U S West Communications, Inc. v. Worldcom Technologies, Inc.

31 F. Supp. 2d 819, 1998 U.S. Dist. LEXIS 20086, 1998 WL 897022
CourtDistrict Court, D. Oregon
DecidedDecember 10, 1998
DocketCiv. 97-857-JE
StatusPublished
Cited by6 cases

This text of 31 F. Supp. 2d 819 (U S West Communications, Inc. v. Worldcom Technologies, Inc.) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U S West Communications, Inc. v. Worldcom Technologies, Inc., 31 F. Supp. 2d 819, 1998 U.S. Dist. LEXIS 20086, 1998 WL 897022 (D. Or. 1998).

Opinion

OPINION AND ORDER

JELDERKS, United States Magistrate Judge.

Plaintiff U S West Communications, Inc. (“US WEST”) brings this action against defendants WorldCom Technologies, Inc. (“WorldCom”) (formerly known as MFS In-telenet, Inc.), the Oregon Public Utility Commission (“PUC”), and PUC Commissioners Roger Hamilton, Ron Eachus, and Joan Smith (“the Commissioners”). The Federal Communications Commission (“FCC”) has participated in this proceeding as amicus curiae.

The dispute concerns an interconnection agreement between U.S. West and World-Com (“the Agreement”). The background facts and procedural history are set forth in the prior opinion dated January 30, 1998, which denied defendants’ motions to dismiss. The parties have each moved for summary judgment.

SCOPE AND STANDARD OF REVIEW

The Telecommunications Act of 1996 (“the Act”), Pub.L. No. 104-104, 110 Stat. 56, 47 U.S.C. § 153 et seq., provides for federal district court review of interconnection agreements concluded pursuant to 47 U.S.C. § 252. “[A]ny party aggrieved” by a decision of a state public utilities commission concerning such an agreement “may bring an action in an appropriate Federal district court to determine whether the Agreement ... meets the requirements of the Act.” 47 U.S.C. § 252(e)(6). The Act does not specify either the standard or scope of review.

After some initial hesitation, the parties now generally agree that the scope of this court’s review is limited to the administrative record. With regard to the standard of review, it is neither desirable nor practical for this court to sit as a surrogate public utilities commission to second-guess the decisions made by the state agency to which Congress has committed primary responsibility for implementing the Act in Oregon. Rather, this court’s principal task is to determine whether the PUC properly interpreted and applied the Act, which is a question of federal law that is reviewed de novo. The court declines WorldCom’s invitation to defer to the PUC’s interpretation of federal law. Without deciding whether such deference is ever appropriate in the case of a state administrative agency, it clearly is not appropriate in this instance because it could result in 50 different interpretations of the Act as each state agency applies its own interpretation of the law.

In all other respects, review will be under the arbitrary and capricious standard.

DISCUSSION

1. Count I (pricing)

A. Unbundled Loop

The arbitrator established an interim price of $17.20 for an unbundled loop. After this action was commenced, the PUC established a new price of $16.14 in a proceeding known as “UM 844.” Although the parties refer to this as the “final” price, it is the court’s understanding that the $16.14 price may be subject to revision in the future if conditions warrant. Therefore, the coui't will use the term “UM 844 price” rather than “final price” when referring to the $16.14 rate.

(i) Challenge to Interim Loop Price

WorldCom contends that adoption of the UM 844 price has mooted U.S. West’s challenge to the interim price, yet simultaneously contends that the challenge to the UM 844 price is not ripe because U.S. West still has remedies in state court. WorldCom cannot have it both ways. Either the UM 844 price has now replaced the interim price (and thus mooted that issue) or else the interim price is still in effect and the dispute is not moot. This court concludes that the dispute over the interim price is moot. In this action, U.S. West is not seeking compensation for the services (if any) that were purchased at the interim price, so the sole remaining question is the price for future services. *823 That will be governed by the UM 844 price (or its successors).

Even if the issue were not moot, this court would affirm the arbitrator’s decision establishing the interim price. The PUC began studying unbundled loop prices several years before the Act was enacted. US West actively participated in those earlier proceedings, known as “UM 351.” When Congress enacted the Act in 1996, it established very short timelines. The arbitrator understandably chose to rely heavily upon the extensive record and analysis that already existed, instead of starting the process anew.

Reliance on those earlier proceedings did not deny U.S. West due process of law. Contrary to the suggestion in U.S. West’s brief, the PUC did not apply principles of collateral estoppel to preclude U.S. West from contesting the loop prices. Rather, the earlier proceedings were treated as evidence that could be considered in the subsequent proceeding, and which the arbitrator and the PUC ultimately found were the most reliable evidence then available. US West was free to introduce contrary evidence and to urge a different result.

The arbitrator also acted properly in declining to consider the voluminous cost studies submitted by U.S. West just two weeks before the hearing. The arbitrator reasonably concluded that he lacked sufficient time to properly analyze those studies before the applicable deadlines, and also expressed concern about the accuracy of those studies.

(ii) Challenge to UM 844 Loop Price

The court rejects most of U.S. West’s arguments concerning the UM 844 price for unbundled loops. The PUC did not err by relying upon the record established in the UM 351, UM 773, and UM 844 proceedings. Nor does the Act require the PUC to ignore its own extensive expertise and experience in overseeing telephone pricing and service in Oregon, and in particular its knowledge of pricing, costs, and related issues as they concern U.S. West.

The parties also dispute the interpretation and application of a stipulation between U.S. West and the PUC. In ¶ 17 of the stipulation, the PUC and U.S. West agreed that in addition to the methodology prescribed in ¶ 16 of the stipulation U.S. West would also submit a study based on the methodology outlined in ¶ 17. The PUC could then compare the results obtained from these two methodologies and decide whether it wished to use the latter method in the future. However, there was no binding commitment by the PUC to use the ¶ 17 methodology in the current round of loop pricing.

A more difficult issue is the number of pairs per drop to be used in calculating-loop prices. US West contends that most existing homes employ a two-pair design, though new construction often utilizes a three or even four-pair design. The number of pairs per drop materially impacts the loop price in two respects. First, the total loop investment (ie., the dividend of the equation) is higher if the scorched node analysis assumes installation of three pairs per drop instead of two. Second, the divisor in the equation is the number of working loops, which is determined by multiplying the total number of loops times the average fill factor (which measures the percentage of lines or other facilities actually being used, as opposed to the theoretical capacity).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
31 F. Supp. 2d 819, 1998 U.S. Dist. LEXIS 20086, 1998 WL 897022, Counsel Stack Legal Research, https://law.counselstack.com/opinion/u-s-west-communications-inc-v-worldcom-technologies-inc-ord-1998.