Union Bank Act 250 Application

CourtVermont Superior Court
DecidedApril 1, 2013
Docket7-1-12 Vtec
StatusPublished

This text of Union Bank Act 250 Application (Union Bank Act 250 Application) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Union Bank Act 250 Application, (Vt. Ct. App. 2013).

Opinion

STATE OF VERMONT SUPERIOR COURT — ENVIRONMENTAL DIVISION

{ In re Union Bank { Docket No. 7-1-12 Vtec (Act 250 Application #5L0468-7) { (Appeal from District 5 Envtl. Comm.) {

Decision on Cross Motions for Party Status and Summary Judgment

Union Bank (“Applicant”) applied for an Act 250 permit from the District 5 Environmental Commission (“the Commission”) for the construction and operation of a bank facility in the Village of Jeffersonville, Vermont. On October 26, 2011, the Commission issued its Findings of Fact, Conclusions of Law and Order, which concluded that the Project as proposed complies with all applicable Act 250 criteria,1 except Criterion 10, which relates to the project’s conformance with the applicable municipal and regional plans. Applicant appealed the Commission’s determination to this Court. Subsequently, Jean Jenkauskas (“Cross-Appellant”), an owner of property adjoining the Project site who participated in the Commission proceeding below, filed a cross-appeal. Cross-Appellant seeks to challenge the Commission’s determination that the Project complies with Criteria 1(D) and 4, and also seeks to raise issues on appeal under Criteria 5, 7, and 8. Currently before this Court is Cross-Appellant’s motion for party status under Criteria 1(D), 5, 7, and 8, in addition to Applicant’s March 20, 2012 motion for summary judgment on Cross-Appellant’s Questions 1, 2, 3, and a portion of 4. In this proceeding, Applicant is represented by Claudine C. Safar, Esq. Cross-Appellant is represented by Brice C. Simon, Esq. The other parties that have appeared in this matter have not filed pleadings concerning the pending motions.

Factual Background In order to put the pending motions into context, the Court recites the following facts, which it understands to be undisputed unless otherwise noted:

1 The District Commission issued Findings of Fact and Conclusions of Law specifically referencing Act 250 Criteria 1(D), 4 and 10, but concluded that Findings and Conclusions were not required under all other criteria, since the District Commission had previously determined pursuant to Act 250 Rule 51(F) that the remaining criteria were not at issue in the pending application. See Re: Union Bank, No. 5L0468- 7, Findings of Fact, Conclusions of Law and Order, at 2 (Dist. 5 Envtl. Comm’n, Oct. 26, 2011).

1 1. On March 25, 2011, Applicant filed an application for an Act 250 permit to construct and operate a bank facility (“the Project”) on a site at the intersection of Vermont Routes 15 and 108 in the Village of Jeffersonville, a municipal entity within the Town of Cambridge, Vermont. 2. In response, Cross-Appellant petitioned the Commission for preliminary party status in the Commission’s proceedings on Applicant’s permit application. Cross-Appellant sought to participate as an interested person pursuant to 10 V.S.A. § 6085(c)(1)(E) under Act 250 Criteria 4, 5, 7, 8, and 10. 3. Both the Project site and Cross-Appellant’s land have flooded in the past. The bulk of Cross-Appellant’s concerns about the proposed Project relate to its potential effect on flooding on her land. 4. Applicant’s application was deemed administratively complete on April 18, 2011. The District Commission then gave notice on April 26, 2011 that since the application and supporting materials sufficiently addressed all applicable Act 250 criteria, it planned to process the application on a “minor” basis and to issue an Act 250 permit without a hearing, pursuant to Act 250 Rule 51. The Commission further noted, pursuant to Act 250 Rule 51(C), that it may still conduct a hearing on the pending application if a party requested a hearing and convinced the Commission that there were “substantive issues” on the question of whether the Project would present a significant adverse impact under any of the applicable criteria. 5. The Commission received timely requests for hearing from Cross-Appellant and the Village of Jeffersonville Board of Trustees. 6. In a Memorandum of Decision dated June 16, 2011, the Commission granted the requests for a hearing and concluded that the Act 250 criteria at issue at the hearing would be Criteria 1(D), 4, and 10. The Commission also noted that it would only consider those criteria and would only render findings of fact and conclusions of law in relation to those criteria, all in accordance with Act 250 Rule 51(F). 7. The District Commission also granted Cross-Appellant preliminary party status under Criteria 4 and 10 and denied her party status requests under Criteria 5, 7, and 8. The Commission reaffirmed Cross-Appellant’s final party status under Criteria 4 and 10 in its October 26, 2011 Findings of Fact, Conclusions of Law and Order. 8. Cross-Appellant did not petition the District Commission for party status under Criterion 1(D), but the Commission permitted Cross-Appellant to offer evidence related to Criterion 1(D) at its hearing.

2 9. In its final decision, the Commission found that the Project complied with Criteria 1(D) and 4 but that it did not comply with Criterion 10, specifically as to the Village of Jeffersonville Village Plan. Thus, the Commission denied Applicant an Act 250 permit. 10. Applicant appealed the Commission’s decision to this Court on January 12, 2012. 11. Cross-Appellant filed a cross-appeal on January 26, 2012. On February 15, 2012, Cross- Appellant filed a Statement of Questions. Question 1 asks whether Cross-Appellant is entitled to party status before this Court under Act 250 Criteria 1(D), 5, 7, and 8. 12. Cross-Appellant did not file a separate motion for party status pursuant to V.R.E.C.P. 5(d)(2) until November 19, 2012.

Discussion Through her motion for party status, Cross-Appellant asserts that she is entitled to party status under Act 250 Criteria 1(D) (floodways), 5 (traffic), 7 (municipal services), and 8 (historical sites). Applicant challenges Cross-Appellant’s claim to party status under all four criteria. Applicant also asserts that the Court should dismiss Cross-Appellant’s entire motion as untimely. In the alternative, Applicant argues that Cross-Appellant has no standing to seek party status under Criterion 1(D), and that in any case she has failed to make a sufficient showing to claim party status under Criteria 1(D), 5, 7, and 8. For the reasons detailed below, we conclude as a matter of law that Cross-Appellant has standing to seek party status under Criterion 1(D) pursuant to 10 V.S.A. § 8504(d)(2)(C) and under Criteria 5, 7, and 8 pursuant to 10 V.S.A. § 8504(d)(2)(B). We also find that Cross- Appellant is entitled to party status before this Court under Criterion 1(D) but not under Criteria 5, 7, and 8. Finally, we deny as moot Applicant’s motion for summary judgment.

I. Timeliness of Motion for Party Status Any person aggrieved by an act or decision of a district commission in a proceeding to review an Act 250 permit application may appeal that act or decision to this Court. 10 V.S.A. § 8504(a). Generally, however, that person must have been granted party status by the district commission, participated in the proceedings before the district commission, and retained party status at the end of the district commission proceedings in order to have standing to appeal. 10 V.S.A. § 8504(d)(1). The person may only appeal those issues under the Act 250 criteria for which that person was granted party status. Id.

3 Notwithstanding these restrictions, a person may also appeal a district commission decision if this Court determines that (1) there was a procedural defect preventing the person from obtaining party status; (2) the district commission’s decision being appealed is the grant or denial of party status; or (3) manifest injustice would result if the appeal is not allowed. 10 V.S.A. § 8504(d)(2)(A)–(C).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
In Re Verizon Wireless Barton Permit
2010 VT 62 (Supreme Court of Vermont, 2010)
Parker v. Town of Milton
726 A.2d 477 (Supreme Court of Vermont, 1998)
Dougherty v. Surgen
518 A.2d 364 (Supreme Court of Vermont, 1986)
Desjarlais v. Gilman
463 A.2d 234 (Supreme Court of Vermont, 1983)
Shahi v. Ascend Financial Services, Inc.
2006 VT 29 (Supreme Court of Vermont, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Union Bank Act 250 Application, Counsel Stack Legal Research, https://law.counselstack.com/opinion/union-bank-act-250-application-vtsuperct-2013.