UMB Bank, N.A. v. Bristol-Myers Squibb Company

CourtDistrict Court, S.D. New York
DecidedJune 24, 2022
Docket1:21-cv-04897
StatusUnknown

This text of UMB Bank, N.A. v. Bristol-Myers Squibb Company (UMB Bank, N.A. v. Bristol-Myers Squibb Company) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
UMB Bank, N.A. v. Bristol-Myers Squibb Company, (S.D.N.Y. 2022).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK ---------------------------------------------------------------------- X : UMB BANK N.A., : : Plaintiff, : : 21-CV-4897 (JMF) -v- : : MEMORANDUM OPINION BRISTOL-MYERS SQUIBB COMPANY, : AND ORDER : Defendant. : : ---------------------------------------------------------------------- X JESSE M. FURMAN, United States District Judge: This is a contract dispute arising out of the November 2019 acquisition by Bristol-Myers Squibb Company (“BMS”) of Celgene Corporation (“Celgene”). ECF No. 1 (“Compl.”), ¶ 2. In connection with the acquisition, BMS issued to Celgene stockholders contingent value rights, or CVRs, which would have value only if marketing applications for three of Celgene’s most valuable products were approved by the Food and Drug Administration (“FDA”) by specified milestone dates. Id. ¶ 29. If FDA approval of a product came even a day late, the CVR Agreement would automatically terminate and the CVRs rendered worthless. Compl. ¶ 32; see ECF No. 1-1 (“CVR Agreement”).1 The Complaint alleges that BMS, in order to avoid paying holders of the CVRs the $6.4 billion they otherwise would have been due, slowed down the approval process for one therapy, Liso-cel, causing it to be approved thirty-six days after the relevant milestone. Compl. ¶¶ 7, 9, 17. Plaintiff UMB Bank N.A., which serves as Trustee under the CVR Agreement, sued on behalf of the CVR holders, alleging that BMS had breached

1 The Court may consider the CVR Agreement in connection with BMS’s motion to dismiss because it was attached to, and incorporated by reference in, the Complaint. DiFolco v. MSNBC Cable LLC, 622 F.3d 104, 111 (2d Cir. 2010). the CVR Agreement by failing to use “Diligent Efforts” to get Liso-cel approved on time and by not making its books and records available for inspection upon request on December 29, 2020, as required by the contract. Id. ¶¶ 34-35, 85-86. BMS now moves, pursuant to Rule 12(b)(6) of the Federal Rules of Civil Procedure, to dismiss the Complaint, arguing principally that Plaintiff

failed to comply with certain pre-suit notice procedures requiring notice of an alleged breach and a ninety-day period to cure the breach before filing suit. See ECF No. 18 (“Def.’s Mem.”). The Court disagrees and, for the reasons that follow, DENIES BMS’s motion to dismiss. The CVR Agreement directs Plaintiff, the Trustee, to “bring suit to protect the rights of the Holders” if “an Event of Default . . . occurs and is continuing.” CVR Agreement § 8.1. An Event of Default is defined, in turn, as a “material default in the performance, or breach in any material respect, of any covenant or warranty of the Company in respect to the Securities . . . , and continuance of such default or breach for a period of ninety (90) days” after notice is provided to the Company. CVR Agreement § 8.1(b). On March 4, 2021, about three months after the CVR Agreement automatically terminated, Plaintiff sent a notice of default to BMS,

Compl. ¶ 101, alleging that BMS had breached the contract by failing to: “use Diligent Efforts to achieve the Milestone[s],” CVR Agreement § 7.8; keep accurate and detailed records to allow Plaintiff to “determine if the Company has complied with its obligations,” id. § 7.5; and permit Plaintiff to “examine the pertinent books and records . . . as may be reasonably necessary,” id. § 4.2(f). Plaintiff waited ninety days, until June 3, 2021, and then filed this suit. See Compl. BMS argues principally that Plaintiff’s suit must be dismissed because the notice of default was sent after the CVR Agreement had terminated, meaning that the default could not have “continued” for ninety days. Def.’s Mem. 17. That argument falls short. For starters, the CVR Agreement explicitly provides that Article 8, which empowers Plaintiff to bring suit, “shall survive termination of this CVR Agreement” and that “the termination of this CVR Agreement shall not relieve any Party of any liability arising from any material breach of its obligations under this CVR Agreement occurring prior to the Termination Date.” CVR Agreement § 1.16; see, e.g., Mtivity, Inc. v. Off. Depot, Inc., 525 F. Supp. 3d 433, 439-40 (E.D.N.Y. 2021) (holding

that “termination pursuant to a termination clause is usually treated as alternative performance” and that “certain clauses of the Agreement [that] are intended to endure . . . would not be affected by termination pursuant to the mutual termination clause”). BMS argues that these provisions are irrelevant because its default could not “continue” for ninety days due to the termination of the contract, such that the alleged breach never matured into “an Event of Default” that would allow Plaintiff to file suit. See Def.’s Mem. 15. But, as this Court recently held in similar circumstances, “[a] party is in default when it fails to perform its contractual obligations. Ordinarily, termination of an agreement does not change that state of affairs; the terminated party remains liable for the breach.” New York Wheel Owner LLC v. Mammoet Holding B.V., 481 F. Supp. 3d 216, 237 (S.D.N.Y. 2020). Accordingly, the requirement that the

breach must continue for ninety days “is more reasonably read to prohibit a demand based on a breach that [the company] has cured.” Id. BMS cites no authority to support the proposition that a breach of a contract cannot, as a matter of law, “continue” after termination of the contract. Instead, the cases it cites for this proposition, see Def.’s Mem. 15, establish only that a contract that has long since terminated cannot be breached, see, e.g., Int’l Techs. Mktg., Inc. v. Verint Sys., Ltd., 157 F. Supp. 3d 352, 357, 363 (S.D.N.Y. 2016), aff’d, 850 F. App’x 38 (2d Cir. 2021). Here, by contrast, the alleged breach undeniably occurred during the pendency of the contract. Next, BMS argues that it would be unfair and counter to the parties’ expectations to allow a suit in these circumstances because, practically speaking, BMS was unable to use the ninety- day notice period to cure the breach by, for example, using diligent efforts to meet the milestone. See Def.’s Mem. 16. But the contract does not require that the breach be amenable to cure in the ninety-day notice period; indeed, the word “cure” appears nowhere in the provision. Instead, the agreement merely requires “continuance of such default or breach for a period of ninety (90)

days after” notice, CVR Agreement § 8.1(b), and here the alleged default remained unremedied ninety days after notice. In any event, as the Court held in New York Wheel, 481 F. Supp. 3d at 237, there are alternative ways to remedy a default, including, in this case, payment of damages or reinstatement of the CVR Agreement, see ECF No. 24 (“Pl.’s Opp’n”), at 18. Finally, as Plaintiff persuasively notes, a contrary reading of the parties’ agreement would produce the perverse result of immunizing any breaches by BMS within the final ninety days of the contract. See Pl.’s Opp’n 17-18. In short, Plaintiff has the better reading of the relevant contractual language. At a minimum, the relevant provisions of the CVR Agreement, taken together, are ambiguous, which is enough to deny BMS’s motion. See, e.g., Orchard Hill Master Fund Ltd. v. SBA Commc’ns Corp., 830 F.3d 152, 156-57 (2d Cir. 2016); see also Mahoney v. Sony Music

Ent., No. 12-CV-5045 (RJS), 2013 WL 491526, at *7 (S.D.N.Y. Feb.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

DiFolco v. MSNBC Cable L.L.C.
622 F.3d 104 (Second Circuit, 2010)
Kelly-Brown v. Winfrey
717 F.3d 295 (Second Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
UMB Bank, N.A. v. Bristol-Myers Squibb Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/umb-bank-na-v-bristol-myers-squibb-company-nysd-2022.