Union Electric Co. v. Lovell Livestock Co.

54 P.2d 112, 101 Mont. 450, 1936 Mont. LEXIS 8
CourtMontana Supreme Court
DecidedJanuary 5, 1936
DocketNo. 7,446.
StatusPublished
Cited by3 cases

This text of 54 P.2d 112 (Union Electric Co. v. Lovell Livestock Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Union Electric Co. v. Lovell Livestock Co., 54 P.2d 112, 101 Mont. 450, 1936 Mont. LEXIS 8 (Mo. 1936).

Opinions

MR. JUSTICE STEWART

delivered the opinion of the court.

This is the second appeal in a case wherein Union Electric Company, a public service corporation, owner and operator of an electric plant at Dillon, is the plaintiff, and Lovell Livestock Company, a corporation owning land adjacent to the plant, is the defendant. For a more complete statement of the case, see 93 Mont. 577, 20 Pac. (2d) 255.

The water used for generating power in the plant is discharged directly from a tailrace into a ditch on defendant’s land. From thence it is conducted across the land.of defendant and into what is known as the Sturgis ditch and on into the Beaverhead River. The Sturgis ditch was constructed for the purpose of conveying the waste water from the plant to the river so as to prevent the flooding of adjacent lands, particularly lands owned by one Rose Heavey, John Butala and others. Before this ditch was constructed, the parties to this action and others were involved in litigation by reason of flooding by such waste waters. On October 31, 1917, the electrie company and the Lovell Company agreed on a basis of settlement, and on that day entered into a written agreement wherein the electric company was party of the first part and the Lovell Company was party of the second part. By the terms of the agreement the electric company was required to, and did, execute a quitclaim deed conveying to the Lovell Company “all of its right, title and interest in and to all the waters of Lovell’s warm springs and Brown’s springs, after their discharge from its hydroelectric plant,” together with the full, complete and absolute control and use thereof. By 'that agreement the electric com *453 pany also agreed to execute and deliver to the defendant a deed conveying to it certain land theretofore purchased by it from one George Rebich for right of way for the Sturgis ditch and upon which it was constructed.

The contractual part of the instrument was preceded by the recitation of certain reasons for making the agreement. Among these reasons it was recited that the parties desired to finally settle, adjust and determine all differences, disputes, claims and demands between them, with reference to all matters, things, claims and demands that then existed and arising since the Rose Heavey litigation, and as to the future use, control and domination of and over the waters of Lovell warm springs and Brown’s springs and of the Sturgis ditch after the waters were discharged from the hydro-electric plant of the first party. It will thus be observed that very specific and plainly expressed reasons were recited as to' the actuating causes for the agreement.

The contractual part of the agreement itself provided: “And as a part of the consideration of this agreement and to the end of all controversies between the parties hereto arising or existing •from all past transactions since the Rose Heavey litigation, it is agreed between the parties hereto, that from this date, the party of the second part will henceforth and forever, as against the party of the first part, maintain, operate and care for the said ‘Sturgis ditch’ and the waters of Lovell’s warm springs and Brown’s springs discharged and released from the hydroelectric plant of the first party to be conveyed therein, and will hold the said first party and its successors altogether harmless and free from any future costs ificident to the maintenance of the said ditch and the diversion of the said waters thereby, and from all future costs, charges, trouble and damage, or litigation, by reason of or on account of the care, flow and control of said waters, excepting only such damages as may hereafter arise from negligence of the party of the first part.”

This contract remained in effect, and during the winters of 1920-21 and 1921-22 the Sturgis ditch filled with snow and ice, *454 and as a result the lands of one Butala were flooded. * Thereafter Butala instituted an action against plaintiff to recover damages. Plaintiff notified defendant of the pendency of the action, and demanded that it defend the same, but this defendant refused to do. Butala finally recovered a judgment against plaintiff, and, as a result thereof, plaintiff was compelled to pay him the sum of $882.30.

Thereafter, plaintiff brought this action against defendant under the indemnity provisions of the contract and sought, in addition to the amount of the judgment paid, the sum of $220.25-for attorneys’ fees expended in the Butala action. The trial court awarded plaintiff only nominal damages, upon the theory that plaintiff and defendant were joint tort-feasors. Plaintiff appealed from the-judgment to this court, where the judgment was reversed and a new trial ordered.

Before the second trial, defendant amended its answer so as to raise an issue not previously tendered, viz.: That at the time the contract was made, and prior thereto, plaintiff operated its plant in such manner -that a constant flow of water was maintained in and through the Sturgis ditch; that the parties fully contemplated and intended that at all times during the life of the agreement plaintiff would continue to maintain a constant flow of water through the Sturgis ditch; that notwithstanding such understanding plaintiff ceased to use the water from Brown’s springs, and otherwise changed the mode of operating its plant, and thereby prevented a continuous flow of water through the Sturgis ditch; that a continuous flow of water in the ditch was in and of itself sufficient to keep the ditch free and clear of ice and snow in the winter; that without such continuous flow of water in the ditch it was extremely burdensome and difficult for defendant to keep the ditch free of ice and snow so that there would be no flooding; and that, by virtue of these circumstances, the overflowing of the Sturgis ditch and the resulting injuries to Butala’s lands were directly and proximately caused by “the failure, carelessness and concurring negligence *455 of plaintiff.” These allegations were all denied by plaintiff in its reply to the amended answer;

The cause was tried to the court sitting with a jury. At the close of the evidence both sides moved for a directed verdict. Instead of granting either motion, the court propounded certain interrogatories to the jury. In response thereto the jury answered that plaintiff’s operation of its plant at the time of making the contract produced and maintained a continuous flow of water through the Sturgis ditch; that subsequent to the execution of the contract, plaintiff so changed its mode of operation as to cause a cessation of the continuous flow of the water through the ditch, and that this materially increased the burden upon defendant in keeping the ditch clear of ice and snow so that it would carry the water discharged from the plant. Thereafter the court entered judgment for the defendant, and plaintiff prosecuted this appeal.

Plaintiff contends that the contract is clear and unambiguous, and that under the terms thereof the duty devolved upon defendant to keep the Sturgis ditch clear so that the water would pass through it and there would be no damage by flooding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ryan Mercantile Co. v. Great Northern Railway Co.
186 F. Supp. 660 (D. Montana, 1960)
Alberts v. American Casualty Co.
200 P.2d 37 (California Court of Appeal, 1948)
Horst v. Staley
54 P.2d 876 (Montana Supreme Court, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
54 P.2d 112, 101 Mont. 450, 1936 Mont. LEXIS 8, Counsel Stack Legal Research, https://law.counselstack.com/opinion/union-electric-co-v-lovell-livestock-co-mont-1936.