Union Electric Company v. Jones

356 S.W.2d 857, 1962 Mo. LEXIS 725
CourtSupreme Court of Missouri
DecidedApril 9, 1962
Docket49093
StatusPublished
Cited by16 cases

This text of 356 S.W.2d 857 (Union Electric Company v. Jones) is published on Counsel Stack Legal Research, covering Supreme Court of Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Union Electric Company v. Jones, 356 S.W.2d 857, 1962 Mo. LEXIS 725 (Mo. 1962).

Opinion

STOCKARD, Commissioner.

This appeal arises out of proceedings brought by Union Electric Company to obtain title to certain land by condemnation to construct electric generating facilities.

Union Electric is a public utility authorized to engage in the manufacture and transmission of electric current for light, heat and power, and for the sale thereof to the public. It obtained the approval of the Missouri Public Service Commission to build, operate and maintain in Reynolds County, Missouri, additional electric generating facilities comprising “a high head pumped storage electric generating station, consisting of five major components, to-wit: a dam, a lower pool, an upper pool, a water way, and a pumping and generating stations, together with necessary transmission lines leading therefrom.” Union Electric proposes to construct the dam across the East Fork of Black River which appellants assert, and Union Electric does not deny, is a nonnavigable stream. This dam will form the lower pool which will have an area of approximately 370 acres, and a substantial portion of the 240 acre tract of appellants’ land which Union Electric seeks to condemn will be flooded thereby. The upper pool with an area of about 50 acres will be constructed about a mile away on top of Prof-fit Mountain at a substantially higher level than the lower pool. A tunnel 6,300 feet in length will lead from the upper pool to a power plant adjacent to the East Fork of Black River, but which is not located at or near to the dam forming the lower pool. When the project is completed electric energy from steam generating facilities in St. Louis will be used during periods when the use of electricty is at a minimum to pump water from the lower pool to the upper pool. *859 When peak loads occur the water will be permitted to flow through the tunnel from the upper pool to the lower pool and generate electric power at the power plant. The entire project will be operated electronically by controls in St. Louis.

Appellants first contend on this appeal that Union Electric does not possess the power or authority to condemn their land, or any part of it, pursuant to Chapter 236 (all statutory references are to RSMo 1959, V.A.M.S., unless otherwise stated) and that the limited power of eminent domain therein granted is exclusive to what they contend is a general power of eminent domain contained in Chapter 523. Both Chapters grant the power of eminent domain in certain factual situations, and each Chapter as now written sets forth the procedure to exercise that power. However, Civil Rule 86, V.A.M.R., now governs the procedure to be followed in the exercise of the power of eminent domain granted by either Chapter. See Civil Rule 86.01, V.A.M.R.

What is now Chapter 236, commonly referred to as the mill dam act, was first enacted in 1822, see Vol. I, Territorial Laws of Missouri, p. 948, but it then pertained to the construction of a dam and of water, grist, and saw mills on a watercourse. By 1835 the application of the act had been limited to a “water course not being a navigable stream.” R.S.1835, p. 406, § 1. In 1905, Laws 1905, p. 232, apparently as the result of the ruling in Southwest Missouri Light Co. v. Scheurich, 174 Mo. 235, 73 S.W. 496, the act was amended to extend the authority to construct a dam across a nonnavigable stream to “any * * corporation chartered and organized to construct, operate and maintain mills, electric power and light works, or other machinery.” We are not concerned in these proceedings with whether Union Electric has complied with the mill dam act, if applicable, and obtained authority to construct the dam. We are concerned only with the grant therein of the power of eminent domain. Section 236.010 provides that certain persons and corporations “may erect a dam” across a nonnavigable stream “if such person or corporation is the proprietor of the land through which the watercourse runs at the point where it is proposed to erect such dam, by proceeding as herein provided.” It appears from the testimony that at the time these condemnation proceedings were commenced Union Electric owned the land on both sides of the watercourse at the site of the dam. Provision is made to determine the “damages each proprietor will sustain by reason of inundation consequent upon the erection of the dam.” Whether the person or corporation building the dam is to obtain title to the land inundated or only flooding rights thereover is not clear, but the inference is that title is not to. be obtained. There is no authority to obtain any interest in land not inundated, even for generating facilities, except that when the land on only one side of the stream is owned, a maximum of one acre may be obtained on the other side to abut the dam. Provision is made that the jury selected to determine .the damages should determine whether “the mansion house of any such proprietor, or the outhouses, curtileges or gardens thereto, immediately belonging, or orchard, will be overflowed” and whether and to what exent “ordinary navigation” (on a nonnavigable stream?) and the passage of fish will be obstructed, as well as other things. It is further provided that if no objections be filed to the proceedings, and it shall appear to the court that the mansion house of any proprietor, or the outhouse, curtilages or gardens thereto belonging, or orchard will not be overflowed, and that the health of the neighborhood will not be materially affected by the stagnation of water, the court shall thereupon grant or refuse the permission prayed for to build the dam according to its judgment of what would be most reasonable and just under all circumstances.

We shall now look to Chapter 523. It apparently represents a consolidation of various grants of the power of eminent domain to companies organized for various *860 purposes. See Laws of Missouri 1851, p. 259 § 8, pertaining to plank roads and macadamized roads; Laws of Missouri 1853, p. 128, §§ 13 and 14, pertaining to railroads; Laws of Missouri 1866, p. 47, pertaining to land taken for telegraph, road and railroad purposes; and Laws of Missouri 1919, p. 207 pertaining to oil, pipeline or gas corporations. In 1915 the power of eminent domain was granted to “any electrical corporation organized for the manufacture or transmission of electric current for light, heat or power.” Laws of Missouri 1915, p. 227. Insofar as applicable to the grant of the power of eminent domain to electric companies, Section 523.-010 now provides: “In case land, or other property is sought to be appropriated by * * * any electrical corporation organized for the manufacture or transmission of electric current for light, heat or power, including the construction (when that is the case) of necessary dams and appurtenant canals, flumes, tunnels and tailraces and including the erection (when that is the case) of necessary electric steam powerhouses, hydroelectric powerhouses and electric substations * * and the corporation and the owners cannot agree upon the proper compensation, then certain procedure is to be followed, which, however, is now subject to Civil Rule 86, V.A.M.R.

It is thus apparent that there are two statutes relating .to the power of eminent domain of electric companies. These provisions must be read in pari materia and, if possible, effect given to each clause and provision. Davenport v. Teeters, Mo.App., 273 S.W.2d 506, 510.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carroll Electric Cooperative Corp. v. Lambert
403 S.W.3d 637 (Missouri Court of Appeals, 2012)
Osage Water Co. v. Miller County Water Authority, Inc.
950 S.W.2d 569 (Missouri Court of Appeals, 1997)
State ex rel. State Highway Commission v. Mann
624 S.W.2d 4 (Supreme Court of Missouri, 1981)
Enger v. Estate of Gianino
609 S.W.2d 719 (Missouri Court of Appeals, 1980)
Craig v. Jo B. Gardner, Inc.
586 S.W.2d 316 (Supreme Court of Missouri, 1979)
State ex rel. State Highway Commission v. Moore
565 S.W.2d 810 (Missouri Court of Appeals, 1978)
Greystone Heights Redevelopment Corp. v. Nicholas Investment Co.
500 S.W.2d 292 (Missouri Court of Appeals, 1973)
Seadade Industries, Inc. v. Florida Power & Light Co.
232 So. 2d 46 (District Court of Appeal of Florida, 1970)
State Ex Rel. State Highway Commission v. Foeller
396 S.W.2d 714 (Supreme Court of Missouri, 1965)
State Ex Rel. State Highway Commission v. Klipsch
392 S.W.2d 287 (Supreme Court of Missouri, 1965)
Southwestern Bell Telephone Co. v. Newingham
386 S.W.2d 663 (Missouri Court of Appeals, 1965)
Union Electric Co. v. Mount
386 S.W.2d 126 (Missouri Court of Appeals, 1964)
Missouri Edison Co. v. Gamm
379 S.W.2d 166 (Missouri Court of Appeals, 1964)
In re Union Electric Co.
356 S.W.2d 300 (Missouri Court of Appeals, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
356 S.W.2d 857, 1962 Mo. LEXIS 725, Counsel Stack Legal Research, https://law.counselstack.com/opinion/union-electric-company-v-jones-mo-1962.