Umatilla County v. Dept. of Energy

CourtOregon Supreme Court
DecidedApril 18, 2024
DocketS070517
StatusPublished

This text of Umatilla County v. Dept. of Energy (Umatilla County v. Dept. of Energy) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Umatilla County v. Dept. of Energy, (Or. 2024).

Opinion

194 April 18, 2024 No. 10

IN THE SUPREME COURT OF THE STATE OF OREGON

In the Matter of the Application for Site Certificate for the Nolin Hills Wind Power Project. UMATILLA COUNTY, Petitioner, v. OREGON DEPARTMENT OF ENERGY, Energy Facility Siting Council, and Nolin Hills Wind, LLC, Respondents. (SC S070517)

En Banc On judicial review of a final order of the Energy Facility Siting Council.* Argued and submitted January 11, 2024. Wendie L. Kellington, Kellington Law Group, PC, Lake Oswego, argued the cause and filed the brief for petitioner on review Umatilla County. Kate E. Morrow, Assistant Attorney General, Salem, argued the cause and filed the brief for respondents on review Oregon Department of Energy and Energy Facility Siting Council. Also on the brief were Ellen F. Rosenblum, Attorney General; Benjamin Gutman, Solicitor General; and Jona J. Maukonen, Assistant Attorney General. Rachel C. Lee, Stoel Rives, LLP, Portland, argued the cause and filed the brief for respondent on review Nolin Hills Wind, LLC. Daniel Kearns, Reeve Kearns PC, Portland, filed the brief for amici curiae Morrow County and The Eastern Oregon Counties Association. ______________ * Judicial review of a final order of the Energy Facility Siting Council issued August 31, 2023. Cite as 372 Or 194 (2024) 195

Daniel Kearns, Reeve Kearns PC, Portland, filed the brief for amicus curiae Blue Mountain Alliance. GARRETT, J. The final order of the Energy Facility Siting Council is affirmed. 196 Umatilla County v. Dept. of Energy

GARRETT, J. Umatilla County seeks judicial review of a final order of the Energy Facility Siting Council (the council) that granted a site certificate allowing Nolin Hills Wind, LLC, to construct a wind energy facility in the county. This case comes to us on direct review of the council’s final order. See ORS 469.403(3) (providing for direct review by this court in such cases). The proposed facility includes, among other things, wind turbines, energy-transmission lines, and other related or supporting facilities. Umatilla County challenges the council’s final order on the ground that the council should have required Nolin Hills to comply with a siting criterion—a two-mile setback between any turbine and a rural residence—that the county had recommended to the council under ORS 469.504(5). For the reasons set out below, we agree with the council that it has authority under ORS 469.504(1)(b)(B) to approve Nolin Hills’s proposed energy facility notwithstanding the facility’s failure to comply with that siting criterion. We therefore affirm the council’s final order. I. BACKGROUND A. Brief Overview of the Dispute As we will explain, state law sets out a complex framework that governs the council’s approval of a site cer- tificate. That framework makes the council responsible for the final determination whether a proposed facility complies with legal requirements and may be approved. However, it also provides a role for local governments, a role that includes recommending “applicable substantive criteria” (which we will explain later in this opinion) that bear on the coun- cil’s determination. Central to this case is precisely what role those applicable substantive criteria play—specifically whether, in this case, as the county contends, those applica- ble substantive criteria should have been given dispositive effect, or whether, as the state respondents1 contend, the council was authorized to approve Nolin Hills’s application despite its failure to comply with all of those criteria. Two 1 The council and the Department of Energy jointly filed an answering brief. They refer to themselves as the state respondents, and we do the same in this opinion. Cite as 372 Or 194 (2024) 197

subsidiary questions are presented by the parties’ argu- ments. One is whether—assuming that the proposed facil- ity is required to comply with the “applicable substantive criteria” recommended by the county—the two-mile setback requirement qualifies as one of those criteria. The state respondents argue that it does not. The other is whether the proposed facility passes through more than three land use zones. If it does, then it is undisputed that the council was authorized to approve the site certificate without con- sidering the applicable substantive criteria at all. As we will explain, we conclude that the council was authorized to approve Nolin Hills’s site certificate even if the proposed facility does not pass through more than three land use zones and even if it does not comply with all of the county’s recommended substantive criteria. That conclusion obviates the need for us to resolve those two subsidiary issues. B. The Council Generally The council is an independent body composed of seven volunteers appointed by the Governor and confirmed by the Senate. ORS 469.450. The council works hand in hand with the Department of Energy (DOE), which is charged with implementing the state’s energy goals and policies. ORS 469.030. Although it is the council that ulti- mately issues the site certificate, each entity plays a role in the energy facility siting process. As we recently explained in Friends of Columbia Gorge v. Energy Fac. Siting Coun., 368 Or 123, 125, 486 P3d 787 (2021), “[t]he council oversees the development of large energy facilities in Oregon, including electric power gener- ating plants, high-voltage transmission lines, gas pipelines, and radioactive waste disposal sites, among other projects.” See ORS 469.470 (listing powers and duties of the council); ORS 469.501 (requiring the council to adopt standards for siting, construction, operation, and retirement of energy facilities2); ORS 469.300(11)(a) (defining “energy facility”). The council carries out that task by issuing site certificates to developers. See ORS 469.320(1) (“[N]o facility shall be constructed or expanded unless a site certificate has been 2 Those standards are adopted as DOE regulations. OAR chapter 345, divi- sions 22-26. 198 Umatilla County v. Dept. of Energy

issued for the site.”); ORS 469.503 (setting out requirements for the council’s issuance of site certificate). To issue a site certificate, the council must find, among other things, that the proposed facility “complies with the statewide planning goals adopted by the Land Conservation and Development Commission.” ORS 469.503(4). A site certificate authorizes the holder to construct, operate, and retire a facility on an approved site, subject to the conditions that the council includes in the certificate. ORS 469.401(1); see ORS 469.300

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State v. Gaines
206 P.3d 1042 (Oregon Supreme Court, 2009)
Save Our Rural Oregon v. Energy Facility Siting Council
121 P.3d 1141 (Oregon Supreme Court, 2005)
Friends of Parrett Mountain v. Northwest Natural Gas Co.
79 P.3d 869 (Oregon Supreme Court, 2003)
Preble v. Department of Revenue
14 P.3d 613 (Oregon Supreme Court, 2000)
Stanley v. Mueller
315 P.2d 125 (Oregon Supreme Court, 1957)
Friends of Columbia Gorge v. Energy Fac. Siting Coun.
486 P.3d 787 (Oregon Supreme Court, 2021)

Cite This Page — Counsel Stack

Bluebook (online)
Umatilla County v. Dept. of Energy, Counsel Stack Legal Research, https://law.counselstack.com/opinion/umatilla-county-v-dept-of-energy-or-2024.