the trial court took up and heard the respondent’s motion for contempt, and entered a judgment on June 23, 2000, finding that the respondent had substantially complied with the January 21, 2000, judgment of the court and the Memorandum, but that the appellant had knowingly and voluntarily faded to comply therewith by failing to issue the certificate of compliance on 2978 Grand, by failing to release the lien thereon and by continuously refusing to comply with the judgment enforcing the Memorandum, and that such conduct was intentional and constituted contempt of court. To purge itself of contempt, the trial court ordered that:

[Wjithin ten days of the date of this Order UHHA shall complete the following:
1. UHHA pay RET $4,756.53, the interest incurred by RET on the construction loans on the property at 2978 Grand,
2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joseph Kyle Metheney v. Melanie Ann Metheney
Missouri Court of Appeals, 2019
Bramble v. Bramble
303 Neb. 380 (Nebraska Supreme Court, 2019)
Smotherman v. White
556 S.W.3d 655 (Missouri Court of Appeals, 2018)
Danelle M. Frantz, n/k/a Danelle M. Shipp v. David B. Frantz
488 S.W.3d 167 (Missouri Court of Appeals, 2016)
Edmondson v. Edwards
280 S.W.3d 752 (Missouri Court of Appeals, 2009)
In Re Marriage of Tibbs
177 S.W.3d 855 (Missouri Court of Appeals, 2005)
Braveheart Real Estate Co. v. Peters
157 S.W.3d 231 (Missouri Court of Appeals, 2004)
In Re Marriage of Crow and Gilmore
103 S.W.3d 778 (Supreme Court of Missouri, 2003)
Farmers Exchange Bank v. Metro Contracting Services, Inc.
107 S.W.3d 381 (Missouri Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
83 S.W.3d 87, 2002 Mo. App. LEXIS 1755, 2002 WL 1966541, Counsel Stack Legal Research, https://law.counselstack.com/opinion/union-hill-homes-assn-inc-v-ret-development-moctapp-2002.