Underpinning & Foundation Constructors, Inc. v. United States Fidelity & Guaranty Co.

325 F. Supp. 2d 194, 2004 U.S. Dist. LEXIS 14160, 2004 WL 1621181
CourtDistrict Court, E.D. New York
DecidedJuly 16, 2004
Docket1:03-cv-05696
StatusPublished
Cited by1 cases

This text of 325 F. Supp. 2d 194 (Underpinning & Foundation Constructors, Inc. v. United States Fidelity & Guaranty Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Underpinning & Foundation Constructors, Inc. v. United States Fidelity & Guaranty Co., 325 F. Supp. 2d 194, 2004 U.S. Dist. LEXIS 14160, 2004 WL 1621181 (E.D.N.Y. 2004).

Opinion

MEMORANDUM AND ORDER

GLASSER, District Judge.

I. SUMMARY

Defendant United States 'Fidelity & Guaranty Company (“USF & G” or “Defendant”), a Maryland corporation, brings this motion seeking summary judgment in an action brought by plaintiff Underpinning & Foundation Constructors, Inc. (“Underpinning” or “Plaintiff’), a New York corporation, to recover for work in performed on a public works project for the New York Power Authority, payment for which was assured by defendant’s bond.

Defendant argues that plaintiff is not a proper claimant under the bond because the underlying contract was in the name of “Underpinning & Foundation-Skanska, Inc.” (“U & F-Skanska”) instead of “Underpinning & Foundation Constructors, Inc.”

For the reasons that follow, defendant’s motion is denied.

II. BACKGROUND

On or about December 19, 2001, the New York Power Authority entered into a contract with North Star Contracting Corporation (“North Star”) for construction of a project designated as the Poletti 500 MW Combined Cycle Power Plant (“the Project”).

On or about February 11, 2002, USF & G, as surety, and North Star, as principal, executed and delivered to the Power Au *195 thority, as obligee, a Payment Bond, Bond No. SN9763, in the penal amount of $5,944,000 (“the Bond”).

In June 2002, a subcontract was created for the performance of piledriving, steel sheet piling and caisson work on the Project for the sum of $1,446,006.03 (“the Subcontract”). North Star is named as the. Contractor. The named subcontractor is “Underpinning & Foundation-Skanska, Inc., a New York corporation having a place of business at 46-36 54th Road, Mas-peth, New York.” (Def. Notice of Mot. Ex. B.) It is undisputed that the Subcontract was prepared by North Star. It is also important to note that the heading in Rider “A” to the Subcontract references “Underpinning & Foundation” as the Subcontractor, not “Underpinning & Foundation-Skanska, Inc.,” and the text of Rider “A” refers simply to “Underpinning.” (Def. Notice of Mot. Ex. B.)

Plaintiff alleges that it performed the work required by the Subcontract, but that North Star has refused to pay beyond a single payment of $388,467.16.

On or about April 9, 2003, a Notice Under Mechanic’s Lien Law for Account of Public Improvement (“the Lien”) was filed in the name of U & F-Skanska.

In November 2003, plaintiff filed the present suit against defendant, asserting that pursuant to the terms of the Bond, defendant is obligated to pay plaintiff $1,057,538.87, the amount owed to it by North Star under the Subcontract, plus an additional $338,196.33 for work it performed beyond the scope of the Subcontract at North Star’s request.

III. DISCUSSION

The principles informing a court’s judgment in a motion for summary judgment have been stated and restated so frequently as not to warrant restating again. See Matsushita Electric Industrial Co. v. Zenith Radio Corp., 475 U.S. 574, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986); Celotex Corp. v. Catrett, 477 U.S. 317, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986).

Defendant’s assertion that the plaintiff was not the party to the Subcontract with North Star, given the plaintiffs exhibits and affidavits opposing this motion, is startling. It can only be ascribed to a bold attempt to avoid an obligation which is plainly theirs. North Star’s use of “Skanska” in the Subcontract and plaintiffs acquiescence to it appear to be attributable to mere inadvertence on the part of both parties.

I begin with the plaintiffs letterhead used in all correspondence with North Star. The upper left corner of the letterhead includes the words “Underpinning & Foundation,” in large type with the word “Skanska” directly underneath, separated by a thin black line. The upper right corner includes the words “Underpinning & Foundation Constructors, Inc.,” with the address 46-36 54th Road, Maspeth, New York, 11378-1020 (the same address indicated on the Subcontract), phone and fax numbers, and a web site address which is represented as www.underpinning.com. 1

Affidavits submitted by the plaintiff which convincingly demonstrate the frivolous basis upon which the defendant’s motion rests include:

1. The affidavit of Peter MacKenna, the plaintiffs President;

2. The affidavit of Fabio Liscindini, the plaintiffs Senior Estimator;

*196 3. The affidavit of Edward P. Forte, the plaintiffs Vice President;

4. The affidavit of George R. Jung, the plaintiffs Manager of Contracts and Administration.

Each affirmatively and unequivocally swears that the subcontract giving rise to the action was between Underpinning & Foundation Constructors, Inc. and North Star, and that North Star knew it and did not believe otherwise, as the exhibits annexed to Mr. MacKenna’s affidavit conclusively show.

The only affidavit in support of the defendant’s motion is one by Peter Boltrek, the Vice-President of North Star, dated March 3, 2004, which the Court finds disturbing. In it, Mr. Boltrek swears that “North Star did not enter into an agreement with the plaintiff Underpinning & Foundation Constructors, Inc. (“Underpinning”).” (Boltrek Aff. ¶ 6.) In paragraph 14, he swears that “plaintiff, Underpinning, did not have a contract with ... North Star and did not furnish the labor, materials or equipment to the Project as alleged in the complaint.” (Boltrek Aff. ¶ 14.)

In stark contrast to that affidavit is a letter, dated October 31, 2003, on North Star stationary, addressed as follows:

Underpinning & Foundation Constructors, Inc.
46-36 54th Road
Maspeth, New York 11378-1020
Attn: Peter E. MacKenna
President & CEO
Re: NYPA’s Poletti Plant

(MacKenna Aff. Ex. C.)

That letter, among other things, contains this sentence: “Please note, that you have an obligation under oúr subcontract agreement to close out the project....” (emphasis added). The letter is signed, “Peter Boltrek, Vice President.” Wigmore was clearly correct in observing that “the moral efficacy of the oath has long since ceased to be what it once was.” 6 James H. Chadboume, Wigmore on Evidence

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Icebox-Scoops, Inc. v. Finanz St. Honoré, B.V.
676 F. Supp. 2d 100 (E.D. New York, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
325 F. Supp. 2d 194, 2004 U.S. Dist. LEXIS 14160, 2004 WL 1621181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/underpinning-foundation-constructors-inc-v-united-states-fidelity-nyed-2004.