Tveidt v. Zandstra Construction, Inc.

2007 SD 120, 742 N.W.2d 55, 2007 S.D. LEXIS 183, 2007 WL 3378443
CourtSouth Dakota Supreme Court
DecidedNovember 14, 2007
Docket24473
StatusPublished

This text of 2007 SD 120 (Tveidt v. Zandstra Construction, Inc.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tveidt v. Zandstra Construction, Inc., 2007 SD 120, 742 N.W.2d 55, 2007 S.D. LEXIS 183, 2007 WL 3378443 (S.D. 2007).

Opinion

MEIERHENRY, Justice.

[¶ 1.] Dewayne Tveidt (Tveidt), as Special Administrator for the Estate of Esther A. Tveidt, appeals a summary judgment order in favor of Zandstra Construction, Inc. (Zandstra). The dispute involved the interpretation of a contract entered into between the parties in conjunction with a South Dakota Department of Transportation (DOT) highway project. The project *57 involved construction of U.S. Highway 14A between Sturgis and Deadwood, South Dakota, and was referred to as the Boulder Canyon Project. DOT contracted with local ranchers and landowners, Esther and Lewis Tveidt, to use their land to dispose of excess embankment material (DOT-Tveidt Contract). Pursuant to the DOT-Tveidt Contract, DOT would be allowed to deposit 300,000 cubic yards of excess material on TVeidt’s property in return for compensation.

[¶ 2.] DOT also contracted with Zands-tra (DOT-Zandstra Contract) to serve as the general contractor on the Boulder Canyon Project. As part of the DOT-Zandstra Contract, Zandstra was required to install thousands of tons of riprap (large stones or chunks of concrete) along the banks of the Bear Butte Creek for erosion control. According to the undisputed facts, the DOT-Zandstra Contract incorporated the DOT-Tveidt Contract.

[¶ 3.] Zandstra contracted with Tveidt (Zandstra-Tveidt Contract) to pay them for a “return haul road” and to purchase “riprap produced on their property.” The Zandstra-Tveidt Contract permitted Zandstra to “[u]se an area on Tveidt’s property to screen and store riprap.... ” The conditions of the contract specified that Zandstra would compensate Tveidt in the amount of $30,000.00 for a return haul road and an additional $2.50 per ton of riprap “produced on [Tveidt’s] property.” In addition to this compensation, Zandstra was bound to “reseed and reclaim” the affected area and backfill a pipe installed by Tveidt.

[¶4.] Zandstra, as general contractor, was responsible for transporting the excess embankment, described in the DOT-Tveidt Contract, to Tveidt’s land. After transporting the excess embankment material to Tveidt’s land, Zandstra screened the embankment for riprap, setting any usable riprap to the side for eventual application to the project. Additionally, Zandstra unearthed riprap from Tveidt’s property, which also was screened and used on the project.

[¶ 5.] Upon completion of the Boulder Canyon Project, Zandstra had hauled a total of 56,931.10 tons of riprap from Tveidt’s property. This total represented riprap from two sources (1) riprap produced by screening the material unearthed from Tveidt’s property (9,948.34 tons) and (2) riprap produced by screening the excess embankment material that had been hauled onto Tveidt’s property pursuant to the DOT-Tveidt Contract (46,982.76 tons). Zandstra tendered payment for the 9,948.34 tons of riprap produced from material unearthed from Tveidt’s property. Tveidt subsequently commenced an action alleging that Zandstra had an obligation to pay for all of the riprap that it screened from the excess embankment material. The trial court granted Zandstra’s motion for summary judgment, finding that the Zandstra-Tveidt Contract only obligated Zandstra to pay for riprap unearthed from Tveidt’s property. Tveidt claims that the trial court erred.

[¶ 6.] Specifically, Tveidt contends that (1) they owned the excess embankment material from which 46,982.76 tons of the riprap were produced and (2) pursuant to the Zandstra-Tveidt Contract, Zandstra had an obligation to pay for the riprap that it produced from the excess embankment material. Since there are no material facts in dispute, our review is limited to whether the law was correctly applied. Kling v. Stern, 2007 SD 51, ¶5, 733 N.W.2d 615, 617.

[¶ 7.] The construction of a contract is a question of law which we review de novo. Id. As this is a matter of contract interpretation, the plain meaning of *58 the words of the contract will be given effect. In re Dissolution of Midnight Star Enterprises, L.P. ex rel. Midnight, 2006 SD 98, ¶ 12, 724 N.W.2d 834, 337. “An interpretation which gives a reasonable and effective meaning to all the terms is preferred to an interpretation which leaves a part unreasonable or of no effect.” Id. (quoting Nelson v. Schellpfeffer, 2003 SD 7, ¶ 14, 656 N.W.2d 740, 744 (citing Restatement (Second) Conteacts § 203(a) (1981))). When interpreting the contract, “[w]e must ‘give effect to the language of the entire contract and particular words and phrases are not interpreted in isolation.’ ” Id. (quoting Jones v. Siouxland Surgery, 2006 SD 97, ¶ 15, 724 N.W.2d 340, 345) (quoting Hartig Drug Co. v. Hartig, 602 N.W.2d 794, 797-98 (Iowa 1999))). The parties direct us to provisions in both the DOT-Tveidt Contract and the Tveidb-Zandstra Contract. Both contracts dealt with the same subject matter and when read together define the intent of the parties in relationship to the excess embankment material, the riprap and its production.

1. The DOT-Tveidt Contract

[¶8.] Tveidt claims that pursuant to the DOT-Tveidt Contract, the excess embankment material hauled on the property to be stored and screened became the personal property of Tveidt entitling the Estate to payment. As support, Tveidt cites to the absence of language in the DOT-Tveidt Contract suggesting that ownership of the excess embankment material would remain with DOT, and the absence of language that suggests that DOT would have the right to screen riprap from the excess embankment material. Tveidt claims that the contract only allowed DOT and its agents to have a right of ingress and egress for the purpose of depositing but not removing excess embankment materials.

[¶ 9.] Zandstra, on the other hand, argues that DOT only contracted with Tveidt for storage and waste of the excess embankment material. In support of its argument, Zandstra points to the absence of any language that suggests that the excess embankment material would become the property of Tveidt. Zandstra argues that the language of the contract implies that any excess waste material would not become property of Tveidt until the area was graded to specification, reseeded and re-fenced.

[¶ 10.] In order to resolve the issue of ownership, we look at the language of both the DOT-Tveidt Contract and the Zands-tra-Tveidt Contract, as both parties suggest. The DOT-Tveidt Contract is a five page document detailing the rights and responsibilities of DOT in regards to its use of Tveidt’s property. Among other things, the contract granted DOT a right of ingress and egress for the purpose of depositing excess embankment material and allowed for DOT’S continued use of Tveidt’ property until the Boulder Canyon Project was complete. The contract also required DOT to restore the property to its original condition after the project was completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nelson v. Schellpfeffer
2003 SD 7 (South Dakota Supreme Court, 2003)
Jones v. Siouxland Surgery Center Ltd. Partnership
2006 SD 97 (South Dakota Supreme Court, 2006)
In Re the Dissolution of Midnight Star Enterprises, L.P.
2006 SD 98 (South Dakota Supreme Court, 2006)
Kling v. Stern
2007 SD 51 (South Dakota Supreme Court, 2007)
Hayes v. Alaska Juneau Forest Industries, Inc.
748 P.2d 332 (Alaska Supreme Court, 1988)
Reed v. City of Omaha
724 N.W.2d 834 (Nebraska Court of Appeals, 2006)
Hartig Drug Co. v. Hartig
602 N.W.2d 794 (Supreme Court of Iowa, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
2007 SD 120, 742 N.W.2d 55, 2007 S.D. LEXIS 183, 2007 WL 3378443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tveidt-v-zandstra-construction-inc-sd-2007.