Umoja Erectors LLC v. DA Nolt Inc

CourtCourt of Appeals for the Third Circuit
DecidedOctober 23, 2025
Docket24-2426
StatusUnpublished

This text of Umoja Erectors LLC v. DA Nolt Inc (Umoja Erectors LLC v. DA Nolt Inc) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Umoja Erectors LLC v. DA Nolt Inc, (3d Cir. 2025).

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT ____________

No. 24-2426 ____________

UMOJA ERECTORS, LLC, Appellant

v.

D.A. NOLT, INC.; NORTH AMERICAN SPECIALTY INSURANCE COMPANY ___________

On Appeal from the United States District Court for the Eastern District of Pennsylvania (D.C. No. 2:20-cv-05046) District Judges: Honorable Gene E.K. Pratter and Honorable Mitchell S. Goldberg ___________

Submitted Pursuant to Third Circuit L.A.R. 34.1(a) May 19, 2025 ___________

Before: PHIPPS, CHUNG, and ROTH, Circuit Judges

(Filed: October 23, 2025) ___________

OPINION * ___________ PHIPPS, Circuit Judge.

After a subcontractor for a municipal construction project performed substandard work, the general contractor did not pay the subcontractor for that work and recouped its

costs associated with corrective work by withholding payment for other work. The

subcontractor then sued the general contractor in federal court, and after a bench trial, the

* This disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not constitute binding precedent. court entered a judgment in favor of the general contractor. The subcontractor unsuccessfully moved under Rule 59(e) to alter the judgment, and it now appeals the

judgment and the denial of that motion. Reviewing the District Court’s legal conclusions

de novo and its factual findings for clear error, 1 we will, for the reasons below, affirm the

rulings of the District Court.

BACKGROUND

In March 2012, the City of Philadelphia announced that its police headquarters would relocate to the Public Safety Services Campus in West Philadelphia. See Umoja

Erectors, LLC v. D.A. Nolt, Inc., 2024 WL 3635670, at *2 (E.D. Pa. Feb. 15, 2024). For

that campus to accommodate the police headquarters, there would have to be extensive

renovations, including asbestos abatement; masonry and plumbing work; replacement of

doors, windows, and roofing; and the erection of new structural steel. To oversee those

renovations for completion by December 16, 2016, the City, in August 2015, awarded a

general construction prime contract in the amount of approximately $13.5 million to D.A.

Nolt, Inc., a New Jersey corporation with its principal place of business in that state. See

id.

The terms of that contract included the Standard Contract Requirements, or ‘SCRs’

as they may be abbreviated, for the City of Philadelphia. One of those SCRs was a

defective work clause, which governed work rejected by a Project Manager: The Contractor shall remove, at its own expense, any work or material rejected by the Project Manager as unsuitable, unfit, or otherwise defective and not in accordance with the Contract Documents, and shall repair, replace or reconstruct the same without additional compensation.

1 See United States v. U.S. Sugar Corp., 73 F.4th 197, 203 (3d Cir. 2023); Vuyanich v. Smithton Borough, 5 F.4th 379, 384 n.4 (3d Cir. 2021).

2 City of Philadelphia Standard Contract Requirements for Public Works Contracts § E.66 (Jan. 22, 2015) (App. 1043). The SCRs defined ‘Project Manager’ as the person

designated as such by the City or “any other individual who may be designated in writing

by the Project Manager as his or her representative.” Id. § A.1.jj (App. 1016). For the steel work, Nolt subcontracted in June 2016 with a limited liability company,

Umoja Erectors, which had two members, both of whom were natural persons and citizens

of Pennsylvania. See Umoja Erectors, 2024 WL 3635670, at *2. In terms of compensation, the subcontract was primarily a time-and-materials agreement: Umoja

would be reimbursed for labor at contractually defined hourly rates and for most materials

at cost. In addition, the parties agreed to a $30,000 ‘coordination fee’ to compensate Umoja for its efforts managing and coordinating the steel work. See id. at *3.

Beyond those terms governing the scope of work and compensation, the subcontract

also included a role for the SCRs. See id. Specifically, it contained a clause binding the

subcontractor to the contractor “by the same terms and conditions by which Contractor is

bound to the [City] under the Contract.” D.A. Nolt-Umoja Subcontract Art. 2.1

(App. 737); see also id. Ex. B (App. 760) (enumerating “City of Philadelphia Standard

Contract Requirements” as one of the “Contract Documents”).

In the second half of 2016 and early 2017, numerous problems were identified with

the steel work, including issues with the steel having been improperly cut or welded. See

Umoja Erectors, 2024 WL 3635670, at *3–5. Some of those errors could be rectified on

the spot; others required that the steel be removed and shipped back to the fabricator for

reworking. See id. at *4–5. All of those mistakes took extra time, and by the project’s

scheduled completion date of December 16, 2016, the City estimated that the steel work

was about 90% complete. See id. at *5. That delay prompted the City to withhold payment

3 to Nolt and to threaten to seek liquidated damages in the amount of $10,000 per day for the costs associated with the delay. Also, because the steel work for a roof for the project was

not timely completed, Nolt had to install a temporary roof in January 2017. See id.

In a letter dated February 10, 2017, Nolt’s Vice President, Rich O’Brien, who later testified at trial that he was the Project Manager for purposes of the subcontract, informed

Umoja of the potential consequences of the City’s position. Cf. id. at *2. Nolt would not

pay Umoja for the redone work caused by the fabrication or erection errors. Cf. id. at *1. Nolt would charge Umoja for any additional costs that it incurred due to the redone work.

And Nolt would seek compensation from Umoja for any liquidated damages that the City

charged it. Ultimately, Umoja completed the steel work in March 2017. See id. at *1. Umoja

submitted invoices in the amount of $299,054.23 for its work performed. Nolt paid Umoja

$26,375.52 on those invoices, and then in a letter from O’Brien, refused to pay the

remainder on the grounds that the charges were for corrective rework and thus not

compensable under the subcontract. See id. And to recoup its costs associated with the

delay, Nolt paid Umoja only $9,262 of the $30,000 coordination fee. See id. at *9.

In 2020, Umoja invoked the diversity jurisdiction of the District Court, see

28 U.S.C. § 1332(a)(1), to sue Nolt for breach of contract, unjust enrichment, and violation

of Pennsylvania’s Prompt Pay Act, 62 Pa. Cons. Stat. §§ 3931–39. During the pendency

of this suit between Umoja and Nolt, the City settled with Nolt and paid Nolt the amounts

it had been withholding. See Umoja Erectors, 2024 WL 3635670, at *1. The dispute

between Umoja and Nolt did not settle, but instead proceeded to a four-day bench trial in

January and February 2023.

4 After that bench trial, the District Court entered judgment for Nolt. It determined that Nolt was “not obligated to pay any charges or invoices for corrective, repair, or redone

work.” Id. at *7. It also found that the unpaid invoices lacked “reasonable certainty”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wilcox v. Regester
207 A.2d 817 (Supreme Court of Pennsylvania, 1965)
Northwest'n Nat. Bk. v. Com'nw'lth.
27 A.2d 20 (Supreme Court of Pennsylvania, 1942)
Cooper v. Harris
581 U.S. 285 (Supreme Court, 2017)
Timothy Vuyanich v. Borough of Smithton
5 F.4th 379 (Third Circuit, 2021)
United States v. United States Sugar Corporation
73 F.4th 197 (Third Circuit, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
Umoja Erectors LLC v. DA Nolt Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/umoja-erectors-llc-v-da-nolt-inc-ca3-2025.