TXU Portfolio Management Co. v. FPL Energy, LLC

328 S.W.3d 580, 2010 WL 2904628
CourtCourt of Appeals of Texas
DecidedJanuary 14, 2011
Docket05-08-01584-CV
StatusPublished
Cited by9 cases

This text of 328 S.W.3d 580 (TXU Portfolio Management Co. v. FPL Energy, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
TXU Portfolio Management Co. v. FPL Energy, LLC, 328 S.W.3d 580, 2010 WL 2904628 (Tex. Ct. App. 2011).

Opinion

OPINION

Opinion By

Justice MORRIS.

This appeal arises out of a contractual dispute between an electricity wholesaler and three wind-powered electrical generation facilities. TXU Portfolio Management Company, L.P. n/k/a Luminant Energy Company, L.L.C. filed a lawsuit against FPL Energy, LLC, FPL Energy Pecos Wind I, L.P., FPL Energy Pecos Wind II, L.P., and Indian Mesa Wind Farm, L.P. (collectively the Wind Farms). It sought to recover liquidated damages after the Wind Farms failed to deliver the minimum annual quantities of wind-generated electric energy and renewable energy credits due under three purchase and sale agreements. The Wind Farms counterclaimed. They claimed TXUPM materially breached the contracts by failing.to ensure enough *582 transmission capacity to allow them to generate all of the electricity that atmospheric conditions would permit. In addition to damages, the Wind Farms and TXUPM both sought declaratory relief with respect to the others’ obligations under certain contractual provisions.

After several partial summary judgment rulings and a jury trial on the remaining issues, the trial court rendered a final judgment that both TXUPM and the Wind Farms take nothing by their damage claims. The final judgment also included a declaratory judgment in favor of the Wind Farms. On appeal, TXUPM challenges the trial court’s take-nothing judgment on its breach of contract claim, the adverse declaratory judgment rulings, the trial court’s denial of its requested trial amendment, and the admission of certain testimony by an opposing expert witness. The Wind Farms filed a cross-appeal contesting the take-nothing judgment on their breach of contract claim and several of the trial court’s evidentiary rulings. For the reasons that follow, we affirm that part of the trial court’s judgment ordering the Wind Farms to take nothing on their claims for damages. We reverse and render judgment in favor of TXUPM on the construction of section 2.03 of the contracts and the enforceability of the liquidated damage clause. We reverse the remainder of the trial court’s judgment and remand the cause to the trial court for further proceedings.

I.

There are three basic components of the electric industry in Texas: power generation, power transmission, and power distribution. See Pub. Util. Com’n v. City Public Serv. Bd., 53 S.W.3d 310, 312 (Tex.2001). Generally, the transmission of electric energy is accomplished through an interconnected network of transmission systems and infrastructure owned and operated by various transmission service providers. This network forms a single grid managed by the Electric Reliability Council of Texas (ERCOT). 1 Every generating facility enters into an interconnection agreement with the transmission service provider that owns the lines to which the generating facility connects. When electricity is produced by a generating facility, it is transmitted to a point of interconnection with the ERCOT grid. From there, it is distributed along the high voltage transmission lines and lower voltage distribution lines to end users who purchase it from retail electric providers.

FPL Energy Pecos Wind I, FPL Energy Pecos Wind II, and Indian Mesa Wind Farm are wind-powered electrical generation facilities located in the McCamey area of West Texas. 2 Each facility executed a contract agreeing to sell to TXU Electric Company, a retail electric provider, annual minimum quantities of renewable energy credits along with the wind-generated electric energy that produced those credits. 3 At TXU Electric’s option, the term of the contracts could be extended through December 2019. TXUPM is the assignee of TXU Electric’s interest in the three contracts. TXUPM sued the Wind Farms for liquidated damages in the form of deficien *583 cy payments under the agreements after the Wind Farms failed to deliver the contractually-required annual minimum quantities of “renewable energy” beginning in 2002. 4 The Wind Farms countered that during the years relevant to this dispute, the McCamey area suffered from chronic transmission congestion because the transmission service providers serving the area failed to timely start and complete needed construction and upgrades of the transmission lines and facilities in and around the McCamey area. 5 This lack of transmission capacity in the McCamey area, in turn, resulted in ERCOT curtailment instructions to the Wind Farms for various periods. 6

The Wind Farms claimed the curtailment instructions „ prevented them from generating all of the energy that they were capable of producing and resulted in their failure to meet the minimum annual quantities required under the contracts. They further contended that TXUPM was required to ensure adequate transmission capacity as part of its contractual obligation to provide transmission services under section 2.03 of the contracts. 7 The Wind Farms argued TXUPM’s failure to do so was a material breach that not only excused their failure to deliver the annual minimum quantities but also entitled them to damages. TXUPM disputed the Wind Farms’ interpretation of section 2.03, arguing it had no obligation to ensure adequate transmission capacity under the plain language of the contracts.

The parties filed cross-motions for partial summary judgment with respect to the proper construction of section 2.03. The trial court granted the Wind Farms’ motion, declaring section 2.03 unambiguously required TXUPM to provide transmission capacity as part of its obligation to provide all services necessary to transmit energy from the Wind Farms to TXUPM’s customers. 8 Both parties then moved for a partial summary judgment with respect to the liquidated damage provision in the agreements. The Wind Farms argued that the $50 deficiency rate used to calculate the deficiency payments was void as an unenforceable penalty. TXUPM, on the other hand, argued that the deficiency rate was a valid measure of liquidated damages under which it was entitled to $25,948,250 for the Wind Farms’ failure to provide the minimum annual amounts of renewable energy from 2003 through *584 2005. 9 The trial court ruled the liquidated damage provision in the contracts was an unenforceable penalty and precluded TXUPM from presenting evidence of liquidated damages at trial. 10

At trial, the Wind Farms did not dispute their failure to provide the minimum annual quantities of renewable energy as alleged by TXUPM.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
328 S.W.3d 580, 2010 WL 2904628, Counsel Stack Legal Research, https://law.counselstack.com/opinion/txu-portfolio-management-co-v-fpl-energy-llc-texapp-2011.